We at Crack4sure are committed to giving students who are preparing for the FIDIC CCM Exam the most current and reliable questions . To help people study, we've made some of our Certified Contract Manager exam materials available for free to everyone. You can take the Free CCM Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
(Please select the one answer in which the mentioned documents are in the correct order (hierarchy), as mentioned in the standard Contract Agreement form of the FIDIC Silver Book (edition 1999).)
Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer ' s Requirements. Which statement is correct?
In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?
Choose all of the correct answers (multiple possibilities).)
(For specific probable future events or circumstances which may adversely affect the Works, FIDIC Red and Yellow Books (edition 1999) provide a duty to notify specific parties. Which two statements are correct?
Choose all of the correct answers (multiple possibilities).)
Giving " Notice " .... [2017 edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Regarding FIDIC Yellow and Silver Books (edition 1999) the Contractor has submitted its design proposal through the Contractor ' s Proposal. Which two of the following statements are true in this respect, after it has been submitted?
Choose all of the correct answers (multiple possibilities).
Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
During the execution of certain Works under a FIDIC Yellow Book (edition 1999), a Contract in a historical area along the silk route, one of the workers on the excavator shouts out to the supervisor of the Contractor it has discovered something on the Site. The supervisor inspects the finding and concludes this is possibly an ancient treasure in a wooden box. The supervisor sees some golden coins through the cracked lid of the box. The supervisor immediately stops the execution of the Works, sends the workers away and blocks access to the Site for all persons. Given the sensitive nature of the findings, the supervisor informs you as Engineer. How do you react?
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(Under the FIDIC Red and Yellow Books (edition 1999), which two of the following answers are correct regarding the application for Interim Payment Certificates? Choose all correct answers.)
When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)
Which of the following statements are not correct? [2017 Edition]
Choose all of the correct answers (multiple possibilities).
Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
(Which one of the following statements is correct regarding the Employer ' s Representative under the FIDIC Silver Book (edition 1999)?)
(In a FIDIC Red Book, the Employer shall have prepared (or have prepared by a design consultant) all the design for the Works. Which of the listed documents form the basis for this design (2 correct answers apply))
Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
Which of the following documents form part of a FIDIC Construction Contract [ " Red Book " (1999)], hence, to be drafted and included among the Tender Documents? (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)
The FIDIC Books are evolutions of earlier contract models, and although the different versions of a specific model are not the same, familiarity in definitions and structure makes it easier to work with different FIDIC books as well as with their different editions.
Is this statement true or false?
Which of the following obligations are relevant to the Engineer ' s roles with regards to insurance? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
Which one of the following statements best describes the requirements of Time for Completion?
Applying FIDIC Silver Book (edition 1999), which one of the following elements shall not form part of the time Programme/revised programme?
(Which one of the following statements regarding FIDIC Golden Principles is correct?)
Which one of the following statements regarding drafting contracts based on FIDIC Books is correct?
(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))
Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(In the FIDIC Yellow Book (edition 1999), the Contractor has to provide the Engineer with documents as stated in Sub-Clause 5.2. Who is responsible for ensuring there is sufficient time allocated for reviewing these documents in relation to the Schedule of the Works?)
(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)
3 Months Free Update
3 Months Free Update
3 Months Free Update