We at Crack4sure are committed to giving students who are preparing for the CompTIA JK0-017 Exam the most current and reliable questions . To help people study, we've made some of our CompTIA E2C Project+ Certification Exam exam materials available for free to everyone. You can take the Free JK0-017 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
A key stakeholder on a project advises the project manager that there is a component of the project that has yet to be decided. They are concerned that their needs regarding this component will not be addressed. In which of the following documents should the project manager record this information?
A project manager has finished the first phase of a project. Who of the following determines if the project continues?
A team member reports that a system component they are working on causes the system to continually reboot. The project manager should record this in which of the following documents?
An experienced team member comes to the project manager to report that they are uncertain of the project requirements. This can MOST likely be attributed to:
Which of the following estimating types requires the MOST effort when creating a work breakdown structure (WBS)?
A project is approved in a series of stages. This is an example of:
A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline?
During execution, a project manager of a construction project requires certain project team members to work outdoors, atop tall buildings. Which of the following would BEST mitigate the risk of injury to those team members, without affecting the approved project schedule?
Which of the following correctly identifies the application of a projects quality management plan?
Which of the following contract types places the LEAST amount of risk on the seller?
Which of the following documents is used when assigning resources to scheduled tasks?
Several project tasks cannot be completed because local resources are not available. The project manager has to outsource the work to find qualified resources. Which of the following risk responses is the project manager using?
A Pareto diagram focuses attention on which of the following?
Which of the following shows a project that is presently over its financial budget?
A hurricane is forecasted near the corporations call center. The project manager has arranged for a redundant call center in another location to accept calls if the corporate call center is unable to receive calls. Which of the following risk responses is the project manager using?
Which of the following is the correct progression of the project life cycle?
The project manager has three stakeholders with whom they need to communicate (not including the project manager). There are six channels of communication. A new stakeholder has been added to the project that the project manager needs to communicate with. How many communication channels are now existent?
Before the execution phase begins, who is in control of the project?
During which of the following process groups is the project charter developed?
A team member on a project uncovers a minor risk with the quality of a purchased component. The team uses their combined expert judgment to determine that the risk to the deliverable is very low. Which of the following is the MOST likely action the project manager should take?
Which of the following steps should be taken to formally close a project? (Select Two).
Which of the following is created as part of the closing phase?
Which of the following is a benefit of the work breakdown structure (WBS)?
A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?
In which of the following organization types is it LEAST likely that a conflict regarding competing demands for resources would take place?
Which of the following components are included in a communication plan? (Select Two).
A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
All of the following are part of the monitoring and controlling process group EXCEPT:
Which of the following may have a significant adverse impact upon the successful completion of an international project? (Select Three).
During which of the following process groups is the availability of required resources for the project determined?
Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).
A project can be defined as which of the following?
Which of the following would MOST likely be reviewed during a project kick-off meeting?
Who has the MOST control over project scope changes?
Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).
A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
Which of the following is MOST likely to be included in a communication plan?
The project is running behind schedule because one of the developers has taken an unscheduled vacation. The project manager informs the developer that any further unauthorized absence will result in removal from the project. Which of the following resolution techniques was used?
Which of the following tools is the BEST to determine the cause of a problem?
Which of the following are examples of a good business case for a new project? (Select Two).
Which of the following documents would be generated to solicit bids from outside vendors?
Which of the following techniques could a project manager use to determine a project schedule based upon a variety of simulations?
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
A project manager has been informed that a project deliverable must be completed by September 1st. Which of the following BEST describes this situation?
A project manager has decided to reduce the impact of a possible threat. Which of the following risk response strategies BEST describes this action?
Monitoring and controlling project work is a control process function that spans from:
A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?
Control limits would be found in which of the following plans?
A project manager sits down to discuss with team members the strengths and weaknesses of a project. This is BEST described as:
Which of the following is the BEST reason to conduct a feasibility analysis?
A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
Two employees do not want to work with each other. The project manager tells the employees to perform the tasks or find other employment. Which of the following conflict resolution styles is being used?
Which of the following activities occur during a project kick-off meeting? (Select Three).
A stakeholder wants information on how frequently the project manager will provide a status report. Which of the following documents would be the BEST place to find this information?