We at Crack4sure are committed to giving students who are preparing for the CIPS L5M9 Exam the most current and reliable questions . To help people study, we've made some of our Operations Management exam materials available for free to everyone. You can take the Free L5M9 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
There are four manufacturing companies located on Seashell Industrial Estate. Each company creates a different product and employs a different maintenance approach to its operations. For each company, select the corresponding maintenance approach and the key operating process characteristic.
Company 1: This company creates craft beer and offers customers a tour of the brewery for a small charge. The brewing equipment is serviced monthly and the brewery is kept extremely clean. All equipment is labelled with the last service date.
Company 2: This company produces seasonal items such as Easter Eggs and Christmas Cake. The equipment has a control panel where lights will flash red advising staff to check oil levels and components. Staff can then report issues to the maintenance team if remedial work is required. Product demand fluctuates throughout the year.
Company 3: This equipment does not often break down and is only fixed when it is reported by staff as no longer working. Company 3 creates toys, providing a large range of product sizes and colours based on different customer requirements.
Company 4: Parts of the machine are serviced quarterly but in general, the machine is left to run its course and is then replaced when it is no longer financially viable to fix. The company produces cereal and the operating process is focused on the quantity produced and therefore uses standardised processes.
Complete the table below by listing the maintenance approach and operating process characteristic for each company. Each response should only be used once: preventive maintenance, run to breakdown maintenance, condition-based maintenance, mixed maintenance, volume, visibility, variation, variety
Company
Maintenance approach
Operating-process characteristic
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 5?
JJ Ltd is a sporting goods manufacturer who is based in the UK. It is considering expanding its operations to include manufacturing sites based in South America. Which of the following considerations will JJ Ltd need to consider now that they are becoming an international organisation? Select TWO
Total Quality Management is built on 8 founding principles. Which of the following do these include? Select THREE.
Khaled has recently been hired as an Operations Manager at a company providing consultancy services. This is his first role in the service industry, previously he has worked at companies providing goods. He understands that services are intangible and therefore there is a difference in how Operations may be managed. Which of the following sentences about services are true? Select THREE
Performance Benchmarking is a form of what type of benchmarking?
Which of the following situations would use a fixed-position layout?
Which of the following operational activities is specifically concerned with checking that completed project outputs conform to customer specifications?
Which of the following would you likely find on a Process Control Chart which is being used to monitor the quality of products manufactured in a factory?
An Operations Manager is responsible for making many decisions. Which of the following would be a strategic decision made by an Operations Manager?
Below are details of five companies who operate a Total Quality Management System (TQM). For each company, select the system used and identify which area of the Balanced Scorecard this relates to.
Company 1: The focus of this company is to gather real-time data to assess the quality of products created during the manufacturing process. There are tight budgets and reworking any defects will affect the bottom line.
Company 2: This company is concerned about how their products are received. They have recently completed market research focused on their client’s feelings. The objective is now to improve the product’s look and performance to meet these expectations.
Company 3: The focus of this company is defining the customer requirements and translating this into a high-quality specification and effective operational process.
Company 4: Within this company there is a group of 6 employees who meet regularly with the objective of reducing issues that arise in the manufacturing of products.
Complete the table below by listing the TQM System used and the relevant Balanced Scorecard criteria for each company. Each response should only be used once: Quality Circle, Statistical Process Control, Kansei Engineering, Quality Function Deployment, Finance Criteria, Business Process Criteria, Learning and Growth Criteria, Customer Criteria.
Company
TQM technique
Balanced Scorecard perspective
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 1?
Below are details of 4 local manufacturing companies. For each company you must decide what the main objective is for the organisation and what layout their manufacturing plant has.
Company 1: This company creates large, delicate products which are hard to move. The main aim of the company is to stand out from competitors due to the superior level of materials used and by using the latest forms of technology to create the items.
Company 2: This company produces 72 different items and has designated zones within its premises for the creation of each item. The zones are organised based on the technology used and some products may be passed between different zones to be completed. The company creates many different items in response to changing customer demands, with many product lines only lasting a single season.
Company 3: Company 3 creates one product which flows along a single production line, with staff members adding to the product on four different occasions. The company must produce a high volume of this singular product in order to break even. Therefore, there is always a steady flow of items through the plant and it is important there is no stoppage in production.
Company 4: This company produces small batches of products, as and when they are ordered by customers. Due to uncertainty in demand, a high profit margin is added to the cost of each item. Teams in the factory are grouped into different areas depending on the technological process they are using.
Complete the table below by listing the objective criteria and plant layout for each company. Each response should only be used once: flexibility, speed, quality, cost, functional layout, cell layout, product layout, fixed-position layout
Company
Performance objective
Plant layout
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 2?
Dillan is an Operations Manager at Fancy Foods Ltd which is looking to expand the business into a new geographic area. Dillan is doing some research into three potential locations for a new manufacturing and warehouse facility. Which of the following would be primary considerations for Dillan? Select TWO
A fast-food restaurant provides a drink machine for customers to use, which allows the customer to select the drink that they wish by putting their cup under the machine and pushing a button. The machine will first drop ice into the cup, but this button will not work unless the cup is placed on an X. What is this an example of?
Logan has recently been appointed to the position of Operations Manager within in IT firm. The CEO has charged Logan with improving the performance of the department, in particular, in ensuring that promises made to customers are kept. Logan is therefore prioritising KPIs for the team including the delivering of services on-time and customer retention. Which of the 5 Performance Objectives of Operations Management is Logan focusing on?
How can a company measure the dependability of an item it produces? Select TWO
There are four manufacturing companies located on Seashell Industrial Estate. Each company creates a different product and employs a different maintenance approach to its operations. For each company, select the corresponding maintenance approach and the key operating process characteristic.
Company 1: This company creates craft beer and offers customers a tour of the brewery for a small charge. The brewing equipment is serviced monthly and the brewery is kept extremely clean. All equipment is labelled with the last service date.
Company 2: This company produces seasonal items such as Easter Eggs and Christmas Cake. The equipment has a control panel where lights will flash red advising staff to check oil levels and components. Staff can then report issues to the maintenance team if remedial work is required. Product demand fluctuates throughout the year.
Company 3: This equipment does not often break down and is only fixed when it is reported by staff as no longer working. Company 3 creates toys, providing a large range of product sizes and colours based on different customer requirements.
Company 4: Parts of the machine are serviced quarterly but in general, the machine is left to run its course and is then replaced when it is no longer financially viable to fix. The company produces cereal and the operating process is focused on the quantity produced and therefore uses standardised processes.
Complete the table below by listing the maintenance approach and operating process characteristic for each company. Each response should only be used once: preventive maintenance, run to breakdown maintenance, condition-based maintenance, mixed maintenance, volume, visibility, variation, variety
Company
Maintenance approach
Operating-process characteristic
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 3?
There are four manufacturing companies located on Seashell Industrial Estate. Each company creates a different product and employs a different maintenance approach to its operations. For each company, select the corresponding maintenance approach and the key operating process characteristic.
Company 1: This company creates craft beer and offers customers a tour of the brewery for a small charge. The brewing equipment is serviced monthly and the brewery is kept extremely clean. All equipment is labelled with the last service date.
Company 2: This company produces seasonal items such as Easter Eggs and Christmas Cake. The equipment has a control panel where lights will flash red advising staff to check oil levels and components. Staff can then report issues to the maintenance team if remedial work is required. Product demand fluctuates throughout the year.
Company 3: This equipment does not often break down and is only fixed when it is reported by staff as no longer working. Company 3 creates toys, providing a large range of product sizes and colours based on different customer requirements.
Company 4: Parts of the machine are serviced quarterly but in general, the machine is left to run its course and is then replaced when it is no longer financially viable to fix. The company produces cereal and the operating process is focused on the quantity produced and therefore uses standardised processes.
Complete the table below by listing the maintenance approach and operating process characteristic for each company. Each response should only be used once: preventive maintenance, run to breakdown maintenance, condition-based maintenance, mixed maintenance, volume, visibility, variation, variety
Company
Maintenance approach
Operating-process characteristic
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 4?
Below are details of five companies who operate a Total Quality Management System (TQM). For each company, select the system used and identify which area of the Balanced Scorecard this relates to.
Company 1: The focus of this company is to gather real-time data to assess the quality of products created during the manufacturing process. There are tight budgets and reworking any defects will affect the bottom line.
Company 2: This company is concerned about how their products are received. They have recently completed market research focused on their client’s feelings. The objective is now to improve the product’s look and performance to meet these expectations.
Company 3: The focus of this company is defining the customer requirements and translating this into a high-quality specification and effective operational process.
Company 4: Within this company there is a group of 6 employees who meet regularly with the objective of reducing issues that arise in the manufacturing of products.
Complete the table below by listing the TQM System used and the relevant Balanced Scorecard criteria for each company. Each response should only be used once: Quality Circle, Statistical Process Control, Kansei Engineering, Quality Function Deployment, Finance Criteria, Business Process Criteria, Learning and Growth Criteria, Customer Criteria.
Company
TQM technique
Balanced Scorecard perspective
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 5?
Total Productive Maintenance and Just in Time are examples of Total Quality Management (TQM). Is this correct?
Doug's Doughnuts Ltd is a large manufacturer of doughnuts. They produce in excess of 100,000 doughnuts per day which are boxed and sent to supermarkets and other retail outlets for sale. Large pieces of machinery are used to make the doughnuts. Which form of maintenance would be the most appropriate to use at Doug's Doughnuts?
When quality is used as a foundation to build improvements in other areas such as dependability, what is this theory known as?
Which of the following stakeholders are also internal customers?
In an organisation that uses Quality Control to determine whether manufactured products conform to customer requirements, which of the following activities would most directly demonstrate product-level inspection?
There are four dimensions of operating processes; volume, variety, variation and visibility. What is meant by variation?
Building redundancy into operational procedures increases what for an organisation? Select TWO
Which of the following are performance objectives which can be applied to the Operations department at any organisation? Select THREE
Farmer Ted harvests strawberries and sells these to retailers. Once the strawberries are collected from the field they are sent through a machine which will sort them by colour- ensuring only red strawberries are sent for packaging and any green, unripe strawberries are not. Which method of Poka Yoke is being used here?
Joan is the Operations Manager at a Dentist Surgery and has recently completed a Pareto Analysis with the hopes of improving the quality of service offered. Which of the following would be a possible finding from this analysis?
Below are details of five companies who operate a Total Quality Management System (TQM). For each company, select the system used and identify which area of the Balanced Scorecard this relates to.
Company 1: The focus of this company is to gather real-time data to assess the quality of products created during the manufacturing process. There are tight budgets and reworking any defects will affect the bottom line.
Company 2: This company is concerned about how their products are received. They have recently completed market research focused on their client’s feelings. The objective is now to improve the product’s look and performance to meet these expectations.
Company 3: The focus of this company is defining the customer requirements and translating this into a high-quality specification and effective operational process.
Company 4: Within this company there is a group of 6 employees who meet regularly with the objective of reducing issues that arise in the manufacturing of products.
Complete the table below by listing the TQM System used and the relevant Balanced Scorecard criteria for each company. Each response should only be used once: Quality Circle, Statistical Process Control, Kansei Engineering, Quality Function Deployment, Finance Criteria, Business Process Criteria, Learning and Growth Criteria, Customer Criteria.
Company
TQM technique
Balanced Scorecard perspective
Company 1
Box 1
Box 5
Company 2
Box 2
Box 6
Company 3
Box 3
Box 7
Company 4
Box 4
Box 8
Which of the following will you put into box 8?
The goal of Operations Management is to create processes which ensure the three Es: Efficiency, Effectiveness and Efficacy. What is meant be Efficacy?