What is the actual duration as of the status date or data date of Activity B?

If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

Determine the correct formula and date for the late start for the Activity 11001:

STION NO: 146
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
When should the project documents be reviewed to assess their impact on the organization and administration of a project?
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
If Activity E's duration changes to 4 months, what is the overall duration of the project.

There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

Which of the following are NOT normally included in the project scope statement, either directly or by reference?
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?

Scenario: You are providing construction management services for a small office building project. Your duties include reviewing and approving the contractor's baseline schedule. The contractor has submitted the first baseline schedule for the project.
The contractor subsequently submits a CPM schedule for its baseline schedule submittal. As part of your review, you look at the durations for each activity in the schedule. How do you determine if a duration of 10 work days for drywall installation is accurate?
By subtracting a measured unit productivity rate during an impacted period from the unit productivity rate during an unimpacted period, the resulting value represents:
Using the normal schedule, what is the early finish date and total float of Activity 10002?
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

Which of the following will always describe the critical path? The path with
When a fragnet of activities represents a known schedule risk, which activity will most likely change the overall outcome?
Select the most appropriate explanation for use of a winter/wet weather seasonal calendar for use in this project?
Using the normal schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Which of the following is NOT required when performing weekly or monthly schedule updates?
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?
Determine the correct formula and date for the late finish for Activity 9004.

Using one crane capable of 30 lifts per day. for 3 column pours requiring 28 lifts each, plus assorted work in the area requiring an additional 150 lifts, what are the lowest planned workdays for this work?
The amount of time that an activity can be delayed from its early start date without delaying project completion is called:
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

What owner action could have mitigated the late completion of the project?
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

In an earned value-based system, a schedule performance index of less than one for the project indicates the project is: