Practice Free CDCS EXIN EPI Certified Data Centre Specialist Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the Exin CDCS Exam the most current and reliable questions . To help people study, we've made some of our EXIN EPI Certified Data Centre Specialist exam materials available for free to everyone. You can take the Free CDCS Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

Management requests a 15-minute battery bank at full UPS load. UPS specs:

    30 kVA, PF 0.8

    Battery 384 V (192 cells), end discharge 308 V

    Inverter PF 0.8, 400 V output

What information is missing to perform the calculation?

A.

UPS efficiency

B.

Inverter efficiency / output PF

C.

Load imbalance

D.

Available battery charging current

Question # 7

The temperature in the computer room is being increased from 18°C/64°F to 27°C/81°F.

What is the impact, if any, on the amount of gas required to suppress a fire assuming the gas is a Halocarbon?

A.

The amount of gas required will be higher

B.

The amount of gas required will not change

C.

The amount of gas required will be lower

D.

The change to the amount of gas cannot be determined without knowing the change in humidity as well

Question # 8

EMF shielding material needs to be installed as EMF levels from the transformer room into the computer room are measured at 100 mG. The transformer room is ~10 meters away, separated by a corridor. Where should shielding be installed?

A.

It does not matter; either close to the transformer room or computer room is okay

B.

As close as possible to the transformer room

C.

As close as possible to the computer room

D.

Shielding is not required as 100 mG is within acceptable levels

Question # 9

Is it allowed to make design changes during the implementation phase?

A.

No, after a design freeze no further changes are allowed.

B.

Any change is fine as long as it is within the scope of the project.

C.

Yes, but only when time to implement is not exceeded.

D.

Only when there is a strong business and/or technical justification.

Question # 10

You want to make cooling more effective by setting cold aisle temperature to 4 °C (39 °F). Is this acceptable?

A.

Yes, but only if cooling systems can maintain this continuously

B.

Yes, as long as dewpoint doesn’t go below -9 °C (16 °F)

C.

No, 4 °C (39 °F) is below the allowable ASHRAE range

D.

No, intake air must be exactly 20 °C (68 °F)

Question # 11

When designing a data center network, your company wants to minimize the number of network cables to install. What type of physical cabling layout would be the best choice?

A.

Top of Rack (ToR) design

B.

End of Row (EoR) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Question # 12

Where should raised-floor installation start?

A.

Point A (entrance corner)

B.

Point B (side wall)

C.

Point C (center of the room)

D.

Point D (corner opposite entrance)

Question # 13

What is the effect of having a damper (in open position) construction in a raised-floor tile?

A.

Dampers allow for a higher supply air temperature

B.

Dampers increase the air volume by approximately 10%

C.

Dampers reduce the air volume by approximately 10%

D.

Dampers can be used when there is a high rate of temperature change in the computer room

Question # 14

A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).

Will the network architecture be part of this audit?

A.

No, as concurrently maintainable only applies to electrical and mechanical (power and cooling).

B.

Yes, but only if the network administration does not comply with ANSI/TIA-606.

C.

Yes, amongst other aspects, the network architecture should be Rated-3 compliant with the requirements of ANSI/TIA-942.

D.

No, only the type of cabling used will be audited.

Question # 15

What indicates the overcurrent of a fuse or breaker?

A.

The maximum inrush current an overcurrent protection device can handle within a defined period of time

B.

The maximum electrical current which can flow in a particular electrical system under short-circuit conditions; it is determined by the voltage and impedance of the supply system

C.

The current at which the device will trip

D.

The current that a fuse or breaker is able to interrupt without being destroyed or causing an electrically damaging arc

Question # 16

What precaution shall be taken for cabling leading into an equipment rack when a data center is in a seismic-prone area?

A.

Cables should be loosely organized to allow for movement and be latched at the connectors.

B.

Cables shall be tightly organized to the rack and trays to avoid movement.

C.

Cables can be organized in any way as it is not important.

D.

Cables should be replaced by busbar trunking.

Question # 17

What is forced entry resistance based on?

A.

Time, tools, and people

B.

Rate and installed number of CCTV cameras

C.

Building materials used and the location of the data center

D.

The number of security guards on duty

Question # 18

What is the minimum requirement for power feeds to a Rated-4 data center (ANSI/TIA-942)?

A.

Two feeds from two different substations, one power company not acceptable

B.

Two feeds from two different substations, one power company acceptable

C.

Two feeds from one substation

D.

One feed split into two distribution boards

Question # 19

When designing a data center network, your company wants to minimize the number of network switches to manage.

What type of physical cabling layout would be the best choice?

A.

ToR (Top of Rack) design

B.

EoR (End of Row) design

C.

Star network design using coaxial cables

D.

It does not matter as the number of switches is not influenced by the physical cabling layout

Question # 20

What is the first step in the design stage of the data center life cycle?

A.

Select vendors

B.

Do a design validation

C.

Define the scope of the project

D.

Freeze the design

Question # 21

You need to install a highly sensitive fire detection system. The data center has a high airflow rate. Which system should you recommend?

A.

Dry pipe sprinkler system

B.

Ionization smoke detector

C.

Photoelectric smoke detector

D.

VIEW (Very Early Warning) smoke detector

Question # 22

In which stage of the data center life cycle does commissioning take place?

A.

Retire

B.

Operate/optimize

C.

Implement

D.

Design

Question # 23

The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).

What influence does this have on Electrostatic Discharge (ESD)?

A.

No influence as long as the temperature is at approximately 20°C/77°F

B.

Relative humidity has no influence on ESD

C.

ESD levels will go up

D.

ESD levels will go down

Question # 24

A computer room needs to be fitted out with a gas-based fire suppression system. The computer room will be a high-density data center with about 30% of the racks being closed circuit cooling blade-center racks.

Should the supplier of the fire suppression system be informed on the design of the racks?

A.

No, cooling and design of racks have no influence on the fire suppression system design.

B.

Only when the rack height obstructs a potential fire suppression release point.

C.

Yes, the design of the racks has an influence on the fire suppression system design.

D.

Only when the racks might block access to the fire panel.

Question # 25

A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.

What type of generators should be installed?

A.

Standby generators should be installed in at least an N+1 configuration

B.

Continuous generators should be installed, at least in an N+1 configuration

C.

A combination of standby-, prime-, and continuous-generators, as the duration of the power outage is unpredictable. The total available capacity of the generators should be at least 500% of the data center load

D.

Continuous generators should be installed; no N+1 configuration is needed as the generators will run all the time

Question # 26

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch H?O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

Question # 27

What is the advantage of OM5 multimode fiber cabling?

A.

Supports SWDM, requiring fewer fibers

B.

No advantage—same as OM4

C.

Designed for cheaper LED transmitters

D.

100 Gbit/s link for 500 m reach

Question # 28

Where should perforated tiles be installed?

A.

At the back of racks

B.

Every 5th rack

C.

One tile per rack in front

D.

As close to AC as possible

Question # 29

You are allowed to use a calculator for this question. The total power consumption of the ICT equipment in a rack is 6 kW. The equipment is traditional ICT equipment with a Delta-T of approximately 11 °C / 20 °F. Calculate the approximate CFM required to cool the equipment in the rack.

A.

Approximately 1,500 CFM

B.

Approximately 1,000 CFM

C.

Approximately 500 CFM

D.

Approximately 160 CFM

Question # 30

You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?

A.

No, there is a significant difference in the formula for the different types of fire suppression gases.

B.

Yes, as long as you take the difference between the net and gross volume into account.

C.

Yes, as long as you use the same units of measure, i.e., kg/m³ or lbs/ft³.

D.

Yes, as long as you change the 'S' factor of the formula to reflect the gas type used.

Question # 31

In which stage of the data center life cycle does testing and commissioning take place?

A.

Design stage

B.

Implement stage

C.

Operate/optimize stage

D.

Retire stage

Question # 32

What is needed to determine the Relative Humidity (RH)?

A.

Wet bulb temperature, local atmospheric pressure, and calculator

B.

Dry bulb temperature, airflow, and conversion table

C.

Cold surface with dew collection counter

D.

Dry bulb temperature, wet bulb temperature, and psychrometric chart

Question # 33

An MCB needs to be installed in the PDU of an air-conditioner unit.

Which breaking curve should you select?

A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

Question # 34

An MCB needs to be installed in the PDU of an ICT rack. Which breaking curve should you select?

A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

Question # 35

What is the advantage of using Multi-fiber Push-On (MPO) connectors?

A.

No advantage, cannot be used with OM4 fiber

B.

Allows a single connector with multiple fibers running parallel, enabling easy upgrade to 40–100 Gbit/s

C.

Made of high-quality materials, reusable without risk

D.

Very flexible, can be used for both copper and optical fiber

Question # 36

The building requires sprinklers and is equipped with a wet-pipe system. What action should you recommend for the computer room?

A.

Maintain the current wet-pipe system

B.

Replace the wet-pipe system with a deluge system

C.

Replace the wet-pipe system with a pre-action system

D.

Replace the wet-pipe system with a dry-pipe system

CDCS PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

CDCS PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: EXIN EPI Certified Data Centre Specialist
  • Last Update: Dec 14, 2025
  • Questions and Answers: 120
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

CDCS Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included