3 Months Free Update
3 Months Free Update
3 Months Free Update
You are reviewing the project's traceability matrix after the first cycle of testing. You have discovered that new requirements have been introduced and others have
changed.
What should you do? [2]
You have been looking at the actual vs expected defects in one high risk area of the software The actual is much higher than the expected value What should you do?
You are the Test Manager for a software house (SoftTech), who provide a core banking product to retail banks around the world to enable their customers to process payments via the Internet and telephone banking.
Your current project is to integrate SoftTech's core banking product with Welsh Bank's existing bank systems. However, Welsh Bank's systems are maintained by experienced developers and are poorly documented.
Welsh Bank has stated that this project must comply with Financial Conduct Authority (FCA) regulatory banking standards.
A specification for the 10 interfaces to Welsh Bank's existing systems has been produced by SoftTech's development team.
You have been asked to plan and conduct reviews for the system integration and support documentation of all the systems. Which of the following is the BEST approach for this project?
SELECT ONE OPTION
Your test team has created a custom automation tool that will be used for an upcoming release. Now that the tool has been coded, what
should be the next step? [1]
Which two of the following activities would normally occur in the Acquisition stage of a tool's lifecycle?
a) Assign a tool administrator to decide on best use of the tool
b) Establish a backup and restore strategy for the tool
c) Review other tools provided by the same vendor
d) Determine how the tool may be impacted by a change to the operating environment
e) Develop and implement a training plan for new users of the tool
SELECT ONE OPTION
You plan to introduce a new tester to your Agile team who has expertise in test automation, a necessary skill lacking in current team members. The individual has a high degree of technical competence but has only ever worked alone and admits to finding face-to-face communication difficult.
What would be the BEST course of action?
Assuming that 'In progress' means that somebody is working on a fix and that 'Resolved' means that the fix passed the confirmation test; which option provides a defect workflow that flows in a sensible way from an initial state to a terminal state?
Assume that you are part of a team conducting test design for a new university system that will allow students to update their own personal information. The Test
Strategy states that positive and negative testing should be carried out. along with performance, security and interoperability testing against all new requirements.
The following requirements have been identified by stakeholders:
1. Students must be able to make changes to the following information:
a Name (due to marital status)
b Marital status
c. Home address
d. Home telephone number
e. Email address
f. Mobile telephone number
g. Contact details in case of emergency
2 Only Reception staff must have access to the information held.
3 The system must support 2000 concurrent users and details updated on the system within 20 seconds.
4. Interoperability of the new system with the other systems maintained by the University for student Registrations.
Test analysis for functional and non-functional testing has iust bequn and the following test conditions have been identified:
Which one of the following is a valid test condition that is missing from the table of test conditions and has clear traceability back to the test strategy and requirements?
SELECT ONE OPTION
Test Analysts are doing test design for a change request to an insurance comparison system. The system provides car insurance quotations, using data input by the user.
The change request states:-
Drivers must be aged between 17 to 85 years inclusive to qualify for insurance comparison.
The following Test Conditions have been identified:
1 Driver's age is less than the minimum
2. Driver's age is within the valid range
3. Driver's age is more than the maximum
The Test Strategy states the test techniques to be used include Equivalence Partitioning and Boundary Value Analysis. Using the Test Conditions and techniques stated in the Test Strategy, the following Test Cases have been created.
As the Test Manager you are reviewing these Test Cases for traceability to the Test Conditions and to ensure that the change request will be adequately tested in accordance with the Test Strategy.
Which of the following statements is FALSE? SELECT ONE OPTION
You are testing a new product that will turn on the windshield wipers of a car when the sensors detect there is moisture on the windshield. Depending on the information
returned from the sensors, the wipers will be turned on at one of the following speeds: slow intermittent, medium intermittent, fast intermittent, slow constant, medium
constant, fast constant. Your team has identified the following test condition:
Test Condition 1.1.1 - Verify that the windshield wipers can go from slow constant to fast constant speed when the amount of moisture increases appropriately.
Your team has defined the following steps for a test case for this test condition:
1. Set the moisture sensor to request slow constant
2. Increase the moisture to set the sensor to request fast constant
3. Verify that the wipers respond with fast constant speed
Given this information, which of the following statements is correct? [2]
There is a debate in your organization about who can close a defect report The developers think they should be able to reject and close defects without any further steps The testers are not happy with this approach as they are afraid the rejections may go undetected and the developers may close something without understanding the real problem
How can this problem be rectified7
A test team is working long hours to achieve a deadline for release of a new product which has had problems throughout development and is well behind schedule. Which of the following is most likely to have a MOTIVATING effect on the testers in the team?
SELECT ONE OPTION
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but
it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development
team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be
watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate
for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]
You have initiated a test process improvement project for your organisation using the STEP model. You have agreed the objectives, goals, scope and coverage of the process improvements with the stakeholders and defined the success criteria that will be applied to the project. Success criteria make risk reduction the most important target benefit for the process improvements, but overall return on investment is also an important consideration. You have just received the initial test
assessment report.
Which ONE of the following would be the next step? SELECT ONE OPTION
Which of the following BEST explains how test process improvement can benefit an organisation? SELECT ONE OPTION
Refer to SCENARIO 1
Week 4 of test execution has been completed and the following test report has been produced
Review this report against the organisational Test Strategy, what is the status of the Test Strategy objectives? SELECT ONE OPTION
As test manager, you need to determine if there are likely to be new security risks arising from proposed changes to an in-house purchasing application. You invite a security testing consultant, who is external to the organisation, to assess the changes and provide you with their written report of perceived security risks.
Which risk identification technique are you using?
As the Test Manager working for a company developing safety related software for defence equipment, you have been asked to consider how you can track test progress and report on the following:
1) Test cases adequately cover all requirements
2) Issues relating to safety critical vulnerabilities are being addressed in priority order
3) How much of the developed system has been exercised through testing What tools would help to achieve this?
SELECT ONE OPTION
Which of the following is a key characteristic of a management review? [1]
Which work experience is likely to develop the necessary skills to effectively test a software system? [3]
You have recently implemented a new defect management process which now includes a defect triage committee whose job is to review all new defects. The process is shown in the following diagram:
b. The total number of defects rejected as not a problem following investigation by the product author
c. The number of defects returned to the defect author, expressed as a percentage of all defects raised
d. The total number of defects that failed re-test more than once
e. The total number of defects closed by the defect triage committee
SELECT ONE OPTION
Which of the following Is a way in which risk analysis drives test analysis?
When closing out a defect report, which of the following developer commentaries is most likely to motivate a tester? [1]
As the Test Manager for an agile project how would you BEST plan and guide the testing activities during development? SELECT ONE OPTION
What is the primary use for the traceability information regarding the relationship between test results and test conditions during test execution? [2]
SCENARIO 1
DreamPartner dating agency are redesigning their dating application following a major security breach in which sensitive customer data was made publically available. The redesign includes stronger security encryption and performance tuning.
The product risk register for the redesign project, which was produced after all requirements had been agreed, includes the following:
The organisational Test Strategy contains the following objectives:
1. A Risk-based lest approach must be adopted for all projects
2. Functional regression testing should start as soon as functional testing is complete
3. Automated tests may be run before or in parallel with manual tests
The project Test Plan has allocated 6 weeks to complete all test execution, with functional testing taking 3 weeks to execute, performance and security testing 2 weeks each and regression testing 1 week.
Which of the following options places the test suites (TS1 to TS5) in the correct order for test execution?
SELECT ONE OPTION
SoftTech provides a core banking product to retail banks to enable their customers to process payments via the Internet and telephone banking and. as SoftTech's Test Manager, you are responsible for system testing and system integration testing of all SoftTech's products.
Your current project is to integrate SoftTech's core banking product with an existing bank's systems, which are maintained by experienced developers but poorly
documented.
A specification for the 10 interfaces to the bank's existing systems has been produced by SoftTech's development team. There is an estimating matrix for system integration testing that allows 2 man days per interface for preparation, plus 2 man days per interface for test execution. The exit criteria for the completion of system integration testing has been agreed as:
1. No open Severity 1 defects
2 No more than 10 open severity 2 and/or 3 defects
3. All interfaces tested
4. Cost estimate must not be exceeded
System integration test execution is scheduled to last 5 weeks, with week 5 reserved for regression and bug fixing only. At the end of week 3 the following test report has been produced (figures on a week by week basis, not cumulative):
B. Open severity 2 and 3 defects
c. Interface testing progress
d. Development resource for debugging
e. Available budget
SELECT ONE OPTION
Which of the Mowing should be used to understand the context of testing within an organization?
You are a new lest manager in an organization You have been asked to assess the defect process to determine if there are any efficiency improvements that could be made that would reduce the cost of quality You have started digging through the defect Information What information would be most helpful for this investigation?
One of your team members is struggling to identify the requirements to be tested for a project The requirements documents are not conventional but you have determined that the data is there. If they do some digging to find it Given this information in what competence area does this person need to improve?
You have been asked to make a recommendation on deployment readiness on the software your team has been testing.You have the following metrics:
Given this information what is a critical metric you are missing?
Which of the following metrics would be most beneficial to collect to determine the effectiveness of a review process? [2]
Which of the following is the proper order for the stages of a tool lifecycle?
Your test process is fully integrated into the software development lifecycle. You are at which TMMi level? [1]
An old stock control system is being decommissioned and replaced with a new system that has been running successfully in the live environment for the last few months. The stakeholders would like to -
• retain historical information held in the database to comply with their data retention policy (which requires order information to be retained for 7 years)
• query the historical information by running pre-written SQL queries.
• all commands must be invoked by keyboard as one of the end users is unable to use a mouse
The pre-written SQL queries will be designed, developed and tested by the developers who are decommissioning the system and writing the data migration routine.
As the system to be decommissioned is integrated to other systems that will remain operational, the stakeholders have requested that testing incorporates all systems that are part of the stock control suite.
The stakeholders and project manager have identified the following risks, in priority order -
• 1st - Data has not been successfully migrated to an archived data store, resulting in the inability to query past stock levels and re-order details.
• 2nd - Historical data for the last 7 years is unavailable, resulting in the failure to meet the data retention policy.
• 3rd - Failure of existing systems within the stock control suite, adversely affecting the operational running of the business
The risks are to form the basis of the test objectives. Which three of the following test activities, work products and/or resources achieves the test objectives?
a. Use of the live database to test the data migration does not corrupt or lose data
b. A test plan detailing the test approach for ST. SIT & OT test levels
c. Accessibility testing of the pre-defined SQL queries
d. Security and Penetration testing of the archived database
e Performance testing of the data migration exercise to ensure it completes in the time specified by the stakeholders
f. Functional testing of the pre-defined SQL queries
g. Regression testing of the end to end process for maintaining specified stock levels.
The Test Manager must assemble team members that have which of the following characteristics? [1]
You have decided to help your team improve their skills. One of their assignments is to mentor a junior member of the team Which competency should you expect the mentor to develop during this exercise?
In an Agile project, when Is it acceptable lo not write a formal defect report when a defect is found''
If you are monitoring code coverage during testing to determine what areas still need testing what type of testing is likely occurring?
You tend to be conservative in your project estimations because you know how many things can go wrong and extend the schedule. You manager is not happy with your estimates and thinks you are being too negative with your numbers and not trying hard enough Which estimation method should you use to provide your manager with a positive' number while still also providing the number you think is more realistic?
You are working In an environment that is continually pushing process improvements down to the lest team You are skeptical that any of these have actually accomplished any improvement In fact you know that some of the changes have actually impaired progress
Given this information what step of the IDEAL model is missing?
You are working on a project where the business part of the organization works traditionally with defined requirements, but the development team follows an Agile model Neither team plans to change their approach What is the proper name for this type of project approach''
You are working with a development team who have a CI/CD pipeline implemented. They want to integrate your team's existing test automation into the pipeline to augment their unit tests so they will have continuous testing. They have already determined that this is technically possible with the tool you are using but with require some changes to the test automation framework to integrate the results reporting
What will your team need to make this happen?
You have been seeing a high number of rejections of defect reports The developers are complaining that they do not understand what the problem is. even though they have been supplied with screenshots. You have checked a number of the 'problem' defect reports and have not found any information that is missing. The descriptions are very detailed and include all the necessary information in a long descriptive paragraph.
What change should you recommend that should help with the developer s problems?
Your team has been assigned to test a loyalty card program for a supermarket chain. Because this is a highly competitive market significant investment has been made to determine the shortcomings of the products offered by competitors While the feature sets are mostly the same, there is a wide variance In usability and performance and the users perceptions of these quality characteristics
Given only this information what test approach would be most appropriate?
You have been asked to estimate the testing effort for an upgrade to a legacy product Your team did the testing on the last upgrade, and you have ascertained that this upgrade is about 10% bigger than the last one Given this information which estimation technique should you use to come up with the test effort number?
You have assembled the following cost of quality numbers 1 000 defects were found prior to release and 100 were found after.
Given this information what should you conclude?
Your team has decided that they will build their own test management tool This will allow them to link the requirements and test cases together providing full traceability It will also allow them to create fully customized reporting and color-coded dashboards They have estimated the time required to create the new tool and the cost These fit within the project schedule and budget
What other consideration should be taken before this decision is made?
Your manager has decided that your team of manual testers should all become test automation engineers Your team is much stronger in analysis than In technical testing so you are concerned about their ability to adapt. What tool capabilities could help with this transition?
It the lest manager must repeatedly step in to resolve conflicts within the team what phase is the team in and what competencies are required from the test manager?
Which of the following is required to apply an experience-based testing approach''
You are looking to Improve the efficiency of testing. The developers have been claiming that the majority of defect reports they receive are invalid either due to the test environment or because the tester did not follow the right steps In a standard defect management process where should you look for more information about these invalid defects?
Your defect opened trend is converging to the closed trend but there is still a gap. What does that gap represent?
Your organization has decided to augment your testing team with an offshore team. The offshore team members are experienced testers who are experts in the domain of the system under test Your team is worried about the offshore team taking their jobs and they are resistant to the change You need to pick three of your team members to be the ambassadors for the new team
Which competences will be most important for your ambassadors to possess?
In what environment are you most likely to see multiple defect management systems used in one project?