3 Months Free Update
3 Months Free Update
3 Months Free Update
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
True or False: The Scrum Framework encompasses rules or guidelines for architecture?
Who determines whether the development team has been assigned enough work in a Sprint?
You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?