Month End Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

ENOV612-PRG PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

ENOV612-PRG PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: V6 ENOVIA V6 Program Central (V6R2012)
  • Last Update: May 25, 2025
  • Questions and Answers: 138
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

ENOV612-PRG Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

ENOV612-PRG Practice Exam Questions with Answers V6 ENOVIA V6 Program Central (V6R2012) Certification

Question # 6

If you DO NOT think you will need a template in the future, you should:

A.

delete the template

B.

promote it to inactive

C.

delete the WBS

D.

clear out the date range

Full Access
Question # 7

When a route is started, task assignees will see the task where?

A.

Workspace page

B.

Tasks page

C.

Meetings page

D.

Routes page

Full Access
Question # 8

When viewing a dashboard and the slip date is 0 to 4 days later than the estimated end date, the slip date will be:

A.

Red

B.

Green

C.

Yellow

D.

Black

Full Access
Question # 9

In the, Out Of The Box, Project Dashboard, the color code for tasks is:

A.

Yellow to indicate a task is late

B.

Red to indicate a task is due within one day

C.

Green to indicate a task is not started

D.

Orange to indicate a task is at risk

Full Access
Question # 10

What is the maximum character length for the name of a Program?

A.

64

B.

127

C.

264

D.

Unlimited

Full Access
Question # 11

What metric CANNOT be deleted from Critical to Quality (CTQ)?

A.

Goal

B.

Controlled

C.

Measured

D.

Predicted

Full Access
Question # 12

Risks CANNOT be created for:

A.

Projects

B.

Project Concepts

C.

Project Templates

D.

WBS Tasks

Full Access
Question # 13

Looking at the below image, when would you expect to work on the Create Instructor Guide task (WBS 2.4) by looking at the Dependency column?

ENOV612-PRG question answer

A.

Cannot start until Approve Student Guide finishes

B.

Cannot start until Approve Student Guide starts

C.

Cannot start until Create Slides finishes

D.

Cannot finish until Create Slides finishes

Full Access
Question # 14

To add a subtask under a parent task, on the WBS screen you would select the parent task and then click

A.

Add to Selected

B.

Add Under Selected

C.

Add Subtask Below

D.

Insert Under Selected

Full Access
Question # 15

If you select the Metrics Icon on the below dashboard, what happens?

A.

Data that has been generated will be displayed in a series of graphs

B.

A Financial line graph will be displayed that will show actual costs of the program

C.

A Bar chart will be displayed with the Actual and Estimated costs

D.

A Pie chart will be displayed indicating the Cost Ratio breakdown

Full Access
Question # 16

When you create a Project from a template, what method is used to determine what WBS tasks will be created?

A.

Project Policy

B.

Project Visibility

C.

Questions assigned to tasks

D.

Task Dependency

Full Access
Question # 17

When viewing a Gantt Chart, the user can change the time grid settings to view it by....

ENOV612-PRG question answer

A.

Year, Month, Week, Day, Hour, Minute

B.

Quarter, Month, Day, Hour, Minute

C.

Year, Quarter, Month, Day

D.

Year, Month, Week, Day, Minute

Full Access
Question # 18

ENOV612-PRG question answer

Business goals are objectives that are satisfied by a:

A.

Project

B.

Program

C.

Task

D.

Route

Full Access
Question # 19

When a Program is in the Active state, the program:

A.

is ready to be used

B.

contains Projects that are active or archived

C.

Start Date cannot be edited

D.

Estimated Finish Date can be edited

Full Access
Question # 20

Before you create a Work Breakdown Structure (WBS), you should...

ENOV612-PRG question answer

A.

Assign members to the project

B.

Promote the project to Approve

C.

Set up the end dates

D.

do all of these

Full Access
Question # 21

Edits to a Project Template affect:

A.

any current project that is in the Active state that was created from the template

B.

any future project that will be created from that template

C.

any project that is in the Create state that was created from that project

D.

all projects that were created from that template

Full Access
Question # 22

What is this view on the Project Assessment telling you?

A.

The Project health is in trouble and needs immediate attention.

B.

The Project is in good shape.

C.

The Project is on schedule but has a high risk that must be watched and managed.

D.

The Project is complete.

Full Access
Question # 23

What do the small red triangles indicate in the below image?

ENOV612-PRG question answer

A.

The cells are locked and cannot be edited

B.

The cells are editable

C.

The cells data has been pasted by the Edit menu

D.

The cells data is new data

Full Access
Question # 24

To add Persons to Projects, you would use what Categories menu item?

A.

Members

B.

Add Users

C.

Properties

D.

Approvals

Full Access
Question # 25

Int the following image, what does the dependency (FS) specify?

ENOV612-PRG question answer

A.

Import the points WBS task must finish before the Filter the points task can start

B.

Import the points WBS task must start before the Filter the points task can finish

C.

Import the points WBS task must finish before the Filter the points task can finish

D.

Import the points WBS task must start before the Filter the points task can start

Full Access
Question # 26

What feature would you use to solicit opinions about the concept project from members of the project team and from outside the project team, such as your suppliers or customers?

A.

Discussions

B.

Subscriptions

C.

Task efforts

D.

Resources

Full Access
Question # 27

When displaying a Gantt Chart, the user CANNOT change what display parameter?

A.

Hide a column

B.

Show a column name

C.

Sort a column

D.

Color

Full Access
Question # 28

What does the red square in the following image, indicate?

ENOV612-PRG question answer

A.

The task is not complete and the current date is after the task estimated finish date

B.

The task is not complete and there are less than 5 days before the project's estimated finish date

C.

The task is complete

D.

The task has not started

Full Access
Question # 29

Program Central users can list:

ENOV612-PRG question answer

A.

all Programs for their Company

B.

only Programs that they are members of

C.

only Programs that are in the Inactive state

D.

only Programs that are in the Active state

Full Access
Question # 30

What support information can you attach to Assessments?

A.

Only Existing Documents that have been checked in

B.

Any WBS structure

C.

Any supported Document type

D.

No files can be attached to Assessments

Full Access
Question # 31

Routes can be deleted when they are in what state?

A.

Started

B.

Stopped

C.

Finished

D.

In any state

Full Access
Question # 32

In the following image, what does the "Reset" button do?

ENOV612-PRG question answer

A.

It resets the values of the modified fields

B.

It displays all the fields that are editable

C.

It reset the value of the last value that was changed

D.

It clears out all the date fields

Full Access
Question # 33

What are the lifecycle states of a program?

A.

Active and Inactive

B.

Create, Active, Archive

C.

Active and Archive

D.

Create, Active, Inactive and Archive

Full Access
Question # 34

In the members' page of a project, what members can you add to a project?

A.

Persons

B.

Roles

C.

Groups

D.

All of these

Full Access
Question # 35

What is a project?

A.

A collection of tasks to be performed

B.

Several tasks in a specific sequential order

C.

Tasks bounded by time, resources and required results

D.

All of these

Full Access
Question # 36

You have a 2 day fixed task with these dates: Start: Thur Jul 24, 2003 End: Fri Jul 25, 2003, you have a 2 day dependent fixed task that is set for FF+1.0 d then the dependent task will have this:

A.

Estimated Start Date Fri Jul 25, 2003 And this Estimated Finish Date Mon Jul 28, 2003

B.

Estimated Start Date Wed Jul 23, 2003 And this Estimated Finish Date Thur Jul 24, 2003

C.

Estimated Start Date Thur Jul 24, 2003 And this Estimated Finish Date Fri Jul 25, 2003

D.

Estimated Start Date Tues Jul 29, 2003And this Estimated Finish Date Wed Jul 30, 2003

Full Access
Question # 37

When creating a Resource Loading report, you can use what periods?

A.

Weekly, Monthly, Quarterly

B.

Daily, Weekly, Monthly

C.

Daily, Weekly, Quarterly

D.

Weekly, Monthly, Yearly

Full Access
Question # 38

What is the key benefit of having a folder in a project?

A.

Control the access to project documents

B.

To track each person who revises a file

C.

Lock the document that is checked out for editing

D.

All of these

Full Access
Question # 39

The assessor can evaluate what areas of a project for health through the dashboard?

A.

Schedule, Cost, Resource, Risk

B.

Schedule, Expense, Resource, Issues

C.

Issues, Expense, Risks, Schedule

D.

Cost, Issues, Resource, Expense

Full Access
Question # 40

When you copy an existing project, what components are brought over to the new project?:

A.

Tasks

B.

Folders

C.

Documents

D.

All the above

Full Access
Question # 41

When defining the task duration, you can do it in...

A.

Days

B.

Hours

C.

Fractions

D.

All of these are possable

Full Access