In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?
A business analyst (BA) is modelling requirements to assist the stakeholders in visualizing the appearance and capabilities of a planned solution. What technique is the BA using?
A business analyst (BA) has determined that “Product Box”, a collaboration game, will provide a fun way to engage the stakeholders when working on prioritizing the list of features. What should the BA do?
An organization has two different solutions to grow its business. One project is worth $375,000 to the organization. The second project is worth $565,000 to the business. The organization can only do one of the projects and elects to do the second project for $565,000. What is the opportunity cost of this decision?
Holly's organization uses a plan-driven approach to business analysis. When it comes to communication in Holly's organization what type of communication will likely be required?
As a candidate for CCBA, you should be able to recognize the activities associated with each knowledge area. Which of the following is an elicitation process that is a part of job observation?
Complete this statement.are longer-term, ongoing, and qualitative statements of a state or condition that the organization is seeking to establish and maintain.
The business need is considered to be the most critical step in the business analysis effort. Why is the definition of the business need considered the most critical step?
You are the business analyst for your organization and you're creating a data flow diagram to show how
information is input, processed, stored, and output from a system. Which element of a data flow diagram represents a process that transforms data by combining it with other data?
Complete this sentence. If a requirement cannot be verified, it cannot be successfully.
An organization has invested $750,000 into a technology to help secure, automate, and communicate customer ordering. The solution has worked well for the past six months, but a newer technology has been developed that surpasses the abilities of the current solution and solves many defects and issues the company has with the existing solution. Purchasing the newer solution, however, means that the company will have to discard the solution that's only been in place for the past six months. What term can be assigned to the monies already implemented into the existing solution?
Wanda is the business analyst for her organization and she is currently working on the specify and model requirements process. One of the elements of this process is the documentation of the textual requirements. Wanda must describe the capabilities of the solution, any conditions that must exist for the requirements to operate, and what third component of the textual requirement?
You are the business analyst for your organization. Management has asked that you create a method to store the project requirements including those under development, under review, and the requirements which have been approved. What is management asking you to create?
A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?
The project plan called for deliverables to be handed over at the end of the project. Although the client's business team was satisfied, the client's technical team was extremely resistant to this approach. What could the business analyst (BA) do to mitigate the technical team’s resistance?
If you're a business analyst and using an event-based elicitation task, such as a requirements workshop, what can be considered as essential to establish with the participants?
Marcy is working with stakeholders to understand the stakeholders' needs as part of the business requirements. The stakeholders are describing their needs for new computers for their designers. The stakeholders have specifications, monitors, and software selected for the business requirements. What are the stakeholders actually defining in this scenario?
Which of the following are not appropriate for a plan-driven business analysis approach? Each correct answer represents a complete solution.
Ralph is a business analyst for his organization and he's using the plan-driven approach for business analysis. Ralph has captured the requirements of the project, but what must happen before he can begin capturing and defining the requirements at a deeper level of detail?
Which stakeholder in the solution assessment task will provide information on technical constraints that could limit the solutions that may be implemented?
Which one of the following statements best describes requirements prioritization?
You have been assigned as the Project Manager for a new project that involves the development of a new interface for your existing time management system. You would like to plan the communications that need to be made during the project lifecycle. Which of the following would be a critical tool/technique to help in your communications planning?
There are four methods to generate the business need in an organization. Which approach is described as the need to achieve a strategic goal?
Complete this statement. Policies and rules serve as boundaries andthe organization and the operation of the organization.
Linda works as a project manager for an IT project. She is getting new developers for completing her project. Which of the following processes is she involved in?
According to the book 'A Guide to the Business Analysis Body of Knowledge', effective business analysis practices can do what to the amount of change to requirements in a stable business environment?
You are the business analyst for your organization and you're training Marcy, a new business analyst, on how requirements are defined. Which one of the following best describes how requirements are defined?
Which one of the following statements is most true about changing requirements in a change-driven approach to business analysis and requirements management?
Which one of the following terms is not a business analysis planning and monitoring approach?
You are the business analyst for your organization and you're working with several stakeholders to identify, manage, and approve requirements. Your organization requires using a plan-driven approach to business analysis and changing management. In this approach, who is most likely to approve changes to requirements?
A facilities management company has an ambitious growth plan of doubling the revenue of their office waste recycling service over the next 12 months. The business analyst (BA) plans to define the objectives and align them with the enterprise's vision, mission and goals. What element of ‘SMART’ goals would this objective refer to?
What can be considered the only input to the task of defining assumptions and constraints?
What type of a business analysis approach focuses on the rapid delivery of business value in short iterations?
Which elicitation activity is best described to ensure that the needed resources are organized and available for the elicitation?
Holly is the business analyst for her organization and she's leading a requirements workshop for a proposed solution. In this workshop, Holly is using a requirements tracing matrix to help prevent against scope creep. What is scope creep?
You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?
What do business goals and objectives of enterprise analysis actually describe?
You are the business analyst for your organization and you're working with your manager to discuss the constraints and assumptions that may affect the requirements. Your manager wants to know from where you've derived the list of constraints and assumptions. What's the best answer as to where assumptions and constraints are identified?
Martha is the business analyst for her organization and she's been asked to help create a SMART goal for her company. Which one of the following organizational goals could be considered SMART?
You are the business analyst for your organization. On your current project you'll be using the change-driven approach for defining requirements and gathering feedback. Which of the following statements best describes the change-driven approach?
Consider a business analyst who is completing the business analysis tasks of specifying and modeling requirements for an organization. This task can help an organization achieve all of the following objectives except for which one?
A business analyst needs to prepare the requirements package for her endeavor in a predefined template for her company. What term can be assigned to this standardized template for packaging the requirements?
You're organizing the business analysis approach for your organization. Jane wants to know when changes to requirements are most likely to happen in business analysis processes. Which one of the following statements best describes when changes to requirements may happen?
You are the business analyst for a large project that will create new software for the entire organization. This new software will affect all of the administrative assistants in the organization schedule meetings, reserve facilities, and share calendars. There are approximately 2,400administrative assistants in your organization and not all of these people can attend requirements gathering workshops. What approach can you use to manage and gather requirements from these 2,400 administrative assistants?
All of the following are documented approaches to business analysis work except for which one?
As a business analyst, you should be able to identify the characteristics of each business analysis task and domain area. Which one of the following statements best describes the characteristics of the business analysis knowledge area of requirements analysis?
You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis. Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?
You are the business analyst for your organization and you're performing the solution assessment process. When you assess a solution, what are you actually looking for?
You are the business analyst for your organization and you're working with Adam on business analysis processes. Adam is steeped in knowledge regarding the project's purpose. Of the following, what type of business analysis stakeholder is Adam?
You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus. Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour. What does the 25 workstations per hour represent in this scenario?
A business analyst wants to elicit requirements from a large group of stakeholders. One of her primary goals of this event is to produce a broad set of options for solutions. Which elicitation technique would you recommend for this business analyst?
You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?
If a requirement has been satisfied, why is it still considered a requirement?
Which solution scope creation technique can be best described as the depiction of the scope of work required to integrate the new solution into the business and technical environments?
John and Hanna are business analysts in their organization and they are completing the verification activities to check for completeness of the requirements. When should John and Hanna perform these verification activities?
Which element of the process of assessing the capability gaps is best described as gathering as much enterprise architecture information as is available about the current state of the organization and the areas affected by the business need?
When a business analyst completes the elicitation process, she will create four outputs. Which one of the following is an output of the elicitation process?
You are the business analyst for your organization and you've identified a business need. In order to satisfy this business need, you believe that your organization will need to hire three electrical engineers, purchase equipment, and likely provide training to existing resources. What process is being described in this scenario?
What elicitation technique is best described as a study to compare the strengths and weaknesses of an organization against its peers and competitors?
You are the business analyst for your organization and you're working with Nancy, the Sales Director. You've been identifying requirements for Nancy about the sales force and her desire to add a customer management solution to the sales process. Nancy believes that the software can help automate the sales process, keep things better organized than the current approach, and ultimately create more sales for the organization. As a business analyst, which one of the following should you advise Nancy about her need?
What should an organization do if the business analyst has determined that the existing capabilities are inadequate to seize an opportunity?
In the life of a project, when do the number and impact of change requests often increase?
Some of the requirements in the solution must be completed because of laws and regulations in your industry.
Management would like you, the business analyst, to rank the requirements according to the relevant laws. What type of requirements prioritization is management having you complete?
Two business analysts (BAs) are working on a requirement elicitation activity. One BA comes across a checklist that contains stakeholder details such as who are involved, location, group dynamics that are to be considered before beginning the elicitation activity and seeks a clarification from the second BA. The other BA explains that these details, along with several other items mentioned in the checklist, are required to:
You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which of the following are primary inputs of planning the business analysis approach?
Each correct answer represents a complete solution.
According to the business analysis book 'A Guide to the Business Analysis Body of Knowledge', which your exam is largely based on, almost all methodologies fit somewhere along a spectrum between plan-driven and what other methodology?
Which requirements allocation technique is best described as the breaking down of the solution scope into smaller units for allocation?
You are the business analyst for your organization and you're working with your team to define the business problem. As part of this analysis, you've identified the adverse impacts of the problem, the benefits from a
potential solution, and how quickly the problem could be solved. What other element should you consider?
Which stakeholder map shows the relative influence, impact, and relation of stakeholders by plotting them closer to or farther away from the solution?
You are the business analyst for your organization and you and your staff are creating as many solutions as possible to an identified problem in the solution approach process. What is this activity element called?
A business analyst (BA) was asked to send the requirement details to the project manager (PM), director, vice president (VP), and Chief Information Officer (CIO). The BA shares the complete set of requirements to the PM and director, while creating a summarized version for the VP and CIO. Which aspect of requirement specification and modeling was the BA performing?
A business analyst (BA) is compiling information about different approaches that will meet solution
requirements in order to make a recommendation for solution design. To evaluate whether externally available solutions meet the requirements, which of the following will the BA create and distribute?
The business analyst (BA) assigned to support a legacy system has developed a customer survey to assess its usability. Before distributing the survey, what should the BA do?
A business analyst (BA) needs to obtain agreement on and approval of requirements for a software solution. In order for this task to proceed, what does the BA need to understand?
A client wants to rehire a business analysis consulting firm for another project. The assigned business analyst (BA) developed a good rapport with the stakeholders, but delivered documents that contained lots of technical jargon that the client could not fully understand. Based on the feedback, the consulting company should:
The Business Requirements Document (BRD) prepared by the business analyst (BA) was circulated to stakeholders for approval. Some stakeholders objected to the Use Case diagrams and could not understand them. Why would these be included in the document?
A business analyst (BA) has documented the components of an information technology (IT) library, in preparation for establishing a consolidated catalogue of IT services. When interviewed, several of the IT managers indicated they already have a catalogue, and have no additional information to provide. What activity is necessary to support the project?
A business analyst (BA) is planning to elicit requirements. The BA understands the scope of the elicitation and has selected interviewing as an appropriate technique. Which of the following is part of the logistics for these interviews?
The business analyst (BA) recommended a new application be rolled out in phases. After reviewing alternatives, the project sponsor agreed. What does the BA expect to achieve by this approach?
A business analyst (BA) is defining a stakeholder approval approach for the requirement deliverables. The project involves implementing new government regulatory requirements with significant risk to the organization in case of non-compliance. According to the BABOK ® GUIDE, what will the BA need to do?
An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?
A business analyst (BA) is validating requirements and has found that the design cannot be validated to support the requirements. Which of the following is creating this situation?
During a project to replace an existing system, requirements for new functionality were elicited. Upon further investigation, additional types of requirements related to other features and characteristics were also identified. What can facilitate effectively understanding the different types of requirements?
A one-location restaurant has been a huge success and the owner wants to expand into more markets. The owner wants to ensure that the quality of the food and pleasing atmosphere is maintained without introducing new variables. Working with the key members of the organization, the owner determines that training and standard processes must be defined. The owner engages a business analyst (BA) to create training materials and operating procedures based on the existing processes at the original restaurant. During this documentation, the BA identifies some opportunities for improvement. How must the BA proceed?
Performance measures have been collected and analyzed by a business analyst (BA) to evaluate a solution that was launched a few years ago; however, the performance measures do not indicate whether or not the solution is contributing to the desired value. What is the recommended next step?
A business analyst (BA) is identifying the functions and features required for a new enterprise software solution. The BA reviews historical documents about the current business processes and then interviews each stakeholder group, individually, asking Questions about current business processes. The BA compares the information obtained during the stakeholder interviews with the information gathered from the historical documents. Which activity is the BA performing with this approach?
A business analyst (BA) creates several use case scenarios to specify the requirements for a system. When the beta version of the system is released, there are problems because several important pieces of information are missing. What should the BA have done to avoid this situation?
A business analyst (BA) is developing the requirements for an inventory management system. Some current accounting processes are automated but other departments like purchasing, marketing, sales and distribution departments work in isolation and have a manual process. They extensively use spreadsheets to maintain the transactions and at the end of the day the department managers manually verify and reconcile transactions before supplying the information to the accounting department. In order to verify and validate the elicited requirements, the BA will need to prepare a:
A business analyst (BA) is tasked with designing a method of ensuring that the requirements captured during the elicitation sessions satisfy the needs and expectations of the customer experience, within an initiative. The BA identifies a way that the stakeholder requirements can be structured to ensure realization of the desired customer experience. Which viewpoint describes the approach taken by the BA to structure the requirements?
A business analyst (BA) is working on a project involving the purchase of a commercial off-the-shelf (COTS) product. All internal risks have been identified and assessed. What is the BA's next course of action?
The business analyst (BA) has documented the requirements for a new system and is preparing the requirements for approval. Which of the following helps ensure that requirements are fully understood and traceable?
A business analyst (BA) is measuring solution performance of a new system. What should the BA consider to avoid skewed results and an inaccurate conclusion?
A business analyst (BA) identified that a stakeholder requirement for an online system led to a functional requirement to provide a user login screen. This is an example of which type of traceability relationship?
A business analyst (BA) is eliciting requirements for a pharmaceutical distribution company with an expansion plan across many states, each with their own tools and methods. To make the requirements as re-usable as possible, what should the BA do?
A global organization is implementing a new Knowledge Management System and communication to the different regions has been informal. The approach is to convert the few remaining regions iteratively. The team has experienced variances at this point but feels confident in these final conversions. How should the business analyst (BA) communicate the information?
A business analyst (BA) working with a large insurance corporation interviewed an industry thought leader who predicted that many of the regulations currently imposed by the government will change very soon. The BA carefully documented all these inputs from the thought leader because it will impact many of the strategic initiatives of the insurance company. What specific element of requirement validation is being executed by the BA?
A new regulation is introduced that the project must comply with to remain competitive and industry compliant. Management wants to understand the effect of this new requirement on the project. What will the business analyst (BA) use to evaluate the change?
A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?
During planning, elicitation, and sign off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in this process?
Before beginning requirements elicitation, a business analyst (BA) has planned the necessary activities, identified needed stakeholders, and documented this in the Business Analysis Plan. Which approach will help the BA ensure that stakeholders are available when required?
A business analyst (BA) is determining the current state as part of a new project. What is an internal enterprise asset that the BA must include in the analysis?
The business analyst (BA) has prepared a requirements package and it is now ready to present to the stakeholders. What is the purpose of presenting the package?
During the analysis, synthesis, and refinement of elicitation results the business analyst (BA) has discovered that some information is missing. Which course of action would resolve the situation?
A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?
A general insurance company wants to enter a new market that has the potential for high profit and little competition. The business analyst (BA) was asked to prepare a presentation for key stakeholders to show how the new segment will deliver value for stakeholders. Which of the following is best suited for this purpose?
A business analyst (BA) is in the process of specifying the confirmed results of a requirements elicitation workshop. Which of the following helps ensure that the correct information about the requirements is provided to the participants?
A new regulation results in organizations needing to change online contractual wording. A business analyst (BA) has elicited the requirements and documented them in a change control request. Where will the BA find out which stakeholder has the authority to approve, deny, or defer the change request?
A business analyst (BA) is proposing design options and a number of opportunities are occurring that need to be understood further. One particular opportunity will prevent different stakeholders from performing the same function in distinctly different ways. What type of opportunity is this?
A senior business analyst (BA) must review the requirements specification of a junior BA. The senior BA puts together a list of key evaluation criteria to guide the determination of a requirement’s quality. Which of the criteria below is a characteristic of a quality requirement?
Stakeholder requirements were approved for a business process reengineering initiative along with the creation of a roadmap. Due to market conditions, the product roadmap is modified to move the default process to the next iteration. What should the business analyst (BA) update in the stakeholder requirements?
A business analyst (BA) elicits requirements from end users for a new application and then documents a set of use cases and use case scenarios. What should the BA do next?
Two stakeholders are arguing over which model to use for requirements. One insists that using an activity diagram is superior, while the other prefers a state diagram. How should the business analyst (BA) resolve the conflict?
A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?
The business analysis (BA) team is evaluating a new commercial off-the-shelf (COTS) application that will be implemented in the coming months. The company has over 20 legacy systems deployed. The Chief Information Officer (CIO) is worried about the need for integration and that some key linkages are missing.
What is the BA team evaluating?
A business analyst (BA) has been asked to develop a plan to complete the associated business analysis activities for a project in which an organization is switching from a manual to an automated process for receiving payments. As the final step in developing the plan, which technique will the BA use?
The business analyst (BA) is analyzing the formal relationships between people working in the enterprise. Which technique will the BA use to perform this task?
A business analyst (BA) worked with two stakeholders to finalize the access rights related requirements for an internal software application. According to the first stakeholder “Comments, once entered in the application, should be stored for 365 days and should not allow the users to delete”. According to the second stakeholder, “The users with super administrator privileges should be able to add/delete/modify every page/section in the entire application.” Which characteristic does this pair of requirements fail to meet?
A business analyst (BA) has elicited non-functional information for a system's replacement. In reviewing the elicitation results, the BA finds the number of concurrent users is a large portion of the target user group, which seems high. How should the BA proceed?
A project is being initiated to create new financial reports for the accounting department, and the accountants have a wide range of views as to what would serve them best. What should the business analyst (BA) do to develop the correct set of requirements?
A business analyst (BA) is working on a project involving the purchase of a commercial off-the-shelf (COTS) product. All internal risks have been identified and assessed. What is the BA's next course of action?
A business analyst (BA) is assigned a new project and is beginning to prepare for elicitation. Which task must the BA complete before preparation of the elicitation process can begin?
A business analyst (BA) is planning how to present a set of requirements for a project with financial constraints. Which requirements attribute should the BA assign to allow cost implications to be assessed?
During planning, elicitation, and sign-off of requirements, the stakeholders felt that their opinions were not heard and information was not frequently shared. What major competency was lacking in this process?
A business analyst (BA) is identifying the functions and features required for a new enterprise software solution. The BA reviews historical documents about the current business processes and then interviews each stakeholder group individually, asking questions about current business processes. The BA compares the information during the stakeholder interviews with the information gathered from the historical documents. Which activity is the BA performing with this approach?
While planning the prioritization approach for an upgrade to a legal property application, the business analyst (BA) needs to check the organization's business policies prior to identifying the stakeholders to participate in the prioritization process. The business policies will help the BA because they:
The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (BA) what would improve the stakeholder's ability to understand the requirements. Which of the following will improve the requirements quality?
A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company's risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors. What is the company's attitude toward risk, as assessed by the BA?
A business analyst (BA) has been tasked with examining and analyzing the relationship between a set of requirements by verifying that they are unambiguous. What will the BA be looking for?
A new Chief Executive Officer (CEO) is appointed to revive a chain of well-recognized superstores. The CEO wants to increase sales by introducing online shopping. Most stores are understaffed, and maintenance is a challenge. Which of the following would be considered an asset?
A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline. What must the BA do to ensure maximum business value?
A project team needs to maintain the traceability of requirements for a software system. Due to the large number of requirements, which of the following methods should the team use?
A project manager (PM) is planning the project timelines along with a business analyst (BA), and they come across the task of requirement allocation. The PM wants to know what the dependencies are before the requirement allocation task is initiated and seeks the BA's advice. Which of the following is a dependency that the BA will highlight as a prerequisite for requirement allocation?
A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 100-page document with models and business rules to all stakeholders. Which best practice did the BA violate in this situation?
The business analyst (BA) has prepared a requirements package, and it is now ready to present to the stakeholders. What is the purpose of presenting the package?
The human resources department of an organization needs a new report. The business analyst (BA) assigned to this effort has scheduled a requirements workshop with the users. Users from the legal department have also been invited to the workshop. As the BA sets up the workshop, what can be done in advance to ensure a productive and focused workshop?
A business analyst (BA) is preparing an analysis approach to replace a 12-year-old air traffic control system. The BA aims to define the solution definition before implementation, capture theinformation in standardized templates, and ensure that all activities are identified first and then divided into tasks. Which approach provides the appropriate level of formality for this project?
A lead business analyst (BA) has received negative feedback on the deliverables produced by BAs in the organization. A major concern was ambiguous requirements. What technique will help ensure business analysis information is clear and understandable?
Market studies projected a 28% year-over-year growth for five (5) years for commercial vehicle loans. A company that provides lending for commercial vehicles wanted to keep up with industrydemand; however, their applications were not capable of scaling to the increased demand for loan processing and billing. The company is deploying a new system to meet the demand. The project started five (5) years ago and cost $2 million USD. The project metrics are to be evaluated after five (5) years. The return on investment (ROI) for the project is calculated at 11%. The project sponsors are upset that the desired ROI for the project was not met. What was the root cause of this issue?
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
A business analyst (BA) is facilitating a meeting with subject matter experts (SMEs) in which the SMEs are answering questions about the major business processes and associated activities the business performs. The BA will create a deliverable from this discussion that will assist in defining scope. What technique is the BA using?
A business analyst (BA) has elicited the following requirement: "The solution must ensure the portal response times are under 2 seconds." What requirement classification schema does this requirement belong to?
A business analyst (BA) has spent the week conducting work sessions with key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure that they have been correctly defined and documented. Which of the following describes the purpose of their work?
A recent survey shows that a newly implemented system has features that the users have never used. Upon reviewing the survey report, the Chief Executive Officer (CEO) highlighted that the company must avoid future implementations with functionality that does not provide any business value. What must the business analyst (BA) do to ensure future requirements meet a business need?
A business analyst (BA) has recently joined a large consultancy firm where BAs are globally distributed on different assignments. Where would the BA find expectations for business analysis work as mandated by the consultancy firm?
A business analyst (BA) is managing stakeholder collaboration to ensure positive reactions are capitalized upon. There is uncertainty as to whether the correct stakeholders have been identified. Which technique can be used to correct this situation?
A business analyst (BA) has set up a number of elicitation workshops with key subject matter experts (SMEs) on a new project. All SMEs have accepted the workshop invitations except forthe legal SME, who has not responded to any invitations. The first workshop is scheduled for next week, and the BA has tried unsuccessfully to reach the legal SME by phone. How should the BA proceed?
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?
Bonny is the business analyst for her organization and she's making a determination from which vendor the solution should be purchased. She has identified several categories to measure each vendor's overall performance and solution. cost, schedule, experience, certification, references, and years in business. For each category, she has identified scores the vendor may earn; for example, cost is worth 25 points, schedule is worth up to 20 points, and years in business is worth up to ten points. The vendor who gets the most points in the assessment will win the contract. What is Bonny using in this scenario?
You are a business analyst for your organization. Your current business analysis endeavor includes working with stakeholders located in offices around the world. Because these stakeholders are dispersed, what is likely to increase in this endeavor as opposed to a collocated group of stakeholders?
One of the techniques to assess capabilities in an organization is to use SWOT. What does SWOT accomplish?
You are the business analyst for your organization and you've been working with several stakeholders to
gather requirements for approval.
The requirements have been approved with the exception of a conflict on one requirement. What must you and the stakeholders do in regard to this conflict before the business analysis endeavor may continue?
A business analyst (BA) is logging the end user concerns and resolves these on a priority basis as mandated by the government. This project is a simple application, with no major strategic or financial impact to the organization. The BA strongly enforced end-to-end requirement traceability for this project. Why would the BA recommend this traceability approach?
A business analyst (BA) is developing requirements for a project with a limited budget. The business owner will be prioritizing requirements so that low value requirements can be de-scoped and the project remain within budget. Which of the following should the BA take into account to facilitate prioritization and ensure business objectives are met?
A business analyst (BA) is working on a project that has a number of stakeholder conflicts and issues. The BA is finding it difficult to resolve the conflicts and issues effectively. What should the BA do to prevent a similar situation in the future?
The following chart represents attendance of subject matter experts (SME) and the solution owner for a requirements review and approval meeting held weekly by a business analyst (BA).
The requirements package was approved by the solution owner during the May 30 meeting. After implementation of the solution, the BA learns that the users in SME-3 s area are not using the system. Which business analysis activity should the BA have monitored more closely to mitigate this situation?
An organization's board of directors has funded a new mobile application to support external customers. The business case was developed with emphasis on objectives to broaden the organization's brand and increase customer engagement. The business analyst (BA) is reviewing a group of user stories with the product owner. One of these user stories is: "As a customer service representative, I need to enter my time on the mobile application so that I can leave work to pick up my sick daughter from school". The product owner wants to take advantage of this opportunity to provide the staff a way to enter their time away from the office and create an interface to the Payroll application. How must the BA evaluate alignment with the existing scope?
After a walk-through of the requirements specification with the business users, the group determines that five requirements are now mandatory due to new government regulations. What should the business analyst (BA) do following the meeting?
The director of a furniture store manages a group of skilled carpenters who make furniture from locally available materials. The director decides to automate its inventory processes so that carpenters can place orders for raw materials themselves. A business analyst (BA) is engaged to define the requirements and propose options for commercial off-the-shelf (COTS) inventory management solutions. After meeting with the director, the BA needs to schedule a workshop with the carpenters to:
The business analyst (BA) has an item logged in the action items register requiring the verification of forthcoming legislation in the next 3 months that might have an impact on the proposed architecture. What should the BA do next?
A business analyst (BA) decided to capture requirements by inviting all the stakeholders to meet at an office location. After invitations were sent, it turned out that not everyone could attend this meeting because of their individual dispersed locations.
Which of the following does the BA need to adjust to handle this situation?
A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities. Which element of stakeholder management is the BA performing?
A business analyst (BA) is planning how to present a set of requirements for a project with financial constraints. Which requirements attribute should the BA assign to allow cost implications to be assessed?
A new product that is tablet-enabled is being considered to replace an older product to process orders. The data captured is sent to existing downstream applications which are not being updated. What is the first thing that a business analyst (BA) should consider?
A deployed loan product was funded with the expectation of prepayment risk reduction. Initially key performance indicators would be to take similar loan prepayment rates over the previous 10-year period and compare it with the new product. After implementation, the business analyst (BA) determines that the decade old housing market is vastly different. Which of the following should the BA consider for validity of performance measures?
A company wants to launch a new product that will have similar features to an existing product. A business analyst (BA) working on the project has invited the product manager to explain the features and business rules of the new product. Which activity must the BA perform in preparation of the session?
During a lesson learned session, stakeholders had a heated discussion on the performance measures being employed and why they are necessary. The business analyst (BA) explained that performance measures are required to:
The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help move the project forward?
A business analyst (BA) is tasked with performing a gap analysis between two existing systems to combine into a single system or run just one system. Which of the following modelling formats will show the requirements for both systems side by side?
A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?
The claims intake workflow of an insurance company is being standardized across all branch offices. The business analyst (BA) assigned to this project has interviewed users individually in all the offices and plans to schedule a workshop with all the users. What should the BA do to prepare for the workshop?
The business analyst (BA) has structured information so it is easy to find, does not conflict with other information, and is not duplicated unnecessarily. Which additional factor does the BA need to take into account when deciding how to structure the information?
A project team member is confused about why a small change requires the team to look at the different enterprise-level business objectives when a desired state can be achieved easily without this analysis. What can the business analyst (6A) do to help the team member understand?
A project manager asks a business analyst (BA) to conduct a meeting to walk the stakeholders through how requirements are structured. Which of the following requirement viewpoints will help the BA provide that information?
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
A business analyst (BA) has spent the week conducting work sessions with a project's key stakeholders. Together, they have been reviewing user requirements and high-level design flowcharts to ensure that they have been correctly defined and documented. Which of the following describes the purpose of their work?
The project manager has tasked the business analyst (BA) to collect a performance measure on the solution implemented in the latest release. Which of the following considerations can help the BA obtain that information?
A business analyst (BA) develops a template to document the product feature requirements for an enterprise software solution. Within the template, the BA includes the following additional information: source, priority level, level of complexity, and last modified date. What does the additional information describe?
A recent survey shows that a newly implemented system has features that the users have never used. Upon reviewing the survey report, the Chief Executive Officer (CEO) highlighted that the company must avoid future implementations with functionality that does not provide any business value. What must the business analyst (BA) do to ensure future requirements meet a business need?
A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?
A business owner has marked certain requirements as high priority for the upcoming release. After performing some analysis, the project team concluded that some of these requirements are not actually high priority and can be implemented in later releases. How should the project team proceed with prioritizing requirements?
A business analyst (BA) plans to organize a focus group to bring all the interested parties together and discuss the issues and possible risks for the new initiative. Due to the geographical differences of each participant a videoconferencing service will be used to satisfy stakeholder preferences. Which approach is the BA defining?
A business analyst (BA) asked two stakeholders with approval authority to approve the requirements. The stakeholders are being asked to confirm that:
A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 600-page document with models and business rules to all stakeholders. Which best practice did the BA violate in this situation?
A business analyst (BA) is defining relationships between business requirements and solution components. Which guideline will the BA use to accomplish this?
An organization has hired a consulting firm to implement and customize a software solution they purchased. The firm has raised concerns regarding the effort required to develop a solution that meets all requirements. On what basis should the requirements be prioritized in this context?
A business. analyst (BA) is working on a project to implement a commercial off-the-shelf application for tracking customers. In an observation session with a Domain subject matter expert (SMF). the BA notes that the SME keeps separate records for the customers who are also vendors. The BA knows that the new software has a module for vendor management that would integrate the vendor and customer records. Which type of opportunity has the BA identified?