We at Crack4sure are committed to giving students who are preparing for the Autodesk BIM_MGT_101 Exam the most current and reliable questions . To help people study, we've made some of our Autodesk Certified Professional in BIM Management for Building Design exam materials available for free to everyone. You can take the Free BIM_MGT_101 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
A BIM manager is creating a firm-wide template for mobilization plans to outline the key steps, resources, and strategies required to set up and launch BIM operations at the beginning of projects.
Which two components should the template include to accomplish the goal? (Select two.)
During a model review, several linked files appear missing or unloadable in the federated coordination file. The files were present and working the day before, and no changes were made to the Revit host model itself.
As the BIM manager, what is the most appropriate step to troubleshoot the issue?
The BIM manager oversees both design coordination and post-handover data requirements and is asked to ensure the digital deliverables align with the owner’s long-term asset-management system.
To minimize information gaps, inconsistencies in file formats, and unclear responsibilities throughout delivery, which tool should the BIM manager rely on to define who provides what information, when, and in what format, from design through facilities handover?
Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.
The BIM manager has finalized the BIM Execution Plan (BEP) for a multi-discipline educational facility project. Some consultants have already begun modelling, while others are onboarding late. A few external stakeholders are not listed in the original BEP distribution but will need access to coordinated models during design and preconstruction.
What two actions could be taken in order to manage distribution of updates? (Select two.)
The BIM manager is working in an Architectural model that uses the phases Existing and New Construction . They have linked in a Structural model that uses only Phase 1 for existing and Phase 2 for new construction. After linking, they notice that demolition elements from the Structural model do not display correctly in the demolition views.
Which approach allows the BIM manager to display linked elements correctly based on this phase setup, without changing the phases in the linked model?
During an initial coordination meeting, the team agreed that the contractor will be able to mark up the latest model and sheets in Autodesk Forma every week.
Which two actions should the BIM Manager take to ensure this is implemented correctly? (Select two.)
During a coordination meeting, project leads ask for a report showing only active clashes between mechanical systems and structural framing in patient-room zones, following the approved clash matrix.
What is the most effective way to provide this report using Model Coordination?
Refer to the exhibits.




The firm’s technical group would like to show demolished elements as dashed red in all future projects. The BIM manager is updating the Revit template to meet this new standard.
Which Phase Graphic Override will accomplish this?




A team member accidentally unpinned and dragged a linked CAD file, and it is no longer aligned according to the Shared Coordinates.
How can the BIM manager realign the linked CAD file in the Revit model?
The BIM manager is launching a civic center project with strict sustainability and lifecycle data goals. During early planning, each discipline proposes different modelling approaches, and there is concern that downstream data handoff may be inconsistent.
To establish BIM goals and uses that ensure alignment from design through operations, what should the BIM manager do first?
Note: In the context of this exam, the term Level of Development (LOD) is used interchangeably with level of information need.
During a weekly BIM health review, the BIM manager compares two versions of the same architectural Revit model submitted one month apart. The newer model’s file size has doubled, synchronization time has increased by 40%, and users report sluggish performance. A model audit reveals no major geometry changes, but warnings have increased from 600 to 750, and several Civil CAD files are now imported.
What is the most likely root cause of the model performance degradation?
A Revit model in Autodesk Forma that does not have any consultant links is opening for all team members except one. The project BIM manager has already audited and compacted the model.
What should the BIM manager do so that the team member can open the model?
3 Months Free Update
3 Months Free Update
3 Months Free Update