Question # 6

What is the primarily purpose of an escalation?

A.

automate workflow processes

B.

monitor time sensitive records

C.

trigger scheduled reports or actions

D.

make automatic updates to records

Full Access
Question # 7

Which statement is true about master Preventive Maintenance (PM) records?

A.

a master PM record does not generate associated PMs

B.

a master PM record generates work orders like any other PMs

C.

associated PM records can be created from master PM records

D.

associations cannot be made between existing PM records and a master PM record

Full Access
Question # 8

Job plan's responsibility can be assigned to a supervisor, crew, lead, and owner. Which statement is true regarding a work order that results from a job plan?

A.

The values for supervisor, crew. lead, and owner from the job plan always carry over to the work order regardless of the values for supervisor, crew, lead, and owner defined on the preventive maintenance record.

B.

If the values for supervisor, crew, lead, and owner on the preventive maintenance record are different compared to those on the job plan, the values on the preventive maintenance record take the place of those on the job plan when copied to the work order.

C.

If the values for lead and owner are different on the preventive maintenance record compared to those on the job plan, the values on the preventive maintenance record take the place of those on the job plan when copied to the work order. Values for supervisor and crew come from the job plan.

D.

If the values for lead and owner are different on the preventive maintenance record compared to those on the job plan, the values on the job plan take the place of those on the preventive maintenance record when copied to the work order. Values for supervisor and crew come from the preventive maintenance record.

Full Access
Question # 9

A user is able to create a new work order from the Work Order Tracking application, the Assets application, and from which other application?

A.

Meters

B.

Job Plans

C.

Purchase Contracts

D.

Condition Monitoring

Full Access
Question # 10

What are examples of stock categories in IBM Maximo Asset Management V7.5?

A.

Stock. Non-Stock. Reorder

B.

Stock. Non-Stock, Direct Issue

C.

Stock. Non-Stock. Special Order

D.

Direct Issue. Reorder. Special Order

Full Access
Question # 11

Which statement is true about creating a Service Level Agreement (SLA)?

A.

It is created based on asset collections listed in the asset inventory.

B.

It is created based on a Maximo business object to which it applies.

C.

It is created based on service requests initiated by the Work Orders application.

D.

It is created based on contract approvals specified in the Contracts and Warranties application.

Full Access
Question # 12

When installing IBM Maximo Asset Management V7.5 without using the middleware installer to install IBM WebSphere Application Server, which step must be taken for a successful installation?

A.

The JMS connection factory must be created in a special, separate cell connected to an IBM DB2 data store to provide a way for server failures to be recovered.

B.

The WebSphere Application Server must be configured to allow for remote execution and access traffic in order for the installer to successful^ obtain the trust.p12 file using a remote file copy method.

C.

JMS data stores must be created using a database (with a supported vendor: IBM, Oracle, or Microsoft) in order to allow the manual configuration of the JMS resources to be successfully completed.

D.

The trust.p12 keystore file must be copied from the WebSphere Application Server's deployment manager profile>/etc directory to a suitable location and be provided as an input to the installation program

Full Access
Question # 13

Which statement describes an inventory backorder reservation?

A.

the reservation quantity must be less than 10

B.

the reservation quantity must be greater than 10

C.

the reservation quantity must be satisfied by the current balance on the inventory record

D.

the reservation quantity must be satisfied by the available balance on the inventory record

Full Access
Question # 14

Which criteria in the organization's work orders Edit Rules rules options specifies when field values can be changed?

A.

a given work order status

B.

a given work order work type

C.

when given work order is Approved

D.

when given work order is in Workflow

Full Access
Question # 15

Preventive Maintenance (PM) work orders can be triggered by which two criteria? (Choose two.)

A.

Meter-based PMs based on asset meter readings

B.

Time-based PMs based on elapsed time since previous work

C.

Unit measure-based PMs based on the threshold of the Unit of Measure application

D.

Asset-based PMs based on the status of the asset when it is moved in the maintenance storeroom

E.

Item Master-based PMs based on the status of the item when it is moved in the maintenance storeroom

Full Access
Question # 16

A customer wants to send an e-mail using the Create Communication action from Work Order Tracking using a communication template The Communication Template Accessible From should be set to what value?

A.

APPS

B.

WOTRACK

C.

WORKFLOW

D.

ESCALATION

Full Access
Question # 17

The Asset Templates application creates multiple assets at one time. At what level is the asset created?

A.

Site

B.

Item Set

C.

Database

D.

Organization

Full Access
Question # 18

What is the purpose of the Inventory Usage application?

A.

To list all inventory tool items within a storeroom

B.

To list all inventory service items within a storeroom

C.

To track the issue, transfer, and reuse of inventory items within and across sites

D.

To track the issue, transfer, and return of inventory items within and across organizations

Full Access
Question # 19

Where is authorization for changing general ledger component types done?

A.

Organizations application

B.

Security Groups application

C.

Chart of Accounts application

D.

Database Configuration application

Full Access
Question # 20

A user can review the meter readings history from the Assets application and which other application?

A.

Meters

B.

Meter Groups

C.

Condition Monitoring

D.

Activities and Tasks

Full Access
Question # 21

What is the initial default status when creating a Request for Quotation?

A.

INPRG

B.

DRAFT

C.

WAPPR

D.

INACTIVE

Full Access
Question # 22

How is Assignment Manager used?

A.

To assign PMs to a site

B.

To assign users to security groups

C.

To dispatch assignments from a workflow process

D.

To dispatch labor and schedule work for the organization

Full Access
Question # 23

Which fields must be specified to define an inventory item's reorder details?

A.

Reorder, Reorder Point, Safety Stock, and Order Unit

B.

Reorder, Reorder Point, Lead Time, and Primary Vendor

C.

Reorder, Reorder Point, Lead Time, and Economic Order Quantity

D.

Reorder, Reorder Point, Safety Stock, and Economic Order Quantity

Full Access
Question # 24

Where are labor option settings defined?

A.

Sites application

B.

Labor application

C.

Person application

D.

Organizations application

Full Access
Question # 25

A purchase order can be created from which three applications? (Choose three.)

A.

Assets

B.

Locations

C.

Contracts

D.

Item Master

E.

Purchase Requisitions

F.

Request for Quotations

Full Access
Question # 26

A failure class can be associated to which two Maximo entities? (Choose two.)

A.

Meters

B.

Assets

C.

Routes

D.

Locations

E.

Preventive Maintenance

Full Access
Question # 27

When creating new Business Intelligence and Reporting Tool (BIRT) reports for use by the various IBM Maximo Asset Management applications, which step correctly describes a part of the process to add a new report?

A.

Before design files are imported, any associated library files must be imported

B.

Using the system configuration option, choose the report designer files to import

C.

Using the BIRT Report Designer Workstation, select the menu item to import the new report

D.

Before design files are imported, the location files that specify the location of the images and report files must be populated

Full Access
Question # 28

Where are IBM Maximo Asset Management V7.5 properties changed?

A.

Logging.properties file

B.

Mxserver.properties file

C.

System Properties application

D.

Application Properties application

Full Access
Question # 29

Which type of role is defined as: You use this data type to route a record based on information in a person record?

A.

USER

B.

PERSON

C.

USERDATA

D.

PERSONGROUP

Full Access
Question # 30

Which statement is true regarding the master Preventive Maintenance (PM) record?

A.

A master PM record is generated by the Meters application.

B.

A master PM record is generated by the Assets application.

C.

A master PM record generates work orders like any other PM.

D.

Associations between existing PM records and a master PM record can be made.

Full Access
Question # 31

When a work order is created from a preventive maintenance record that references a route, the route stops will become child work orders with a common job plan. From which record will the resulting parent work order description be created?

A.

It will be the same as the route description.

B.

It will be the same as the job plan description.

C.

It will be null, to be updated with a description specific to the job.

D.

It will be the same as the preventive maintenance record description.