Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free BIM_MGT_101 Autodesk Certified Professional in BIM Management for Building Design Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the Autodesk BIM_MGT_101 Exam the most current and reliable questions . To help people study, we've made some of our Autodesk Certified Professional in BIM Management for Building Design exam materials available for free to everyone. You can take the Free BIM_MGT_101 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.

Which two components should the template include to accomplish the goal? (Select two.)

A.

Common Data Environment.

B.

Contract template.

C.

Roles and responsibilities.

D.

Specifications.

E.

Project milestone dates.

Question # 7

During a model review, several linked files appear missing or unloadable in the federated coordination file. The files were present and working the day before, and no changes were made to the Revit host model itself.

As the BIM manager, what is the most appropriate step to troubleshoot the issue?

A.

Check that file paths to linked models were set as relative and validate that the folder structure remains unchanged.

B.

Ask the modelling team to rebind all linked models using absolute file paths.

C.

Remove the missing links and advise each team to reinsert their models before the next coordination meeting.

D.

Recreate the host model using a previous backup and manually reload each link.

Question # 8

The BIM manager oversees both design coordination and post-handover data requirements and is asked to ensure the digital deliverables align with the owner’s long-term asset-management system.

To minimize information gaps, inconsistencies in file formats, and unclear responsibilities throughout delivery, which tool should the BIM manager rely on to define who provides what information, when, and in what format, from design through facilities handover?

Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

A.

The file-naming protocol and model-authoring standards.

B.

The Quantity Takeoff Checklist and/or the BIM Execution Plan.

C.

The Model Element Table and Level of Development (LOD) matrix.

D.

The Master Information Delivery Plan (MIDP) and/or the BIM Execution Plan.

Question # 9

The BIM manager has finalized the BIM Execution Plan (BEP) for a multi-discipline educational facility project. Some consultants have already begun modelling, while others are onboarding late. A few external stakeholders are not listed in the original BEP distribution but will need access to coordinated models during design and preconstruction.

What two actions could be taken in order to manage distribution of updates? (Select two.)

A.

Update and reissue the BEP only to the consultants who have not yet started modelling to ensure they catch up to project standards.

B.

Formally distribute the BEP to all relevant parties as an addendum to the contract.

C.

Formally distribute the BEP to all relevant parties and confirm receipt to ensure alignment on roles, responsibilities, and agreed BIM processes.

D.

Upload the BEP in a shared Autodesk Forma Data Management folder to ensure version tracking and verify access to stakeholders.

E.

Wait until construction coordination begins before sharing the BEP with external stakeholders.

Question # 10

The BIM manager is working in an Architectural model that uses the phases Existing and New Construction . They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.

Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?

A.

Apply a phase-filter override to the linked model using Visibility/Graphics settings.

B.

Open the linked model and manually change its phase names to match the host model.

C.

Map the linked model’s phases to the host model’s phases in the Revit Link properties.

D.

Override the linked view’s phase settings using view templates in the host model.

Question # 11

During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.

Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)

A.

Email PDFs to the contractor every week.

B.

Update Publish Settings to include sheets.

C.

Create blank sheets for all disciplines.

D.

Enable Model Coordination.

E.

Schedule Publishes in Design Collaboration.

Question # 12

During a coordination meeting, project leads ask for a report showing only active clashes between mechanical systems and structural framing in patient-room zones, following the approved clash matrix.

What is the most effective way to provide this report using Model Coordination?

A.

Create a custom View from the published models, then export the filtered clash-list results.

B.

Ask each discipline to review its own clash results and report any critical issues from its perspective.

C.

Export all clash results to a spreadsheet and manually filter by trade and zone.

D.

Assign all relevant clashes to mechanical and structural teams using the Issues tool.

Question # 13

Refer to the exhibits.

BIM_MGT_101 question answer

BIM_MGT_101 question answer

BIM_MGT_101 question answer

BIM_MGT_101 question answer

The firm’s technical group would like to show demolished elements as dashed red in all future projects. The BIM manager is updating the Revit template to meet this new standard.

Which Phase Graphic Override will accomplish this?

BIM_MGT_101 question answer

BIM_MGT_101 question answer

BIM_MGT_101 question answer

BIM_MGT_101 question answer

A.

Exhibit 4

B.

Exhibit 2

C.

Exhibit 1

D.

Exhibit 3

Question # 14

A team member accidentally unpinned and dragged a linked CAD file, and it is no longer aligned according to the Shared Coordinates.

How can the BIM manager realign the linked CAD file in the Revit model?

A.

Publish the Coordinates from the host model to the linked CAD file.

B.

Select the linked CAD file and use the Move command to realign the link.

C.

Select the Shared Site of the linked CAD file and move the instance to the defined Site.

D.

Ask the consultant to update the CAD file and relink it.

Question # 15

The BIM manager is launching a civic center project with strict sustainability and lifecycle data goals. During early planning, each discipline proposes different modelling approaches, and there is concern that downstream data handoff may be inconsistent.

To establish BIM goals and uses that ensure alignment from design through operations, what should the BIM manager do first?

Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.

A.

Ask each team to submit its standard BEPs for review and consolidate them into one reference document.

B.

Finalize the LOD matrix and data drops based on similar past projects, updating it during the design process as needed.

C.

Begin developing the internal BIM templates and content, assuming they will be applicable to this project.

D.

Host a stakeholder session to review the project-specific requirements and BIM uses, and establish mobilization needs and modelling requirements.

Question # 16

During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.

What is the most likely root cause of the model performance degradation?

A.

A rise in geometry complexity.

B.

An accumulation of audit history and backup data.

C.

The presence of imported Civil CAD files.

D.

The increase in model warnings.

Question # 17

A Revit model in Autodesk Forma that does not have any consultant links is opening for all team members except one. The project BIM manager has already audited and compacted the model.

What should the BIM manager do so that the team member can open the model?

A.

Clear the user’s collaboration cache files and retry again.

B.

Agree to a user request for a hardware upgrade.

C.

Roll back the model to a previous version.

D.

Publish the model to Autodesk Forma and ask the user to retry again.

BIM_MGT_101 PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

BIM_MGT_101 PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Autodesk Certified Professional in BIM Management for Building Design
  • Last Update: Jul 12, 2026
  • Questions and Answers: 57
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

BIM_MGT_101 Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included