Question # 6

As part of the agreement with one of your suppliers, you must always order product by the 100s. For example, if the required supply is 105, you must order 200, if it's 275, you must order 300. Which item attributes will help you achieve this?

A.

Minimum Order Quantity

B.

Fixed Lot Size Multiplier

C.

Maximum Order Quantity

D.

Fixed Order Quantity

E.

Rounding

Full Access
Question # 7

It is now January 2023. Your customer has loaded 3 years worth of shipment history (for 1/1/20 through 12/31/22) and wants to generate a monthly forecast for 2023 based on two years of shipment history.

When creating a demand plan, which two plan scope and demand plan options should your customer use? (Choose two.)

A.

For demand plan option, add forecast shipments as forecasting profile, and enter historical buckets as 24.

B.

For demand plan option, add forecast shipments as forecasting profile, enter history start date as 1/1/21. forecast start date as 1/1/23. and enter forecast end date as 12/31/23.

C.

For demand plan option, add forecast shipments as forecasting profile, enter history start date as 1/1/21. enter history end date as 12/31/22. and enter forecast start date as 1/1/23.

D.

For demand plan option, add forecast shipments as forecasting profile, enter historical buckets as 24. and enter forecast buckets as 12.

E.

For plan scope, select plan horizon as 12 months, forecasting calendar as Gregorian, and forecasting time level as month.

F.

For plan scope, select plan horizon days as 365. forecasting calendar as Gregorian, and forecasting time level as month.

Full Access
Question # 8

Your client uses product categories and global sourcing rules for supply planning. However, their newest product doesn't follow these rules. For a specific item in the category, it needs to be sourced from a different supplier globally.

How should they set this up for the easiest maintenance, going forward?

A.

Create a new global sourcing rule for the item; remove the category level assignments and create new item level assignments for all items in the category pointing each to the correct global sourcing rule.

B.

Create a new local sourcing rule for the item; assign it to the assignment set at the item level; leave the category as is for the remainder of the products.

C.

Create a new global sourcing rule for the item; assign it to the assignment set at the item-organization level; leave the category as is for the remainder of the products.

D.

Create a new global sourcing rule for the item; assign it to the assignment set at the item level; leave the category as is for the remainder of the products.

E.

Create a new global sourcing rule for the item; assign it to the assignment set at the item-organization level; alter the category to be category-organization for the remainder of the products.

Full Access
Question # 9

As a new planner, you want to test simulation set functionality. You have created a simulation set named 'Test Simulation Set.' In this simulation set, you have already added Item 98573. You would like to change the item specification 'Fixed Order Quantity' to 10 within this simulation set.

Which sequence will allow you to accomplish this task?

A.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight item > Select 'Action' > Select 'Edit' > Find Fixed Order Quantity specification> under the 'Action' column select 'set value as' > under the 'Value' column enter 10

B.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight item > Select 'View' > Select 'Columns' > Check box next to Fixed Order Quantity specification> the 'Fixed Order Quantity' will now show on the Item 98573 line > Highlight line for Item 98573 and scroll right until you find 'Fixed Order Quantity' > Change value to 10

C.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight item > Select 'Action' > Select 'Edit' > Find Fixed Order Quantity specification> under the 'Action' column select 'reset to original' > under the 'Value' column enter 10

D.

Select and open 'Test Simulation Set' > Search and select Item 98573 > Highlight line for Item 98573 and scroll right until you find 'Fixed Order Quantity' > Change value to 10

Full Access
Question # 10

When planning for customer demand to be fulfilled from internal organizations or from a contract manufacturer, what are the four types of planned orders that can be generated? (Choose four.)

A.

Make orders for items being manufactured in the contract manufacturer organization.

B.

Transfer orders for internally owned components being transferred from contract manufacturer to internal organizations.

C.

Transfer orders for internally owned components being transferred from internal organizations to contract manufacturer organizations.

D.

Transfer orders for finished goods being transferred from contract manufacturer organizations to internal organizations.

E.

Buy orders for components purchased at internal organizations and contract manufacturer organizations.

F.

Return orders for items being manufactured in the contract manufacturer organization.

Full Access
Question # 11

Which KPIs are available to measure forecasting accuracy and specify how these measures aggregated from item-organization level to higher levels.

A.

MAPE, MAD, and Bias are used to measure forecast accuracy. MAD and Bias are aggregated using sum. MAPE is aggregated using weighted average.

B.

MAPE, MAD, and Bias are used to measure forecast accuracy. MAPE and Bias are aggregated using weighted average. MAD is aggregated using sum.

C.

MAPE, MFE, and Bias are used to measure forecast accuracy. MAPE and Bias are aggregated using weighted average. MFE is aggregated using sum.

D.

MAPE, MFE, and Bias are used to measure forecast accuracy. MAPE and MFE are aggregated using weighted average. Bias is aggregated using sum.

Full Access
Question # 12

You are defining material planners for your organization. However, when you go to Manage Material Planners, your organization does not appear in the list of values. Why?

A.

The organization was not enabled for collection under Manage Planning Source Systems.

B.

The organization must be enabled in Manage Planning Parameters.

C.

The organization is an Item Organization.

D.

The organization must be enabled in Manage Planning Profile Options.

E.

You do not have data access to the organization.

Full Access
Question # 13

You have executed Planning Data Collection and want to confirm that data has successfully been collected. Identify the three data combinations that can be viewed using the Maintain Supply Network Model Page. (Choose three.)

A.

Customer Location and Carriers

B.

Safety Stock and Subinventories

C.

Sales Channel and Demand Class

D.

Calendar and Master Organization

E.

Supplier Site and Service Level

Full Access
Question # 14

Each of your planners is responsible for a different geography and set of product lines, so each planner needs to see just their own set of data, analyses and dashboards.

How do you configure the application so each planner can have their own custom dashboard viewable only to themselves?

A.

Create public page layouts that are tailored to specific business needs.

B.

Create private page layouts that are tailored to specific business needs.

C.

You cannot create custom dashboards by user.

D.

Enable layout security checkbox in the Administer Planning Security

Full Access
Question # 15

Which four types of items are eligible to be included as Supply Planned Items in the Supply Plan? (Choose four.)

A.

Demand plan items

B.

WIP components

C.

All planned items

D.

Purchased Items

E.

Supply plan items

F.

All sales orders

Full Access
Question # 16

Planners are complaining about getting too many exception messages, some of which have minima value for evaluating plan health.

Which three solutions could reduce message clutter? (Choose three.)

A.

Go to Configure Exceptions, and specify a threshold for various messages.

B.

Go to Configure Exception Sets, and for the currently used exception set. specify a threshold for various messages.

C.

Go to Configure Exception Sets, duplicate the currently used exception set, remove the undesired messages from the duplicate set. then assign the duplicate set to all plans.

D.

Go to Configure Exception Sets, create a new set with only the messages the planners care about, and then, set all supply plans to use this new exception set.