Labour Day Special - 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: c4sdisc65

Note! SDM_2002001050 has been withdrawn.

SDM_2002001050 Practice Exam Questions with Answers SDM Certification - NI Certification

Question # 6

As far as project meetings are concerned which of the following statements is correct?

A.

Due to cost saving measures I only organise project team meetings if major changes in scope or timeline occur from customer side.

B.

I'm organising regular project team meetings to keep the project team fully informed about the project’s progress at a detailed level and to check if any re-planning and/or modification of the project plan is required.

C.

I'm organising regular project team meetings in order to have a feeling about the progress of the different streams in my project.

D.

In the regularly organised project team meetings my major focus is to check the performance of the project team members.

Full Access
Question # 7

What impact can be expected during the execution of projects for which the scope of work is not clearly defined ?

A.

No impact.

B.

Non Conformance costs due to not planned extra works.

C.

Original Project Time Frame cannot be kept due to additional clarification meetings.

D.

Additional Efforts due to intensive Change Management.

Full Access
Question # 8

Which milestone(s) must be completed before invoicing?

A.

Provisional Acceptance.

B.

Final Acceptance.

C.

Internal Acceptance.

D.

It depends on the Contract.

Full Access
Question # 9

Before which approval gate you have best possible influence on risks and the related costs?

A.

Gate 4.

B.

Gate 5.

C.

Gate 6.

D.

Project closing.

Full Access
Question # 10

What is the purpose of the Change Management module of IPM?

A.

Tracking additional Resources

B.

Tracking additional PO's for suppliers due to Quality issues.

C.

Documentation tracking

D.

Track and follow up of deviations from baselines

Full Access
Question # 11

A subcontractor approved and selected by Procurement is working for your Project but delivering installations with too many items in the Punch List. Which of the following actions would you choose first?

A.

Disqualify the company and ask Procurement for a new supplier.

B.

Stop the payment for this subcontractor until quality issues are solved.

C.

Cancel new PO's to this subcontractor.

D.

Refer to the contractual Quality Requirements and develop a recovery plan with the Subcontractor.

Full Access
Question # 12

What does it mean if Schedule Performance Index (SPI) is greater than 1?

A.

Very good progress as the project is ahead of schedule.

B.

Cost Overrun as the rollout is ahead.

C.

Cost Saving as the project will finish earlier.

D.

That deviations in the rollout are impacting the accuracy of cost forecast negatively.

Full Access
Question # 13

What is the basic source of information for the development of the Quality Plan?

A.

Project quality and acceptance requirements stated in the current customer contract.

B.

Equipment installation manuals.

C.

Templates from NSN PM Compass.

D.

Experience from previous projects executed with the same Customer.

Full Access
Question # 14

In case a customer contract is not yet signed and a PO has not been received yet, in which circumstances can a service be subcontracted ?

A.

If the value of the Purchase Order does not exceed the approved cost baseline.

B.

If an Early Ramp-up Project (ERP) was approved.

C.

If subcontractor agrees to receive his PO later, after the customer PO is issued.

D.

If there is a formal approval from the Project Manager.

Full Access
Question # 15

What is ROLLO?

A.

Rollo is the official NI tool for planning and tracking a Customer Project rollout.

B.

Rollo is the official NI tool for risk management of a Customer Project rollout.

C.

Rollo is the official NI tool for sales forecasting of a Customer Project rollout.

D.

Rollo is the official NI tool for quality management of a Customer Project rollout.

Full Access
Question # 16

Why is the Project Resource Plan required during the 'Create Customer Solution' Phase?

A.

To initiate recruitment of project team.

B.

In order to make a services cost calculation.

C.

To reserve resources from Resource Manager.

D.

To reserve subcontractor resources.

Full Access
Question # 17

Which one of the following is NOT a risk?

A.

Customer might run in environmental issues with the municipality due to our product and missing ISO14000 certification.

B.

Our Subcontractor might charge us for the extra site visits as this particular case is not written down in our supply contract.

C.

Logistic has informed the project that the delivery which was expected last week has not arrivedyet.

D.

The acceptance criteria's in the contract amendment might lead to additional effort as it's wording could be misunderstood.

Full Access
Question # 18

Which of the following is included in the scope statement?

A.

Cost baseline.

B.

Project quality plan.

C.

Project plan.

D.

Project deliverables.

Full Access
Question # 19

What is the KPI generated out of the Site Quality module of IPM?

A.

RA - Rollout Accuracy.

B.

P-SQI - Project Site Quality Index.

C.

SILT - Site Invoice Lead Time.

D.

TILT - Telecom Implementation Lead Time.

Full Access
Question # 20

When should the costs be recognized according to the IPM process?

A.

When Internal Acceptance is granted.

B.

When the invoice from the subcontractor is received.

C.

When the Purchase Order is created and sent to the subcontractor.

D.

When the subcontractor confirms the reception of the Purchase Order.

Full Access
Question # 21

What is the recommended action when customer asks for a consistency check to his network planning files which was not included in NSN scope of work?

A.

Execute if there is a risk to harm the customer satisfaction.

B.

Initiate the Change Management Process.

C.

Execute but only with formal approval of the Project Manager.

D.

Execute if the task will not have a significant impact on the project cost and keep customer happy.

Full Access
Question # 22

Who is primarily accountable for maintaining the NELLE tool data properly?

A.

Project manager.

B.

COM.

C.

CT F&C.

D.

Care Manager.

Full Access
Question # 23

Who is primarily accountable for maintaining ROLLO tool data properly?

A.

Process & Tools specialist.

B.

Project quality engineer.

C.

Implementation manager.

D.

Rollout manager or project director.

Full Access
Question # 24

Which effort is contributing to reduce the project asset levels and hence improve project cash flow performance of an NI project?

A.

Combining different customer acceptances in order to bundle customer invoices.

B.

Making sure all "task completed" milestones are updated in IPM without delay.

C.

Ensuring that local project warehouse never runs out of inventory.

D.

Ensuring that the equipment is delivered to the site at least 2 days before the site will be ready for installation.

Full Access