Pre-Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free AD0-E911 Adobe Workfront Project Manager Certified Professional Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the Adobe AD0-E911 Exam the most current and reliable questions . To help people study, we've made some of our Adobe Workfront Project Manager Certified Professional exam materials available for free to everyone. You can take the Free AD0-E911 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

Which group of project elements can be used to monitor an active project’s progress?

A.

Gantt chart, project Condition, and Metrics

B.

Risks, planned hours, and resource utilization

C.

Project status, Updates, and Sharing

Question # 7

A project manager would like to see the Budgeted Variances between the hours for the current week. Where is that information found at the project level?

A.

Utilization section

B.

Hours tab

C.

Finance section

Question # 8

Task 2 has a 5-day duration, is tied to Task 1 with a predecessor, and is expected to begin once Task 1 is completed. Due to a resource availability conflict, Task 1 was rescheduled to start 1 week later. Once Task 1 was rescheduled, the planned start date on Task 2 did not dynamically shift by 5 days as expected but instead remained the same planned start date that existed before the change to Task 1.

What may have caused the planned start date of Task 2 to remain the same?

A.

The primary assignee had already submitted a Commit Date for the previous planned start date on Task 2, even though the project owner did not accept this Commit Date, the project plan made this date a Must Start On Constraint on Task 2.

B.

The project owner has at some point made a manual change to the planned start date of Task 2, which has in turn changed the Task Constraint of Task 2 to Must Start On.

C.

The primary assignee had scheduled time off during the new planned start date that Task 2 should have shifted toward. Due to this time off scheduled the date remained the same.

D.

The project owner has at some point made a manual change to the Task Constraint of Task 2 to As Soon As Possible, which has forced the date of Task 2 to be static.

Question # 9

What occurs when an individual enters a new commit date that is after the original planned date of a task?

A.

The assignee of any task that has the original task set as a predecessor is notified.

B.

The Project Owner is notified whether this change will impact the Project Timeline.

C.

The Planned Completion Date of the task automatically changes to match the new Commit Date.

Question # 10

Task 1 on Project 1 can only be started once the final milestone on Project 2 is completed.

How can the project manager configure this relationship?

A.

Add a cross-project predecessor on the final milestone of Project 1.

B.

Add a cross-project predecessor on Task 1 in Project 1.

C.

Add a cross-project predecessor on the final milestone in Project 2.

Question # 11

The art director is reviewing and approving a proof and has requested that they only get email notifications for a new proof or version. What Email alert option should be assigned to them on the workflow?

A.

Decisions and Notify recipients about this proof is selected

B.

Disabled and Notify recipients about this proof is selected

C.

Decisions and Notify recipients about this proof is not selected

D.

Disabled and Notify recipients about this proof is not selected

Question # 12

An organization has created unique data fields relevant to their projects. Starting by navigating from a project ' s landing page, where is this data found?

A.

Project Details > Custom Forms

B.

Project Details > Overview

C.

Business Case > Project Info

Question # 13

Which date type on tasks can a project manager manually modify?

A.

Planned

B.

Estimated

C.

Projected

Question # 14

A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?

A.

Actual Completion Date

B.

Progress Status

C.

Status

Question # 15

Which Workfront collection of users allows a task or issue to be assigned to multiple people?

A.

Team

B.

Group

C.

Project Team

Question # 16

A team wants to combine structured project planning with the flexibility to manage tasks in sprints.

Which Workfront methodology allows for this hybrid approach?

A.

Scrum

B.

Waterfall

C.

Kanban

Question # 17

How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

A.

Visit the Dashboard page, create a new Issue report, and update the Issue Owner ID filter with their name, and group by project name.

B.

Visit the Reports page, create a new Project report, update the Project Owner ID filter with their name, and add a column for issues.

C.

Visit the Reports page, create a new Issue report, update the Project Owner ID filter with their name, and group by project name.

Question # 18

A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

A.

Visit the Dashboards page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects.

B.

Visit the Projects page and create a Milestone Path report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

C.

Visit the Reports page and create a Project report. In the filter, update the Portfolio Owner ID to the Portfolio Owner’s name and update the Project Status to exclude complete projects. In Report Options, select " Show the Milestone view on the Details tab. "

Question # 19

A user wants to know if a task is pending approval.

Which task field would the user review?

A.

Status

B.

Critical Path

C.

Priority

Question # 20

A project manager is looking to create a task that must take place from September 10th through September 17th of this year.

Which action must be taken?

A.

Set the Task Constraint to Fixed Dates.

B.

Set a Predecessor for the task.

C.

Set the Duration of One week.

Question # 21

A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.

Which date type would the project manager utilize?

A.

Estimated Date

B.

Projected Date

C.

Planned Date

Question # 22

A project manager has set up and launched a new project for an annual marketing campaign.

Where can the project team locate their work requests?

A.

Email, Workfront Home, Project tasks list

B.

Email, Automatic Reminders, Workfront Home

C.

Event Notifications, Approval processes, Email

Question # 23

AD0-E911 question answer

What do the connector lines between tasks in a Gantt chart represent?

A.

Critical path

B.

Multiple assignments

C.

Predecessor relationship

Question # 24

A portfolio manager has inadvertently given too much access to all the projects in their portfolio to Program Manager A.

How does the portfolio manager rectify the situation to ensure that Program Manager A has Manage access only on their own program?

A.

Share the program with Program Manager A with Manage access and ensure the system administrator adjusts Program Manager A ' s access level.

B.

Share the program with Program Manager A with Manage access and ensure Program Manager A understands they cannot manage the rest of the portfolio.

C.

Share the program with Program Manager A with Manage access and remove Program Manager A ' s Manage access on the portfolio.

Question # 25

A team member has five days to complete a critical path task, and the task requires only one hour. Today is the fourth day in the timeframe, and the team member has not yet worked on it.

What impact does this have on the project progress status?

A.

The next team member cannot start his task.

B.

No impact as the task is not overdue.

C.

The project shows an At Risk automatic condition.

Question # 26

A project manager needs to locate the fixed revenue and costs of a project. Where should the project manager look to find this information?

A.

Business Case

B.

Billing Records

C.

Project Details

Question # 27

An IT department needs to see the Group and Portfolio of each of its projects for reporting purposes.

In which project area does this information reside?

A.

Queue Details

B.

Project Details

C.

Metrics

Question # 28

A company has decided that all projects for the year need to be created from templates and staffed in the following quarter. The projects will need to remain in a backlog until the team has capacity to work on them. There has been confusion previously because the team used Planning status for all work not started.

What should the project manager do to help the team see the difference between work in the backlog versus work that is now being planned?

A.

Load the project template once the team has bandwidth to start on the project.

B.

Create projects but leave the roles in place without assigning users.

C.

Create a custom status for Backlog to use prior to using the Planning status.

AD0-E911 PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

AD0-E911 PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Adobe Workfront Project Manager Certified Professional
  • Last Update: May 10, 2026
  • Questions and Answers: 95
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

AD0-E911 Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included