We at Crack4sure are committed to giving students who are preparing for the Nokia PDM_2002001060 Exam the most current and reliable questions . To help people study, we've made some of our CPM exam materials available for free to everyone. You can take the Free PDM_2002001060 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
At a given point in time, a project has a CPI = 0.7 and SV = €1,000. The project is:
The WBS comprises several levels of decomposition of the total project. The lowest level of definition is always the:
Through which tool and what trigger is supplier work accepted for project business?
A project plan is a:
What is the duration of short term planning (STP) period?
The estimated value of the work actually accomplished is:
In 4C internal resources are planned as:
For which of the following reasons can the cost baseline be updated?
What is the best demonstration that you are in control of your financial processes?
What is NOT included in a basic project cost report?
What is a liable party?
Which resource type is handled by the tempus process?
Change requests should not occur due to:
If Net Sales are €150 and Cost of Goods Sold are €100, what is the Gross Profit in %?
When should risk analysis be performed?
What of the following options is the most appropriate course of action when the project subcontracting cost to date exceeds the plan in the CBL?
A Project is:
The project is not completed until:
The compilation and storage of lessons learned for a completed project can be used to:
What is typically NOT processed in the project cost management tool as a project change?
Company A is working on a project. The project‘s budget is €10,000. The planned value as of date X is €4,000. The project is 30% completed. 60% of the budget has been spent to date X. The Earned Value (EV) of the project is:
What approval process is required when the EAC deviates >2% from the CBL?
Which of the following examples will cause a decline in project cost adherence (PCA)?
What is NOT a key element for the lower level WBS structure set up in SAP from a cost and progress manager perspective?
During project setup, an identified risk event with a 100% probability of occurrence is:
Which of the following KPIs is NOT reported by the cost and progress manager?