We at Crack4sure are committed to giving students who are preparing for the Exin CDFOM Exam the most current and reliable questions . To help people study, we've made some of our Certified Data Center Facilities Operations Manager exam materials available for free to everyone. You can take the Free CDFOM Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

The data center organization conducted a customer satisfaction survey and concluded that a very low number of customers participated.

What is the most likely cause?

A.

The survey did not have enough questions

B.

The survey was not sent on behalf of the data center manager

C.

The survey had too many questions

D.

The survey was sent by postal mail instead of e-mail

Question # 7

Of the below, which is a non-renewable energy source?

A.

Natural Gas

B.

Wind energy

C.

Tidal power

D.

Hydropower

Question # 8

Out of the below, which one is not part of the needs analysis?

A.

Business requirements

B.

Physical infrastructure requirements

C.

Commercial requirements

D.

Legal requirements

Question # 9

Customers complain about support response times being too slow. After a check with the vendor about the agreed SLAs, it is concluded that no violation occurred.

What is the likely cause of the customers complaining?

A.

There is not enough operations staff to respond to customer complaints

B.

The Underpinning Contract with the vendor is not aligned with the customer Service Level Agreement

C.

Customers involved receive standard support only and should upgrade to a premium support level

D.

Service Level Agreement reporting is unclear

Question # 10

A new Service Level Agreement is being proposed for which the data center operations manager must give her approval.

Which document – or information – will she consider consulting first?

A.

Training program overview

B.

Job descriptions

C.

Skills matrix

D.

Resumes of staff

Question # 11

Data center operators complain about receiving too many non-alarm conditions.

What is the best response?

A.

Retrain staff on how to monitor the data center equipment

B.

Conduct a review of alarm information

C.

Instruct data center operators to ignore the non-alarm notifications

D.

Upgrade the monitoring system software to the latest version

Question # 12

In and around the data center, who is responsible for safety?

A.

The safety manager

B.

The facilities manager

C.

All staff

D.

The managing director

Question # 13

According to the World Economic Forum, which of the below is the largest global risk of the next decade?

A.

Global climate change

B.

Air quality in large cities

C.

Earthquakes

D.

Water scarcity

Question # 14

Maintenance needs to be outsourced; management demands a contract option with the lowest risk possible.

Which is the best option to choose?

A.

Basic/standard/non-comprehensive

B.

Time and Material

C.

Comprehensive

D.

Exclusive

Question # 15

The needs analysis has been completed and the data center organization is tasked with the capability assessment.

Which of the below is a mandatory activity as part of the capability assessment?

A.

Review the security needs

B.

Create inventory of skills, knowledge and capacity

C.

Determine the availability requirements

D.

Identify applicable safety requirements

Question # 16

What is the formula to calculate the PUE of a Data Center?

A.

PUE = UPS input power / UPS output power

B.

PUE = VA * PF

C.

PUE = Total facility power / Total IT equipment power

D.

PUE = Total generator capacity / total battery capacity

Question # 17

The data center organization has all its services prepared and wishes to announce the outcome to its customers so that they can place their order.

What document – or information – will it share?

A.

Service portfolio

B.

Business continuity plan

C.

Needs analysis report

D.

Service catalog

Question # 18

During lock-out/tag-out, which of the below is the most recommended procedure?

A.

Operator locking out the equipment and another operator removing the lock-out

B.

Operator locking out the equipment and the safety manager removing the lock-out

C.

Operator locking out the equipment and the facilities manager removing the lock-out

D.

Operator locking out the equipment and the same operator removing the lock-out

CDFOM PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

CDFOM PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Certified Data Center Facilities Operations Manager
  • Last Update: Jan 19, 2026
  • Questions and Answers: 60
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

CDFOM Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included