We at Crack4sure are committed to giving students who are preparing for the CompTIA PK0-005 Exam the most current and reliable questions . To help people study, we've made some of our CompTIA Project+ Certification (2026) exam materials available for free to everyone. You can take the Free PK0-005 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:

• Purpose

• Scope of work

• Location of work

• Period of performance

• Deliverables schedule

• Applicable standards

• Acceptance criteria

• Special requirements

• Payment schedule

Which of the following documents did the client provide to the project manager?

A.

RFP

B.

WBS

C.

SLA

D.

SOW

Question # 7

A project team is determining how an application will be moved to production, who the users will be, and what training is needed. Which of the following best describes what is being developed?

A.

Contingency plan

B.

Scope statement

C.

Transition plan

D.

Communication plan

Question # 8

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

A.

Buy a replacement for the faulty equipment.

B.

Get the maintenance team to resolve the issue.

C.

Escalate the issue to the project sponsor.

D.

Rate the severity of the impact the issue has on the project.

Question # 9

Which of the following activities should a project manager perform during the closing phase? (Select three).

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Question # 10

A PM is working with the development team and stakeholders to determine how to relate first name, last name, and address in a database. Which of the following identifies these types of data elements?

A.

PCI

B.

PII

C.

PHI

D.

CMS

Question # 11

Which of the following concepts represents multiple resources interfaced to run reports?

A.

Code repository

B.

Data warehouse

C.

Storage server

D.

File-sharing system

Question # 12

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.

Question # 13

Which of the following is a reason to use a SOW on a project?

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Question # 14

A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?

A.

Decision board

B.

Whiteboard

C.

Task board

D.

Dashboard

Question # 15

Which of the following best describes why conducting lessons learned sessions is important?

A.

To discuss as a team how to improve and eliminate all the issues in the project

B.

To conduct the team’s performance evaluation and document the results

C.

To report all the mistakes and ensure others do not make the same ones

D.

To document what went right and wrong, as well as possible improvements

Question # 16

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Question # 17

During the planning phase, a PM reviews the SOW from the contractor, grades the full-time equivalents' resumes, evaluates the titles and salaries, and estimates the number of hours for each milestone by full-time equivalents. The PM is most likely:

A.

negotiating resources.

B.

assigning resources.

C.

assessing the resource pool.

D.

adding resources to the schedule.

Question # 18

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

A.

Update the work breakdown structure.

B.

Review the backlog.

C.

Seek baseline approval.

D.

Establish the resource pool.

Question # 19

A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?

A.

Regression

B.

Unit

C.

Stress

D.

Smoke

Question # 20

Which of the following best describes a rollback plan?

A.

Apply an alternative plan if the original plan does not work.

B.

Return to the operational state of a system before applying a requested change.

C.

Restart the project with new resources to avoid failures from previous ones.

D.

Repeat the tasks suggested in the requested change until they work.

Question # 21

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Question # 22

After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?

A.

Provide the change to the CCB.

B.

Perform root cause analysis.

C.

Escalate to the project steering committee.

D.

Update the risk register.

Question # 23

The goal of a project is to fulfill specific technical features requested by customers. Which of the following actions should the product owner take?

A.

Define the success criteria.

B.

Create a communication plan.

C.

Use a task board.

D.

Perform a root cause analysis.

Question # 24

During the progress of a project, the stakeholders require the delivery of multiple milestones with proper presentation of functionalities. Which of the following is the best methodology to use?

A.

Waterfall

B.

SDLC

C.

XP

D.

Scrum

Question # 25

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

A.

Project status report

B.

Requirements Traceability Matrix

C.

Detect log

D.

Signed project charter

E.

Work breakdown structure

Question # 26

Which of the following tasks should the project manager complete first when validating deliverables?

A.

Assess the documentation.

B.

Obtain stakeholder feedback.

C.

Review the project objectives.

D.

Mitigate risks.

Question # 27

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Question # 28

Which of the following best explains why companies apply background screening during the employment process?

A.

To increase access restrictions

B.

To define KPIs for new employees

C.

To evaluate PHI

D.

To apply operational security

Question # 29

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

A.

Milestone

B.

Gantt

C.

Burndown

D.

PERT

Question # 30

Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?

A.

Software as a service

B.

Infrastructure as a service

C.

Data as a service

D.

Platform as a service

Question # 31

Which of the following is the main reason for documenting artifacts?

A.

To provide a record of the project's progress and achievements for future reference

B.

To show stakeholders that the project is on track and progressing as planned

C.

To help team members be aware of roles and responsibilities

D.

To ensure that the project team understands the importance of the project to the organization

Question # 32

Which of the following is a quantitative key performance indicator?

A.

The project sponsor ranked the graphics of an application as four out of five.

B.

The project implements the application in ten different geographical regions.

C.

The workers complete tasks on average 25% faster using a new application.

D.

The use of a multimedia interface appeals more to users under the age of 21.

Question # 33

A utility company issued a directive stating that projects impacting operating systems will not be executed during hurricane season. Which of the following is being acknowledged by this directive?

A.

Company brand value

B.

National environments

C.

Standard operating procedures

D.

Local emergency policies

Question # 34

Which of the following best describes the reason a chat messaging service would be used as the primary form of communication for a project team?

A.

The team is working in different rooms within the same building.

B.

The team is working remotely two days per week.

C.

The team has members distributed around the world in different time zones.

D.

The team is based in the same office but has a large number of members.

Question # 35

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Question # 36

During the testing process, testers have found multiple bugs that could jeopardize the project commitment date Which of the following tools should the project manager use first to update the findings?

A.

Defect log

B.

Change log

C.

Issue log

D.

Risk log

Question # 37

During the testing phase of a project, the legal department rejected a deliverable due to compliance issues. The project manager reviewed the risk register and triggered the mitigation plan for this item. Which of the following documents should the project manager update next?

A.

Schedule

B.

Status report

C.

Issue log

D.

Task board

Question # 38

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

A.

Build

B.

Subscription

C.

Lease

D.

Buy

Question # 39

A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date. Which of the following should the project manager do first?

A.

Hold the project until the devices are delivered.

B.

Evaluate the impact to baselines.

C.

Request another supplier to ship devices.

D.

Update the project timeline with a new project end date.

Question # 40

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Question # 41

A project manager is receiving reports of the actual project expenditures and, based on this information, is making adjustments to the budget. In which of the following phases does this occur?

A.

Planning

B.

Closure

C.

Initiation

D.

Execution

Question # 42

During the execution phase, a new PM was assigned to a project. The PM received a request to add new functionality to the system that is being developed. While the PM was conducting a preliminary review with the team, the technical lead highlighted that this functionality request was rejected during the planning phase. Which of the following documents is the best source for the PM to use to confirm this assertion?

A.

Issue log

B.

Scope statement

C.

Risk report

D.

Change log

Question # 43

A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

A.

Validate against the scope statement and ask for sign-off.

B.

Run a control chart to ensure the quality of the deliverables.

C.

Review the risk register and close up residual risks.

D.

Start the training and handoff for the operations team.

Question # 44

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter

Question # 45

Which of the following best represents the project impact to a company's brand value?

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.The project meets the expected milestones and finishes on time and within budget.

Question # 46

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Question # 47

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

PK0-005 question answer

Which of the following most likely represents the number of items in the backlog?

A.

23

B.

5

C.

10

D.

15

Question # 48

During an agile project, a team member checked the project artifacts in order to anticipate when all the work should have been completed. Which of the following charts was the team member most likely consulting?

A.

Pareto chart

B.

Milestone chart

C.

Burndown chart

D.

Gantt chart

Question # 49

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

A.

External

B.

Internal

C.

Mandatory

D.

Discretionary

Question # 50

A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?

A.

Perform a gap analysis.

B.

Escalate the issue.

C.

Submit a change request.

D.

Approve deliverables.

Question # 51

A PM is reviewing objectives for a project in a new industry. Which of the following items should the PM review first?

A.

Applicable regulations and standards

B.

Relevance to the global environment

C.

Company vision, mission, and values

D.

Impact to the corporate brand

Question # 52

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative

Question # 53

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RFI

D.

RFP

Question # 54

Which of the following statements best describes zero-based budgeting?

A.

Start with the budget from the last project and add any new expenses.

B.

Start with allocating expenses based on the importance of the project.

C.

Start the project with a fixed amount decided by the management team.

D.

Start with no financial plan and justify each new expense.

Question # 55

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?

A.

Performing

B.

Adjourning

C.

Forming

D.

Norming

Question # 56

In the initiation phase, a PM is reviewing the objectives, the high-level requirements, the success criteria, and the budget resources. Which of the following action items will benefit from this analysis?

A.

Developing a RACI

B.

Identifying and assessing stakeholders

C.

Assigning project resources

D.

Establishing communication channels

Question # 57

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Question # 58

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Question # 59

A highly scored negative risk causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

A.

Execute the contingency plan

B.

Perform a work-around

C.

Escalate to senior management

D.

Assign a risk owner

Question # 60

A project manager is unclear about the budget and timeline prior to the start of a project. Which of the following best describes what type of meeting needs to take place?

A.

Kickoff

B.

Demo

C.

Stand-up

D.

Status call

Question # 61

A project manager is comparing the documentation attached to invoices from main vendors with the requirements described in the SOW in order to decide if all are correct. Which of the following best describes what is being performed?

A.

Approving deliverables

B.

Enforcing vendor rules of engagement

C.

Reporting overall process

D.

Scheduling team touch points

Question # 62

After a product is released for production, a tester performs a test to ensure its basic functionality is working as expected. Which of the following is the tester performing?

A.

Smoke test

B.

Stress test

C.

Penetration test

D.

Regression test

Question # 63

During the planning phase, a project manager is mapping out the full scope, calculating task durations, and identifying dependencies. Which of the following is the best tool for the project manager to use?

A.

Gantt chart

B.

Milestone chart

C.

Velocity chart

D.

PERT chart

Question # 64

A PM is meeting with the project team to identify the baseline go-live date, the operational training, and the handoff procedures. Which of the following phases is the project team performing?

A.

Initiation

B.

Closing

C.

Execution

D.

Planning

Question # 65

A project team that handles sensitive data analysis recently onboarded three new employees. Which of the following should the PM do first?

A.

Check employee security clearance

B.

Allow access to the internet on corporate computers

C.

Train the new employees to handle sensitive data

D.

Execute an analysis of the sensitive data

Question # 66

A financial manager reports that several employees' allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?

A.

A project manager assigned the wrong resources.

B.

A project manager did not release the resources

C.

A project manager did not remove the system access.

D.

A project manager did not provide the project sign-off.

Question # 67

A web designer is currently verifying that the website data is compliant. Which of the following data types will be protected after confirming that the controls are in place?

A.

Credit cards

B.

Mission statements

C.

Site certificates

D.

Trademarks

Question # 68

After a weekly status meeting, a project manager needs to prepare and distribute a document with a summary of all the topics discussed, agreements, and next steps. Which of the following documents should the project manager prepare?

A.

Minutes

B.

Project presentation

C.

Memorandum

D.

Issue log

Question # 69

A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).

A.

Company vision

B.

Global environment

C.

Brand value

D.

Mission statement

E.

Portfolio budget

F.

Local legislation

Question # 70

Which of the following would be considered operational security?

A.

Mobile device compliance

B.

Background screening

C.

Multifactor authentication

D.

Facility access

Question # 71

Which of the following tools should a project manager use to assess the activities performed, work effort applied, and the productivity of a project?

A.

Project status report

B.

Project evaluation review

C.

Project management software

D.

Requirements traceability matrix

Question # 72

A project manager will conduct a release on the third Friday of the month. The project manager has notified users that the application will be unavailable for eight hours. Hence, users need to save any information in advance. Which of the following is the project manager most likely conducting?

A.

Application deployment

B.

Rollback plans

C.

Validation checks

D.

Maintenance window schedules

Question # 73

Which of the following requires the MOST availability from the business team?

A.

SDLC

B.

Scrum

C.

PRINCE2

D.

Waterfall

Question # 74

Which of the following best represents an intellectual property breach?

A.

Internal developers use code from a legacy in-house system to develop a new solution for the marketing department.

B.

The price list to end customers was stored on a stolen external hard drive.

C.

A service provider that worked on a project uses the developed software on a project for a new customer.

D.

Customer data is stored on a shared network drive that is accessible by employees from all departments.

Question # 75

As a result of an unpredicted risk, a project manager is documenting a request in the change control log. Which of the following change control processes should the project manager do last?

A.

Escalate to the change control board.

B.

Update the project plan.

C.

Test the implemented change request.

D.

Communicate the change deployment.

Question # 76

Although a project was successfully released into production a month ago, a project manager continues to receive project-related work. Which of the following is the reason for this issue?

A.

The project manager did not release the resources.

B.

The project is in the verification testing phase.

C.

The project manager did not complete the project closure phase.

D.

The project manager did not remove access.

Question # 77

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

PK0-005 question answer

Part 2:

PK0-005 question answer

Question # 78

To gather requirements from stakeholders, the project manager sits down with them and allows them to discuss freely. Which a following technique is the project manager utilizing?

A.

Process moving

B.

Brainstorming

C.

Interview

D.

Focus group

Question # 79

A project was selected for an audit years after the project closed. Which of the following is most likely to be needed for the audit?

A.

Signed contracts

B.

Archived documentation

C.

Project closeout report

D.

Lessons learned

Question # 80

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Question # 81

Which of the following best describes the role of a PM for a CRM system?

A.

To track sales

B.

To store customer information

C.

To implement new features

D.

To pay vendors

Question # 82

Which of the following statements best represents a network issue?

A.

The development team on the fourth floor is unable to access servers and email services.

B.

Cell phones served by a specific telecom company are getting a "no service" message.

C.

A user cannot connect to Wi-Fi because of a wrong ID or password.

D.

A user is receiving an automatic reply message saying that an email address does not exist.

Question # 83

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Question # 84

Which of the following provides a layered approach to logging in to systems that contain an organization's most valuable intellectual property?

A.

Remote access

B.

Password protection

C.

Multifactor authentication

D.

Virtual private network

Question # 85

A project manager has noticed that one-hour status calls are consistently lasting an extra 10 to 15 minutes. Which of the following techniques would be best for the project manager to use?

A.

Meeting minutes

B.

Action items

C.

Timeboxing

D.

Follow-up notes

Question # 86

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

A.

Request a change control ticket.

B.

Review the schedule plan.

C.

Refine the project documentation.

D.

Revise the communication plan.

Question # 87

Which of the following pieces of data are examples of Pll?

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

Question # 88

A new project manager takes over a project midway through the schedule. Which of the following should the project manager do first before continuing the project?

A.

Access project artifacts.

B.

Arrange a brainstorming session.

C.

Conduct a kickoff meeting.

D.

Establish communication channels.

Question # 89

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Question # 90

A project manager is conducting an evaluation of a product to determine whether it is meeting the requirements. The manager needs to compare the current status of the product with its optimal future status and determine what, if anything, needs to be done to improve it. Which of the following types of evaluations would be best for the manager to use?

A.

Gap analysis

B.

External status report

C.

Cost-benefit analysis

D.

Project closeout report

Question # 91

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

A.

Obtain details from the owner of the project.

B.

Update the critical path for the project.

C.

Apply contingency reserves.

D.

Reestimate epic user stories.

Question # 92

Which of the following would a scrum team discuss during a daily stand-up meeting?

A.

The likelihood of uncertain events occurring, the impact of the uncertain events, and the responses to take

B.

Actions to continue, actions to stop, and recommendations on how to proceed in the future for similar endeavors

C.

Buffer utilization and reallocation, critical resources with schedule impacts, and path convergence coordination

D.

Progress from the previous day, projected accomplishments for today, and foreseen issues that may interfere with work

Question # 93

During the testing phase of a project, an executive raises a concern about a missing requirement in the product. Which of the following is the next step the project manager should take?

A.

Communicate the change status.

B.

Ask for a change request submission

C.

Escalate to the change control board

D.

Reject the change to prevent scope creep.

Question # 94

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

Question # 95

A data center is under construction, and the project manager wants to address the risks related to physical injuries. Which of the following is the best risk response method for this scenario?

A.

Avoid injuries by using robots to perform tasks.

B.

Transfer risk to an insurance company.

C.

Mitigate risk by training the construction workers.

D.

Accept the risks inherent to construction.

Question # 96

A project team selected a random sample of patient accounts for testing the deliverable. The data was masked since it contained patient names. Which of the following describes this type of data?

A.

Confidential information

B.

Protected health information

C.

Personally identifiable information

D.

Security clearance

Question # 97

Which of the following is a disadvantage of a cloud model?

A.

Limited processing and storage capacity

B.

Limited expansion capability

C.

Longer latency time

D.

Higher dependency on the vendor

Question # 98

A critical piece of equipment that is needed for the installation of a point-of-sale solution is delayed from the manufacturer. The delay will cause the project to be significantly behind schedule. The project manager decides to buy the item at a higher cost from another vendor who can supply it immediately. Which of the following risk management approaches has the project manager taken?

A.

Mitigate

B.

Transfer

C.

Accept

D.

Share

Question # 99

Which of the following is a capital expense?

A.

Building lease

B.

Building purchase

C.

Building maintenance

D.

Building insurance

Question # 100

Which of the following is the best alternative to allow multiple users to edit a project plan in real time?

A.

Send the file through email as an attachment

B.

Share access to the file on a wiki knowledge base.

C.

Access the file through an online application.

D.

Schedule an in-person meeting to review the plan

Question # 101

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

A.

Change log

B.

Project Gantt

C.

Issue log

D.

Requirements traceability matrix

Question # 102

A new project manager was assigned to a project during the execution phase. The project manager discovers a lot of potential areas that may prevent the project from completing deliverables Which of the following should the project manager do first?

A.

Review the project risk register.

B.

Update the defect tracker.

C.

Meet with stakeholders to discuss concerns.

D.

Add the potential blockers to the issues list.

Question # 103

Which of the following tools is best to use for storing lessons learned?

A.

Whiteboard

B.

Wiki knowledge base

C.

Content management system

D.

Workflow platform

Question # 104

Which of the following software programs would be BEST to use lo store information related to business transactions?

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Question # 105

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

Question # 106

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

Question # 107

A quality assurance team is based in three different locations To validate the project deliverables, a project manager sent the hardware for testing purposes to the team in each of the locations. Two teams confirmed the hardware arrived, but one group did not receive it because of local customs Which of the following ESG factors is the project team facing?

A.

Awareness of the company vision, mission statement, and values

B.

Impact of the project on the company's brand value

C.

Awareness of applicable regulations and standards

D.

Impact of the project on the local and global environments

Question # 108

A project team is developing an application that will allocate a building's parking spaces. The building owner does not agree with using corporate colors in the application and has blocked

the release of the beta version for testing. Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?

A.

Review of existing artifacts

B.

Development of an issue log

C.

Identification and assessment of stakeholders

D.

Establishment of accepted communication channels

Question # 109

Which of the following can a project manager infer from the following velocity chart?

PK0-005 question answer

A.

The project is on schedule.

B.

The project Is ahead of schedule.

C.

The project is behind schedule.

D.

The project is at risk.

Question # 110

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

A.

SWOT

B.

Risk register

C.

Project schedule

D.

RAC

Question # 111

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

A.

RFP

B.

RFQ

C.

RFB

D.

RFI

Question # 112

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

Question # 113

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

A.

Time to be fixed

B.

Impact to project

C.

Issue category

D.

Resource availability

Question # 114

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Question # 115

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Question # 116

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Question # 117

A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?

A.

Inform the CCB to stop communication.

B.

Establish a RACI matrix.

C.

Escalate the communication issues.

D.

Revise the communication plan.

Question # 118

A new junior PM who has ownership of a project does not understand how to manage conflicts involving multiple personalities. Which of the following is the best order of the stages the PM should follow to nurture the team to high performance?

A.

Forming, storming, performing, norming, adjourning

B.

Forming, performing, storming, norming, adjourning

C.

Forming, norming, storming, performing, adjourning

D.

Forming, storming, norming, performing, adjourning

Question # 119

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

13 days and $3,600

Question # 120

An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens' complaints. Which of the following solutions would be BEST?

A.

Enterprise resource planning and end user applications

B.

Electronic document and record management systems

C.

Customer relationship management and databases

D.

Content management and financial systems

Question # 121

Stakeholders ask the PM to provide an updated budget. Which of the following is the most important reason to update a project's budget during the execution phase?

A.

Evaluate the project's communication plan.

B.

Track and manage the project’s financial condition.

C.

Report the project’s risks and issues.

D.

Distribute resources to the project.

Question # 122

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

A.

Risk register

B.

Change log

C.

Traceability matrix

D.

Project status report

Question # 123

Which of the following describes three-tier architecture?

A.

Conceptual, design, and implementation stages

B.

Presentation, application, and data processing

C.

Network, software, and security

D.

Development, testing, and production environment

Question # 124

A client continues to present the project team with additional changes. To help with agreeing upon an expected delivery date, the project manager sets up a meeting with stakeholders. Which of the following should this meeting identify?

A.

Project scope

B.

Project communication

C.

Project budget

D.

Project objectives

Question # 125

A contractor attended a project meeting that was exclusively for company employees. Which of the following actions should the PM take?

A.

Escalate to vendor management.

B.

Consult the request for proposal.

C.

Review the meeting cadence.

D.

Reinforce the rules of engagement.

Question # 126

A stakeholder raises a concern that a certain important functionality might be missing and asks the PM to submit a change request so it can be included. The PM is confident the functionality is included. Which of the following has the PM most likely checked?

A.

Risk register

B.

Detailed scope statement

C.

Requirements Traceability Matrix

D.

Task board

Question # 127

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

Question # 128

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

PK0-005 question answer

Which of the following issues should be addressed FIRST?

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Question # 129

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Question # 130

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

Question # 131

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

A.

Concept of operations

B.

WBS

C.

Integrated master schedule

D.

RACI

Question # 132

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Question # 133

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

PK0-005 question answer

Which of the following was the initial cause of the issue?

A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

Question # 134

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.

PK0-005 PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PK0-005 PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: CompTIA Project+ Certification (2026)
  • Last Update: Apr 6, 2026
  • Questions and Answers: 447
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PK0-005 Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included