Question # 6

An architect finds several vulnerabilities with a customer's digital enterprise that could lead to data loss on a third-party storage system for critical business segments.

Which solution should the architect propose to help the customer to protect their digital enterprise?

A.

an HPE StoreOnce solution configured to take backups of the critical data from the third-party storage

B.

an HPE StoreAll solution configured to migrate the critical data to object-based storage

C.

an HPE StoreVirtual solution configured as a secondary node to replicate the critical data on the third-party storage

D.

an HPE 3PAR StoreServ solution configured to peer persistence with the third-party storage to protect the critical data

Full Access
Question # 7

A customer plans to develop scripts that use the REST API for HPE OneView. However, the customer is concerned about the complexity of the scripts.

Which tool can be used to adopt the HPE OneView REST API quicker?

A.

HPE SmartStart Scripting Toolkit

B.

HPE Operations Analytics for HPE OneView

C.

HPE Python library for HPE OneView

D.

HPE iLO4 using RedFish

Full Access
Question # 8

An architect takes the following notes during a meeting with a customer:

  • plans to introduce an entirely new service offering to customers
  • servers will be virtualized and will consume large amounts of storage space
  • project is to operate in an isolated section of the data center with limited access to the corporate network
  • need flexibility to grow quickly as required by the new service demands on the infrastructure
  • has no repeatable process for firmware management
  • concerned about how long it will take for the project team to become productive on the new infrastructure

Which solution should the architect propose to help the customer overcome all of its project challenges?

A.

HPE BladeSystem solution with HPE 3PAR storage

B.

HPE Apollo 6000 solution with HPE 3PAR storage

C.

HPE ConvergedSystem 700 solution with HPE 3PAR storage

D.

HPE Apollo 2000 solution with HPE 3PAR storage

Full Access
Question # 9

An architect is planning an HPE Apollo 4530 solution to support the Cloudera distribution of Spark and HDFS.

Each HPE ProLiant XL450 in the solution uses the following baseline recommendations:

- 15 8TB HDDs (120TB total)

- 2 10-core 2.3GHz processors

- 128GB memory (64GB on each processor)

- 2-port 10GbE FlexibleLOM

The architect has planned enough servers to meet the customer's requirements for total capacity.

Which two components in this plan are most likely to cause a bottleneck as an increasing number of Spark applications run?

A.

processor and memory

B.

adapter bandwidth and processors

C.

drive capacity and memory

D.

drive type (HDD versus SSD) and drive capacity

Full Access
Question # 10

HPE Moonshot 180G Switch Modules and HPE Moonshot 16-SFP+ Uplink ModulesA customer is planning to

replace its DAS-based third-party server solution with an HPE BladeSystem solution using FlexFabric

connected to an iSCSI based HPE StoreVirtual 3200.

Which method should the architect recommend for migrating data from the old system to the new system?

A.

Use Peer Motion with a temporary 180-day license

B.

Use Business Copy software licensed to the current total size of all DAS storage

C.

Use Virtual Copy software

D.

Use a LAN-based file transfer method

Full Access
Question # 11

Which network infrastructure components should an architect consider when recommending 40GbE in a

server solution?

A.

OM2 cables can be reused for runs of 50 meters or less

B.

OM4 cables can be reused for all runs out to the maximum of 300 meters

C.

Cables will need to be replaced by multi strand MPO cables

D.

Multimode cables will all need to be replaced by single mode cables

Full Access
Question # 12

A customer needs to use LACP to aggregate server network connections. The customer also needs to bond all FlexLOM connections in a single network across multiple switches.

Which networking feature should the architect recommend to meet the customer's needs?

A.

Intelligent Resilient Framework

B.

Transparent Interconnection of Lots of Links

C.

Network Virtualization using Generic Routing Encapsulation

D.

Shared Uplink Sets

Full Access
Question # 13

Which of the HPE Transformation Areas should the architect discuss when the customer’s concerns span backup and recovery, high availability, and disaster recovery?

A.

Transform to a hybrid infrastructure.

B.

Empower the data-driven organization.

C.

Protect the digital enterprise.

D.

Enable workplace productivity.

Full Access
Question # 14

An architect is proposing an HPE Moonshot System, including m710 cartridges, an iLO Chassis Manager, switch, and uplink modules. The customer needs IT staff to be able to access cartridges over a Remote console.

What should the architect explain to the customer?

A.

IT staff can open a Remote Console to any cartridge linked to an mRCA through the iLO CM.

B.

Remote Console access is only supported when a cartridge is part of an HPE Helion CloudSystem 9.x solution.

C.

Remote Console access is not supported for cartridges; IT staff should use local consoles instead.

D.

IT staff can open a Remote Console to any cartridge through the iLO CM.