3 Months Free Update
3 Months Free Update
3 Months Free Update
A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.
The project manager should:
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?
A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?
A milestone task on the critical path has been completed.
Which of the following should the project manager notify?
A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:
Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?
An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
Which of the following actions should the project manager take?
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave.
Which of the following should a project manager update to document this information?
When forming a project team, there are a number of phases.
When a project team is productive and effective this phase is known as which of the following?
Which of the following defines a group of projects that work together to achieve a common goal?
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?
A company has updated the method it uses to initiate projects. The company requires RFPs from three vendors, and low and high bids must be rejected to determine the selected vendor.
Which of the following terms describe this requirement?
Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?
A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:
A software development project is struggling with a certain technology that is unknown to the project team. A project manager has received a third-party proposal to transfer the risk. Which of the following should the project manager do NEXT?
A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.
Which of the following is a necessary step to record the actual durations?
A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.
Which of the following is MOST likely to be the main challenge the influences this decision?
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer
(CEO) directs that all meetings be conducted via video conference to save costs and expedite communication.
This scenario is an example of:
A quality auditor finds suspicious code during a software test. For which of the following could this be a trigger?
Which of the following defines the minimum level of engagement of a stakeholder?
A Chief Executive Officer (CEO) has approached a project team member to request a project change.
Which of the following would be the BEST step for the project manager to take to prevent scope creep?
Based on the table below:
Which of the following is the total float for the critical path?
Which of the following provides tools and standard documentation for the project team?
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.
Which of the following management styles is the project manager MOST likely using?
Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account.
Which of the following should the project manager do to ensure stakeholder expectations are met?
As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan.
Which of the following documents should be reviewed FIRST to uncover the issue?
A recently added stakeholder is unaware of critical changes that will affect the department. Which of the
following should the project manager do FIRST to ensure all parties have the same level of information?
An organization wants assurance that the specialty tools necessary for operation will function as intended for a
specific minimum time period. Which of the following documents BEST provides this assurance?
Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project.
Which of the following MOST likely explains this issue?
Which of the following project phases occurs when requirements are detailed?
A resource is assigned to two projects with two scheduled tasks that complete at the same time.
This is known as:
Which of the following job roles is MOST responsible for providing input on the project requirements, steering
the project, providing expertise, and having vested interest in the project?
The project manager needs to motivate the team; however, is an insufficient budget for awards.
Which of the following motivating agents is the MOST appropriate option the project manager can utilize?
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
A manufacturer is developing a product that will start in one week. The product has a delivery deadline of 90 days.
Which of the following characteristics classifies this as a project?
Based on the table below:
Which of the following is the critical path if Task B has extended to ten days?
A primary work location is unsafe due to a gas leak. The project manager has implemented the business continuity plan and authorized relocation to an alternate site.
Which of the following should be notified?
A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?
A project manager is scheduling activities and determines one activity cannot be completed until another
activity is completed. Which of the following dependency relationships is represented?
Which of the following documents serves the primary purpose of requesting details about a vendor’s capabilities?
A project manager has taken over a project that is already in progress. The project manager notices the
functional manager of one team is unaware of the current progress. Which of the following should the project
manager do? (Choose two.)
Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)
An employee is assigned to a project and is developing a project charter. Which of the following are some of
the constraints the employee would typically face at this stage of the project?
Which of the following captures unforeseen activities throughout the project that need attention and resolution?
While preparing to plan a project, the project manager meets with the key stakeholders to determine the
flexibility between the project constraints. Which of the following techniques should the project manager
consider to reduce personal bias and increase buy-in?
A project manager has been assigned a complex project and does not know all the activities required to complete it.
Which of the following if the BEST approach to determine the work packages for the WBS?
A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?
The PM has requested that a project repository be developed. Sensitive information will be available on the
site that could affect the project’s success. Only personnel who need to know the information will have access.
Which of the following site types is the PM requesting?
The Chief Executive Officer (CEO) has announced that the hardware division will be sold to another company.
The sale of this division is an example of which of the following?
Project status meetings have poor attendance. A SME from the hardware team dominates the meetings when questions are asked, not allowing input from other members.
Which of the following steps should the PM take to make the meetings more productive? (Select two.)
A project manager has developed the initial schedule for an upcoming project.
Using the attached schedule, which of the following is the critical path?
A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue?
To resolve a dispute between two project team members, the project manager allows both parties to provide input on the final design. Which of the following resolution techniques is being used?
An audit, project change, task initiation/completion, gate review, and incident response are examples of:
Which of the following documents will MOST likely result in a time and material agreement?
The responsibility of estimating how long a task will take belongs to the:
A company has been trying to implement a product with multiple challenges for more than two years. Both the company and the vendor mutually agree to cancel the project. Which of the following should be issued?
A newly developed claims processing system will require users of the prior system to be trained to use the new system. During which of the following project phases should the training occur?
A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete
the project on time. Many of these tasks were performed by the former project sponsor.
Which of the following types of change does this illustrate?
A project sponsor is not being updated on the project as expected. Instead of receiving information on a monthly basis, the project sponsor wants to see it biweekly and requests the use of a collaboration site instead of email. Which of the following actions should the project manager perform?
While working on a project, a self-organized team determines what will be accomplished during the next two weeks.
Which of the following describes what the team is doing?
During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium.
Which of the following is the BEST course of action?
An influential stakeholder has left the organization. Which of the following documents MOST likely needs to be updated?
One deliverable failed during testing, and this has already happened several times.
Which of the following tools is MOST appropriate for the project team to use to determine the cause of the problem?
A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
The project schedule performance index is 1.1, and the cost performance index is 0.9. Which of the following describes the project status?
The project manager was asked to provide recommendations for the removal of a vendor. A meeting was scheduled with the key stakeholders and the project sponsor to highlight the reasons for this recommendation.
Which of the following should the project manager bring to the meeting to support this recommendation? (Choose two.)
A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)
A project is in the initiation phase. Which of the following tasks will take place during this phase?
Which of the following is a key aspect of the Agile project management methodology?
A project manager is unsure if the quality of a deliverable from a SME meets specifications.
Which of the following is the BEST way for the project manager to address the issue?
During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?
A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables.
Which of the following steps should the project manager take to BEST resolve the issue?
Input into a project’s requirements is needed for clarification. With which of the following roles would the project manager MOST likely consult?
When a project team member completes a task in the WBS, which of the following are the primary recipients of
the notification? (Choose two.)
A new project manager is taking over a project that is already in the execution phase, and is conducting a review of all meetings to identify usefulness and content. Team members have complained of an overabundance of meetings. Which of the following would be useful to identify who should be required to attend?
The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?
A stakeholder wants to add four more data entry points on the accounts receivable screen of the current application being developed. Which of the following constraints would this impact directly?
A new project manager would benefit from additional assistance with documenting project activities.
Which of the following job positions should the project manager request be added to the team?
During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training.
Which of the following communication methods should be used?
Which of the following methods should a project manager use to improve email communication for a time- sensitive, high-visibility global project? (Choose two.)
A highly skilled, key project team member lacks technical writing skills. Documents are often misunderstood, and the wrong instructions are given.
To retain this key project team member, which of the following steps should the project manager take to BEST resolve the issue?
During a meeting, the project manager abruptly interrupts the discussion of two team members who have not reached an agreement on a particular requirement and continues with the meeting.
Which of the following conflict resolutions is the project manager performing?
Task A has a duration of 2 days and is a predecessor of task B, which has a duration of 3 days and is a predecessor of task C. Task C has a duration of 4 days. Task D has a start-to-start relationship with task A and a duration of 11 days. Which of the following is the lag time for task D?
A project manager is not going to finish a project on time but cannot change the deadline or add more budget. Which of the following types of change would allow the project manager to finish the project successfully?
A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?
A project manager is assigned a global team. The project manager is having difficulty understanding some of what is communicated during conference calls.
Which of the following is the BEST way to address this issue?
A project stakeholder is disappointed the team was not included in some key decisions. This resulted in extra discussions and rework. Which of the following documents should the project manager review and update to resolve this situation?
Which of the following is performed during the monitoring and controlling phase?
The vendor management team has requested all project managers to provide proof to back up complaints on vendor resolution delays.
Which of the following will provide this information?
A vendor is not meeting the agreed-upon quality of deliverables. To try to renegotiate the contract with the vendor, which of the following documents should the project manager use to highlight the areas that need improvement?
A customer-requested change has been denied by the CCB.
Which of the following should the project manager do NEXT?
While planning a project, the project team estimates known expenses but also applies a margin of error for
unknown expenses. Which of the following is the project team trying to determine?
A recent change request was implemented with approval; however, it had an unforeseen negative impact on the critical path. Which of the following measures should be taken to ensure the project is not delayed?
The Chief Executive Officer (CEO) of a company announced that a demerger operation will be completed in the next nine months. Which of the following BEST describes the organizational change?
A project manager is developing a communication plan for an enterprise-wide strategic project. Which of the following communication methods is BEST for sharing the project status reports?
Which of the following organization types requires the project manager to report performance issues to another
department?
A meeting organizer is deciding high-level requirements, the business case, and funding for a new project. Which of the following is the meeting organizer?
A first-time project manager is developing a project charter.
Which of the following are key elements to have the project charter approved? (Choose two.)