New Year Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free PSP Planning & Scheduling Professional (PSP) Exam Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the AACE International PSP Exam the most current and reliable questions . To help people study, we've made some of our Planning & Scheduling Professional (PSP) Exam exam materials available for free to everyone. You can take the Free PSP Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

What is the actual duration as of the status date or data date of Activity B?

PSP question answer

A.

7.

B.

3.

C.

0.

D.

4.

Question # 7

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

A.

Is a milestone.

B.

It is on the critical path.

C.

Was completed in the past.

D.

Has yet to be completed.

Question # 8

If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

A.

Finish-no-earlier constraint on the first activity

B.

Finish-no-earlier constraint on the last activity

C.

Finish-no-later constraint on the last activity

D.

Start-no-later constraint on the first activity

Question # 9

For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

PSP question answer

A.

LS.11001 + 25 days.

B.

02-19-04.

C.

EF.11001.

D.

EF.11001 + 1 day.

Question # 10

Project Life Cycle Phases do NOT include the following item:

A.

procurement

B.

budgeting

C.

design

D.

start-up

Question # 11

What does the heavy, vertical line at "X" represent?

PSP question answer

A.

Delay fault line.

B.

The status or data date.

C.

Change-over limits.

D.

International Date Line.

Question # 12

What was the original planned duration for Activity A through Activity G?

PSP question answer

A.

26.

B.

28.

C.

24.

D.

25.

Question # 13

Determine the correct formula and date for the late start for the Activity 11001:

PSP question answer

A.

LF of 11001 less 27 days plus 1 day equaling 14 Jan 2024

B.

LF of 1000 less 25 days equaling 16 Jan 2024

C.

LF of 11001 less duration of 11001 equaling 16 Jan 2024

D.

LF of 11001 less 25 days plus 1 day equaling 16 Jan 2024

Question # 14

STION NO: 146

Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

A.

6001, 8001, 9001. 9002, 9004. 9005

B.

7001, 8001, 9001. 9003. 9004. 10002

C.

5001,7001.8001,9001,9004,9005

D.

2003,8001.9001.9002,9005,10001

Question # 15

Who can define KPls?

A.

The client and the performing/contracting entity

B.

Environmental regulators

C.

The subcontractors and suppliers

D.

Accounting and Finance

Question # 16

The BEST reason to use multiple calendars is to:

A.

more accurately show how the project will be built

B.

allow each specialty contractor to have a unique schedule of work/non-work periods

C.

track owner activities according to their specific calendar in order to develop a good

working relationship

D.

evaluate float for the benefit of the contractor

Question # 17

Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

A.

Non-excusable delay

B.

Compensable delay

C.

Non-compensable delay

D.

Excusable delay

Question # 18

Why does activity 1001 have two successor activities?

PSP question answer

A.

Because the late finish of 1001 and the late start of 7001 require two successors

B.

Because the problem could not effectively work with only one successor

C.

Because there are two defined logic paths for the work

D.

Because the duration of activities 2001, 2002 and 200.f require two successors

Question # 19

What does the narrow band at "Y" represent?

A.

Resource limitation period

B.

A delaying event

C.

You cannot tell with the information supplied

D.

A rework period

Question # 20

When should the project documents be reviewed to assess their impact on the organization and administration of a project?

A.

After the Award and before the NTP

B.

During the Bid Phase

C.

Before the commercial decision to Did on the project

D.

After the NTP

Question # 21

Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

PSP question answer

A.

After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.

B.

After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

C.

After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

Question # 22

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

A.

15 days.

B.

0 days.

C.

5 days.

D.

10 days.

Question # 23

If Activity E's duration changes to 4 months, what is the overall duration of the project.

PSP question answer

A.

19 months.

B.

20 months.

C.

22 months.

D.

21 months.

Question # 24

: 20

Constraints control events or activities that __________________.

A.

Affect only the forward pass.

B.

Are not based on project relationships.

C.

Affect only the backward pass.

D.

May be over-ridden by activity logic.

Question # 25

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

PSP question answer

A.

2 cranes

B.

1 crane

C.

4 cranes

D.

3 cranes

Question # 26

What are Phases based on and derived from?

A.

Resources

B.

Constructability

C.

Score of Work

D.

Budget

Question # 27

Which of the following are NOT normally included in the project scope statement, either directly or by reference?

A.

Project objectives in terms of cost, schedule and quality measures

B.

Project contract between the contractor and owner

C.

Project justification

D.

Project deliverables

Question # 28

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

PSP question answer

A.

09-28-01.

B.

09-08-01.

C.

09-15-01.

D.

09-18-01.

Question # 29

What is the free float for Activity F?

PSP question answer

A.

3 months.

B.

0months.

C.

1months.

D.

2month.

Question # 30

Identify the minimum project duration.

PSP question answer

A.

20 months.

B.

16 months.

C.

19 months.

D.

21 months.

Question # 31

The best source of project risk or opportunities is:

A.

A similar project in another state

B.

Rumors from the local Chamber of Commerce

C.

Failures by other contractors

D.

Internal and external stakeholders

Question # 32

All the following describe the critical path of a schedule EXCEPT:

A.

Determined by network logic and is the chain of activities that controls the overall project completion time.

B.

Frequently defined as the shortest path through the schedule.

C.

Changed by redefining the network logic or changing activity durations or both.

D.

The series of activities having the least amount of total float.

Question # 33

Baseline schedule can be submitted only__________.

A.

at the beginning or the construction

B.

once the project gets impacted try change

C.

once the design for the construction gets approved

D.

once the safety quality and insurance requirements are met

Question # 34

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.

The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?

A.

The duration for drywall installation should De proportional to how critical the activity is

B.

Review the drywall quantity, methods and location with the project superintendent to determine a reasonable duration

C.

Review the location of drywall work in the contract drawings

D.

Divide the quantity of drywall by the construction crew's dairy production rate for this work

Question # 35

By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:

A.

Acceleration.

B.

Production output.

C.

Productivity loss.

D.

Productivity efficiency.

Question # 36

Using the normal schedule, what is the early finish date and total float of Activity 10002?

A.

24 Nov 2023. and 24 days of tree float

B.

24 Dec 2023. and 24 days of tree float

C.

17 Dec 2023. and 4 days of total float

D.

21 Dec 2023. and 4 days of total float

Question # 37

Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

PSP question answer

A.

Drafting and Proofing the Manual.

B.

Packaging only.

C.

Printing the Manual.

D.

Testing, Manufacturing and Packaging.

Question # 38

How many entities/subcontractors should a scheduled activity cover?

A.

More than one it the activity is in a single calendar period

B.

More than one it the subcontractors agree

C.

Only one

D.

More than one if the concurrent work cannot be split between subcontractors

Question # 39

What changes to logic would eliminate Activity B from the critical path?

A.

Replace the relationship from Activity B to Activity C with SSO

B.

Reduce the lag value of the relationship from Activity A to Activity B from 5 to 0

C.

Add a SS 15 relationship from Activity A to Activity B and replace the relationship from Activity A to Activity B with FFO

D.

Replace the relationship from Activity A to Activity B with FFO and add an FSO relationship from Activity A to Activity C

Question # 40

Which of the following is NOT required when initially planning a project?

A.

Resource Identification and leveling.

B.

The duration of each task.

C.

A schedule that identifies tasks required on a project.

D.

Logical relationships between the tasks.

Question # 41

Which of the following will always describe the critical path? The path with

A.

The longest duration through the network.

B.

Zero float.

C.

Negative float.

D.

The shortest duration and negative float.

Question # 42

When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?

A.

The activity with the highest sensitivity.

B.

The activity with the longest duration.

C.

The activity with the lowest total float value.

D.

The activity with the highest resource loading.

Question # 43

NO: 98

The activity with the most total float is:

PSP question answer

A.

Activity I.

B.

Activity C.

C.

Activity F.

D.

Activity D.

Question # 44

What does the narrow band at "Y" represent?

PSP question answer

A.

Resource limitation period.

B.

A rework period.

C.

Activity inactivity.

D.

You cannot tell with the information supplied.

Question # 45

Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?

A.

to highlight a time when there are more holidays and work therefore will be slower and there will be more absenteeism

B.

to denote a time during which work may not progress as fast as planned and cost and risk may be elevated

C.

to provide a key to co-a weather for safety meetings

D.

to show a difference in the calendar year

Question # 46

Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

A.

407 days

B.

255 days

C.

267 days

D.

477 days

Question # 47

Constructability is NOT intended to:

A.

optimize engineering and procurement

B.

correct deficiencies in the project design

C.

balance project and environment goals

D.

integrate construction knowledge into the design

Question # 48

Which of the following is NOT required when performing weekly or monthly schedule updates?

A.

Percent complete.

B.

Remaining duration of activities.

C.

Actual finish of activities.

D.

Original duration of activities.

Question # 49

When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

A.

Detailed listing of working days for each calendar used

B.

Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

C.

Assigned party responsibility for each work task

D.

Tabular listing of activities showing duration, calendar ID, early and late dates

Question # 50

In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

A.

4001, 5001, and 6001

B.

2003 and 7001

C.

4001 and 5001

D.

2004, 4001. and 5001

Question # 51

Determine the correct formula and date for the late finish for Activity 9004.

PSP question answer

A.

LS.10002 + 1 day -> 11-29-03.

B.

LS.10002^ Lag.7 + i day -> 11-20-03.

C.

LS.10002 - 1 day -> 11-27-03.

D.

LS.10002 - Lag.7 - l day -> 11-20-03.

Question # 52

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?

A.

3 workdays

B.

18 workdays

C.

8 workdays

D.

7 workdays

Question # 53

When are KPIs defined?

A.

At project initiation

B.

At NTP

C.

At the start of the Construction Phase

D.

After the Bidding Phase

Question # 54

Estimate to complete (ETC) is __________________.

A.

The expected remaining cost needed to complete an activity, group of activities or the project

B.

The costs actually incurred in accomplishing the work performed

C.

The expected total cost of an activity, group of activities or the project

D.

The value of the completed work expressed in terms of the budget assigned to that work

Question # 55

At a minimum, periodic reporting must be done at what interval?

A.

Monthly.

B.

As requested by the project manager.

C.

As requested by the owner.

D.

As specified in the contract documents.

Question # 56

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

A.

Negative float.

B.

Free float.

C.

Total float.

D.

Interfering float.

Question # 57

A KPI is an acronym for:

A.

Key Planning Index

B.

Known Planning Impediments

C.

Keep Parameter Integrity

D.

Key Performance Indicator

Question # 58

The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?

A.

263 CY

B.

368 CM

C.

201 CY

D.

306 CY

Question # 59

As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

PSP question answer

A.

A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001

B.

A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity 6002.

C.

A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

D.

A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002

Question # 60

Should activities be coded with the EBS value?

A.

Yes. the project coding should roll up to EBS values

B.

No. only a few EBS values exist at the activity level

C.

No. the EBS Is much higher than activity coding

D.

Yes. the EBS is the most important project coding level

Question # 61

Which of the following is NOT true?

A.

Remaining durations can exceed original durations.

B.

Constraints can interfere with the longest path calculation.

C.

Multiple calendars can affect the total float calculation.

D.

A network must contain only one Critical Path.

Question # 62

What owner action could have mitigated the late completion of the project?

A.

Hire a more senior project manager.

B.

Self-perform more of the work.

C.

Use a procurement agent to monitor and expedite equipment deliveries.

D.

Prepare better structural steel drawings.

Question # 63

Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

PSP question answer

A.

36 lifts

B.

24 lifts

C.

30 lifts

D.

48 lifts

Question # 64

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:

A.

ahead of schedule

B.

on schedule

C.

complete

D.

behind schedule

PSP PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PSP PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Planning & Scheduling Professional (PSP) Exam
  • Last Update: Dec 15, 2025
  • Questions and Answers: 216
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PSP Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included