3 Months Free Update
3 Months Free Update
3 Months Free Update
Where would an ICT distribution designer working for a company responding to a RFP expect to find requirements concerning alternative dispute resolution in the scope of work (SOW)?
In a budding with one join room for serving as the FR and EF and four dedicated TRs on the same floor a total of__________ 103 mm (4 trade size) conduits should be installed to interconnect the backbone pathways to the ER.
After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?
An RFQ usually provides more detail than RFP in selecting material such as:
To properly size and provide accurate cost estimates for a communications distribution horizontal pathway that will include BAS system infrastructure, the designer should provide ________ for every BAS outlet or device based on total floor area.
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
In a PON deployment, which active device is installed at the work area?
Wireless access point
Identify the core switch(es) and server(s) of the data center in the diagram below by dragging the appropriate term into each box in the diagram.
What would prevent a program manager from completing program closure once a program has been completed?
The options for termination an unshielded twisted pair cable for a video surveillance camera at the camera end are an 8-pin 8 conductor outlet and
A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component protect requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process.
What is a critical component of the Program Schedule Management Process?
A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the protects several mandatory changes are identified that would extend the program's completion date
What is the next step for the program manager?
Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)
During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?
A program is completed and the expected benefits are realized Before executing the transition and closing of the program, what should the program manager do?
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress"?
The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system. What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?
A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program
Would this be an acceptable funding arrangement?
You are designing distribution for a seven unit townhouse with in slab conduits. What is the MINIMUM number of 27 mm (1 in) rigid PVC Type 2 or metallic conduit that is required to satisfy distribution to each unit?
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next"?
The program selection committee presents several programs for approval:
Which program was selected based solely on a three-year return on investment?
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals A materials supplier informs the program manager that when this agreement is finalized, it will shorten the products delivery time.
What should the program manager update first?
In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?
Telecommunications cabling (e.g., voice, data, video, security, audio, control) can be damaged during the construction phases of rough-in, drywall installation, and during the siding of the exterior. For these reasons, telecommunications cabling shall be acceptance tested. Acceptance testing includes visual examination and verification of all cabling and qualification of copper cabling for data cabling or certification of copper or optical fiber cabling for data cabling. Verification testing is generally performed in which two of the following steps? (Choose two.)
A program to implement a company's new system is nearing completion and the program manager attempts to close the program However, despite training provided to the operational staff on the new system, there is concern that the defined expected benefits will not be fully realized.
To prevent this concern in the future, which of the following should occur?
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design. Which of the following information about the site shall be included?
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end What should be completed first to close all appropriate contracts?
Close out documentation is initially discussed in which of the following meetings?
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff
What should the program manager do to ensure communications on the component projects are consistent?
While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?
A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.
Which of the following deliverables captures these items?
Program manager B leaves the program and program manager A takes over the program responsibilities Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?
What's the RECOMMENDED twisted pair cable slack length to be left at the work area outlet location to enable the possibility of future changes in the Horizontal Cabling System?
The above performance report shows the earned value (EV) analysis for a program The program director performs a high-level analysis and must present a summary narrative to the steering committee
What do the current findings show?