We at Crack4sure are committed to giving students who are preparing for the Exin PR2F Exam the most current and reliable questions . To help people study, we've made some of our PRINCE2 Foundation Exam exam materials available for free to everyone. You can take the Free PR2F Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
Which is a responsibility of a risk owner?
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
In what process is the authorization to deliver the project's products given?
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
What theme provides the justification for the project?
What theme estimates the cost of delivering the project?
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
Which is a true statement about PRINCE2 event-driven controls
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Which statement about the quality review technique is FALSE?
What plan is created, and submitted for approval, during the Managing a Stage Boundary process?
Which of the following are true statements about a Project Brief?
1. Used to provide a foundation for the Initiating a Project process
2. Created in the Starting up a Project process
3. Used by the Project Board to make an assessment of a project's progress
4. Used as the basis of the Project Initiation Documentation
Which is a purpose of an End Project Report?
Which is a recommended quality review team role?
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Which is a Benefits Review Plan used to assess?
Which is a purpose of the Quality theme?
Which is a purpose of the Risk Register?
When should the Project Board refer to corporate or programme management for a decision?
Where should the names of those who are to approve a product be recorded?
Which of the following take place before the initiation of a project?
1. Appoint the Executive
2. Capture requirements
3. Develop the Project Brief
4. Develop the detailed Business Case
Which risk response type is a recommended response to both an opportunity and a threat?
What product identifies the management stages and other major control points in a project?
Which is a purpose of the Directing a Project process?
Which of the following are objectives of the Directing a Project process?
1. Ensure corporate or programme management has an interface to a project
2. Ensure that work on products allocated to a team is authorized
3. Ensure there is authority to initiate a project
4. Ensure that a project remains viable
Which is NOT a PRINCE2 principle?
Which is NOT included in the PRINCE2 definition of a project?
What is the collective name for individuals or groups who may be affected by a project?
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
Which is a typical core activity within configuration management?
Which is a purpose of a Configuration Management Strategy?
Identify the missing word(s) in the following sentence.
Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a project.
Who carries out audits that are independent of the project?
Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
What process is used by the Project Board to respond to an Exception Report?
Which is a purpose of a Project Brief?
Why is a Project Brief produced?