3 Months Free Update
3 Months Free Update
3 Months Free Update
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
In the basic communication model, which term refers to the method that is used to convey the message?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Which of the following includes how requirements activities will be planned, tracked, and reported?
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Change requests are processed for review and disposition according to which process?
Which tool or technique is used to manage change requests and the resulting decisions?
The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:
What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Organizational theory is a tool used in which Project Human Resource Management process?
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
A tool and technique used during the Perform Qualitative Risk Analysis process is:
Documented identification of a flaw in a project component together with a recommendation is termed a:
Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
Which of the following is an output of Direct and Manage Project Execution?
The process of identifying the stakeholders' information needs is completed during:
Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?
Which cost estimate technique includes contingencies to account for cost uncertainty?
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Which of the following characteristics are found in a functional organizational structure?
Prototype development may be used as a tool for which of the following risk response strategies?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Which Process Group and Knowledge Area include the Sequence Activities process?
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Which of the following involves making information available to project stakeholders in a timely manner?
Which illustrates the connection between work that needs to be done and its project team members?
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
Which of the following tools or techniques is used for Estimate Activity Durations?
What cost control technique is used to compare actual project performance to planned or expected performance?
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?
A risk that arises as a direct result of implementing a risk response is called a:
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?