Summer Special - 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: c4sdisc65

IDPX PDF

$38.5

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

IDPX PDF + Testing Engine

$61.6

$175.99

3 Months Free Update

  • Exam Name: Interior Design Professional Exam
  • Last Update: Sep 12, 2025
  • Questions and Answers: 175
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

IDPX Engine

$46.2

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

IDPX Practice Exam Questions with Answers Interior Design Professional Exam Certification

Question # 6

The PRIMARY reason for the submittal process during Contract Administration is for the designer to

A.

Confirm the quantity of material to be ordered

B.

Alter product specifications prior to the final order

C.

Check for conformance with the contract documents

D.

Verify that the dimensions conform to the site conditions

Full Access
Question # 7

Which consultant should be contacted to correct omissions on the drawing shown below?

IDPX question answer

A.

Electrical

B.

Plumbing

C.

Structural

D.

Fire protection

Full Access
Question # 8

Which of the following installations would require a structural engineer to be involved?

A.

A wall-mounted furniture workstation

B.

A demountable partition wall

C.

A non-load-bearing interior wall

D.

An operable partition wall

Full Access
Question # 9

What is the MINIMUM aisle width in retail areas conforming to universal accessibility standards?

A.

32" [813 mm]

B.

36" [914 mm]

C.

42" [1067 mm]

D.

48" [1219 mm]

Full Access
Question # 10

When does a project team gather information about a company’s culture, mission, values, and business goals to understand possible challenges for a new workplace environment?

A.

programming

B.

client interview

C.

schematic design

D.

design development

Full Access
Question # 11

Why is corrective work completed post-occupancy often MORE costly for the contractor?

A.

The warranty has expired

B.

Progress payments are not included

C.

The work must be performed after hours

D.

Revisions are billed on a cost-plus basis

Full Access
Question # 12

In which type of space would occupant load be calculated using net square footage?

A.

exercise room

B.

airport terminal

C.

museum exhibit

Full Access
Question # 13

During a substantial completion walk-through, a designer notices that a door was installed incorrectly. What should the designer do NEXT?

A.

Meet with the general contractor, review the drawings, and schedule replacement

B.

Process a change order and include the new door location

C.

Add the door location and problem to the punch (deficiency) list

D.

Ask the client to accept the door, with a credit memo

Full Access
Question # 14

A designer is working on a joint venture project with a local engineering firm for a large university project. What drawing system will BEST incorporate coordination of project information?

A.

Facility condition index (FCI)

B.

Building information modeling (BIM)

C.

Project life cycle management (PLM)

D.

Virtual design and construction project manager (VDC)

Full Access
Question # 15

While performing a survey of an existing elevator lobby in a sprinklered commercial building, a designer documents a dead-end corridor. How should this be corrected?

A.

coordinate with engineers to provide more sprinkler heads

B.

reconfigure the corridor to be less than 50 ft [15.2 m] in length

C.

provide a smoke detector and emergency lighting to the corridor

D.

raise the ceiling height to 10 ft [3.0 m] and include 2-hour fire-rated partitions

Full Access
Question # 16

A designer has a contract with a client to provide complete contract documents for a tenant build-out. Specifying FF&E is beyond the scope of the contract. The designer makes some general FF&E recommendations to show a systems furniture layout as required by the local code officials. The furniture comes in over the client’s previously undisclosed budget. What should the designer do?

A.

Suggest that the client purchase directly from the manufacturer

B.

Meet with the client and furniture provider to resolve the problems

C.

Research alternate furniture options to bring the budget back in line

D.

Let the client and the furniture provider work out the budget problems

Full Access
Question # 17

A contractor has notified the designer that the existing paint in a space tests positive for lead. What is the correct course of action?

A.

The lead paint should be encapsulated with oil-based paint

B.

The designer should notify the Environmental Protection Agency (EPA)

C.

A professional licensed contractor should perform lead-paint abatement

D.

A custodian should vacuum with a high-efficiency particulate air (HEPA) filter vacuum

Full Access
Question # 18

A designer is hired to update a community clubhouse in a private residential subdivision. During the pre-design phase, the designer interviews stakeholders to gather information about the use of the clubhouse. Who is the MOST important stakeholder?

A.

HOA

B.

residents

C.

building manager

Full Access
Question # 19

During early planning stages of a sustainable project, which of the following elements are the MOST important to develop?

A.

LED lighting and locally sourced materials

B.

Wind power and recycled content materials

C.

Composting toilets and renewable power sources

Full Access
Question # 20

A building owner hires a design firm to renovate an existing office suite into a live-work space. What is the FIRST step the designer should take?

A.

Perform a site visit

B.

Confirm zoning ordinance

C.

Document the project drivers

D.

Verify the building construction type

Full Access
Question # 21

When reviewing the general contractor’s pay application, the designer should approve the amount for

A.

Utilities and property taxes

B.

Subcontractors’ travel expenses

C.

Delivered materials stored on-site

Full Access
Question # 22

What deliverables are the responsibility of the interior designer in the design development phase?

A.

Power and data plans, floor plans with partition types

B.

Floor plans, reflected ceiling plans with HVAC ductwork layout

C.

Reflected ceiling plans with fixture types, floor plans with partition types

D.

Power and data plans, reflected ceiling plans with sprinkler head locations

Full Access
Question # 23

When calculating the usable area of a multi-tenant floor per BOMA standards, where should the designer establish the boundary between a tenant space and common corridor?

A.

At the centerline of the demising partition

B.

At the face of gypsum board on the tenant side of the partition

C.

At the face of stud on the common corridor side of the partition

D.

At the face of gypsum board on the common corridor side of the partition

Full Access
Question # 24

What is the BEST way for a designer to determine whether the payment application of a contractor is consistent with the work completed to date?

A.

Request a breakdown of the pricing in the payment application to be reviewed by the consultants

B.

Participate in periodic site visits to compare progress onsite to progress claimed in the payment application

C.

Review the project schedule to determine what should be completed by the date of the payment application

D.

Call the subcontractors individually to verify that the work noted on the payment application is indeed complete

Full Access
Question # 25

A storage area has been approved as an accessory occupancy within a retail store. The means of egress requirements are based on which occupancy type?

A.

Storage (S)

B.

Business (B)

C.

Mercantile (M)

Full Access
Question # 26

What is the allowable reach range for an obstructed side reach over a kitchen counter?

A.

34" [914 mm] to 46" [1168 mm]

B.

15" [381 mm] to 48" [1219 mm]

C.

18" [457 mm] to 48" [1219 mm]

Full Access
Question # 27

What is the MOST critical aspect of an existing building to check before locating library shelving and densely packed filing cabinets?

A.

Location of sprinkler lines and heads

B.

Location of columns and bearing walls

C.

Load-bearing capacity of the building’s floor system

D.

Access route from loading dock to the final location

Full Access
Question # 28

While on site, the designer notices that the glazing subcontractor is installing the storefront system in the wrong finish. What should the designer do?

A.

Report the discrepancy in a memo to the contractor and client

B.

Reach out to the glazing supplier to find out which finish was ordered

C.

Explain the issue at the next owner, architect, contractor (OAC) meeting

D.

Tell the subcontractor to stop their work and explain the issue to the contractor

Full Access
Question # 29

In a large project, what is the BEST reason to enter into a joint venture?

A.

Increase the firm’s profit margins

B.

Maximize hiring of short-term staff

C.

Allocate staff resources to one project

D.

Gain experience in a new type of work

Full Access
Question # 30

What is the term for a full-scale representation of products or construction features that may be required in bid (tender) documents?

A.

models

B.

samples

C.

mock-ups

D.

shop drawings

Full Access
Question # 31

Which wall section provides for a two-hour fire-rated wall?

IDPX question answer

A.

1 5/8" [41 mm] metal studs, 1/2" [13 mm] regular gypsum board applied to each side, 3/8" [9 mm] regular gypsum board applied to each side

B.

Two layers 1/2" [13 mm] metal studs, regular gypsum board applied to each side

C.

1 5/8" [41 mm] metal studs, 1/2" [13 mm] type X gypsum board applied to each side, 1/4" [6 mm] regular gypsum board applied to each side, 2" [50 mm] glass fiber insulation

D.

1 5/8" [41 mm] metal studs, two layers 1/2" [13 mm] type X gypsum board applied to each side, glass fiber insulation

Full Access
Question # 32

Delivery of product directly to the client’s address is known as

A.

pro forma

B.

sidemarked

C.

drop shipped

D.

freight on board

Full Access
Question # 33

Referencing the table below, which two spaces could be combined as part of the space needs program?

Space

Days in Use

Hours of Use

Banquet

Friday to Sunday

10am to 10pm

Classroom

Monday to Friday

8am to 12pm

Art Gallery

Wednesday to Sunday

11am to 7pm

Exhibition Hall

Friday to Tuesday

5pm to 10pm

A.

art gallery and banquet

B.

classroom and art gallery

C.

banquet and exhibition hall

D.

exhibition hall and classroom

Full Access
Question # 34

After completion of a project, the client spills coffee on their new lobby sofa. Where would the client look for information on how to remove the stain?

A.

product data sheet

B.

warranty information

C.

maintenance manual

D.

furniture specification

Full Access
Question # 35

Which of the following is MOST likely to require a louvered door?

A.

IT closet

B.

Hotel room

C.

Executive office

D.

Dental exam room

Full Access
Question # 36

What are the PRIMARY components of sustainability?

A.

global, wellness, and universal

B.

LEED, SMaRT, and Green Globes

C.

eco-friendly, non-toxic, and organic

D.

environmental, social, and economic

Full Access
Question # 37

The purpose of a post-occupancy evaluation is to determine

A.

Compliance with the punch (deficiency) list

B.

The quality of general contractor performance

C.

The completeness of the construction documents

D.

Client satisfaction or dissatisfaction with the project

Full Access
Question # 38

A restaurant is designated as which occupancy classification?

A.

public: group P-3

B.

business: group B

C.

restaurant: group R

D.

assembly: group A-2

Full Access
Question # 39

At the time of preparing construction documents, the client is undecided about replacing flooring within the scope of work. How would the designer obtain pricing for including the flooring?

A.

a mock-up

B.

an alternate

C.

an addendum

D.

a change order

Full Access
Question # 40

A lien has been placed on a building. What may be a probable cause for this action?

A.

A subcontractor has not been paid by the general contractor

B.

The certificate of substantial completion has not been issued

C.

The client requires more financing

D.

Contract documents do not comply with building code

Full Access
Question # 41

Which of the following is part of an active system for fire protection?

A.

Area of refuge

B.

Means of egress

C.

Protected stairwells

D.

Pre-action sprinklers

Full Access
Question # 42

A client wants to convert a 10,000 sf [929 m²] retail facility into an office space. What is the MOST important activity to do as a part of programming?

A.

Identify building codes

B.

Prepare record (as-built) drawings

C.

Calculate the number of parking spaces

D.

Determine which consultants are required

Full Access
Question # 43

A corporate client tells their designer that they will be purchasing all of their ancillary furniture directly, and would only like the designer’s assistance with the remaining pieces. Which of the following would be in the designer’s scope to specify?

A.

Reception sofa

B.

Break room barstools

C.

Open office workstations

Full Access
Question # 44

Who should be consulted when specifying materials and finishes to ensure maintenance adherence?

A.

Tenant

B.

Facility manager

C.

General contractor

Full Access
Question # 45

Upon review of all consultants’ drawings, the designer notices that the placement of a water closet is not consistent with the contract documents. What should the designer do?

A.

Provide the dimensions of the water closet along with a notation on the interior design documents of the water closet’s new location

B.

Coordinate the proper location with all parties through a change order

C.

Coordinate with the mechanical engineer and have the water closet relocated on the engineer’s drawings

D.

No action is necessary because the contractor is obliged to follow the interior design documents

Full Access
Question # 46

What is the MOST cost-effective way to locate plumbing fixtures in a commercial building renovation?

A.

Install plumbing fixtures by vertical penetrations

B.

Place plumbing fixtures in the axis of the building

C.

Locate plumbing fixtures on the exterior walls of the building

D.

Place plumbing fixtures as close to existing plumbing lines as possible

Full Access
Question # 47

A designer is planning an office remodel where the tenant is relocating their existing microwaves. After project completion, the tenant is disappointed to discover the outlets for the microwaves were installed at the incorrect height. What could the designer have done to prevent this?

A.

Coordinated the outlet heights with the electrical drawings

B.

Requested an appliance submittal from the general contractor

C.

Scheduled a site walk with the electrical contractor during installation

D.

Verified the equipment specifications with the microwave manufacturer

Full Access
Question # 48

Formaldehyde, PVC, and phthalates are examples of chemicals included in

A.

The Red List

B.

Class C finishes

C.

Hazardous building types

D.

CAL 133 compliant products

Full Access
Question # 49

What is the PRIMARY reason to maintain a master submittal log on a project?

A.

Confirm adherence to the contract

B.

Document the installation schedule

C.

Verify compliance with specifications

D.

Facilitate distribution and timely review

Full Access
Question # 50

During construction, a designer has been informed that the floor tile specified will delay occupancy. What is the BEST course of action?

A.

Modify the specifications to an alternate flooring type that is in stock

B.

Change the specifications to an in-stock tile and obtain the client’s agreement

C.

Notify the client and all subtrades that the anticipated schedule will be delayed

D.

Give an estimate of how far behind schedule the project is, with a new completion date

Full Access
Question # 51

What rating is used to determine a material’s sound absorption?

A.

CAC

B.

STC

C.

NRC

D.

UL (CSA)

Full Access
Question # 52

How do project managers guide a project if they or the design team lacks expertise in a certain area?

A.

Find appropriate consultants and include them in the design team

B.

Use an appropriate consultant if a problem arises during the project

C.

Require project team members to research information on the design criteria

D.

Select one member of the design team to receive training in the expertise required

Full Access