  • Exam Name: Agile Project Management (AgilePM) Foundation Exam
  • Last Update: Oct 8, 2024
  • Questions and Answers: 50
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

AgilePM-Foundation Engine

$46.2

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

AgilePM-Foundation Practice Exam Questions with Answers Agile Project Management (AgilePM) Foundation Exam Certification

Question # 6

Which of the following is a DSMD principle?

A.

Build incrementally from firm foundations

B.

Build incrementally from Feasibility onwards

C.

Build incrementally in Timeboxes

D.

Build incrementally

Full Access
Question # 7

How are the business roles critical to the success of a DSDM project?

A.

Guide the evolution of the solution at the detailed level

B.

Make all decisions

C.

Provide formal progress reporting

D.

Lead Solution Developer demonstrations

Full Access
Question # 8

Which of the following support the DSDM philosophy and principles?

A.

Process, people, products and practices

B.

People, products, phase and plans

C.

Plans, projects, process and people

D.

Phases, productivity, power and process

Full Access
Question # 9

Which purpose relates to the instrumental Success Factors?

A.

Underpins the prioritization of requirements

B.

Informs the development of the Business Case

C.

Positions DSDM projects for a successful outcome

D.

Inform the development of the Terms of Reference

Full Access
Question # 10

Which purpose relates to the Consolidation in a structured Timebox?

A.

To confirm the detail of all the requirements to be delivered by the structured Timebox.

B.

To address the requirements and test the structure Timebox product.

C.

To formality accept the structured Timebox deliverables.

D.

To tie up any loose ends related to Evolutionary Development

Full Access
Question # 11

When is a Timebox Plan updated?

A.

At the Daily Start-ups

B.

At Timebox Kick-ups

C.

As needed by the Project Manager

D.

Each time a Timebox is completed

Full Access
Question # 12

What role is responsible for the delivery of the project from Foundations through to Deployment?

A.

Business Sponsor

B.

Business Visionary

C.

Project manager

D.

Technical Coordinator

Full Access
Question # 13

What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?

A.

Business Analyst

B.

Workshop Facilitator

C.

Business Ambassador

D.

Business Visionary

Full Access
Question # 14

During what phase should a baseline of the Evolving Solution be put into operational use?

A.

Foundations

B.

Evolutionary Development

C.

Deployment

D.

Post-Project

Full Access
Question # 15

When initially creating MoSCoW priorities, what is the primary focus?

A.

Project priorities

B.

Project increment priorities

C.

Timebox priorities

D.

Iterative Development priorities