Labour Day Special - 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: c4sdisc65

Note! 1z0-244 has been withdrawn.

1z0-244 Practice Exam Questions with Answers Oracle EBS R12: Advanced Supply Chain Planning Certification

Question # 6

You define a Supply Chain Plan of type "Master Plan."

In the main tabbed region of Plan Options, you select Planned Items as "All Planned Items" and select the Include Critical Components check box.

Which three describe the Items In the planned organizations that are selected by the plan?

A.

all Items with the Planning Method Item Attribute of "MPS Planning" or "MPS/MPP Planned"

B.

all critical Items and any assembly that has a critical component anywhere in its Supply Chain Bill. All sandwiched Items are also selected.

C.

all Items EXCEPT the ones with the Planning Method Item Attribute set to "Not Planned"

D.

Any Item that has a component with the Planning Method Item Attribute of "MRP/MPP Planned," "MPS/MPP Planned," or "MPP Planned" anywhere in its Supply Chain Bill. All sandwiched Items are also selected.

E.

all Items with the Planning Method Item Attribute of "MRP/MPP Planned," "MPS/MPP Planned," or "MPP Planned"

Full Access
Question # 7

Your client currently has two manufacturing plants, plants, four Inventory locations, and one distribution center. When doing the future state analysis, the Operations Directory at the client site said that they have expansion plans after the go-live of the current Oracle in Implementation. They plan to add 10 more distribution centers and these can be transfer of goods between any two distribution centers. Each distribution center would need to optimize its inventory level and forecasts will be handled in Demand Planning for better customer satisfaction.

The client IT Manager proposes to use one main inventory Organization to represent all the facilities and use sub inventories to represent the various inventory locations in the manufacturing plant and the distribution center. The future distribution centers can be modeled as subinventories because Oracle allows you to define a large number of subinventories. From the system point of view, It will be easier to maintain and inventory transfers between sub inventor using Move Orders are possible.

Select three correct statements about the above scenario.

A.

You design multiple inventory Organizations to model this so that in future when the client needs to plan a transfer from one facility to another, ASCP will be able to suggest such a transfer.

B.

You design the same way as the client IT Manager because It will fulfill all the requirements of the client.

C.

Inventory Optimization does not calculate safety stock at the subinventory level. So the client needs multiple inventory Organizations.

D.

Demand Planning forecasts by Organization, not by subinventory. So the client needs multiple inventory Organizations.

E.

Global Order Promising can calculate availability at the subinventory level, so you need one inventory Organization with multiple subinventories.

F.

You design the same way and you also add more transaction types to take care of future transfers between any two distribution centers.

Full Access
Question # 8

Identify the three steps that a planner can perform during Net change Simul-ation On-line planning.

A.

Add Supplier capacity.

B.

Change BOM Supply Type for a component from Phantom to Supplier.

C.

Firm Discrete Jobs.

D.

Add new Resource availability by adding shifts.

E.

Change Item attribute order modifiers.

F.

Change Resource Basis from Item to Lot.

Full Access
Question # 9

Identify three correct statements about phantom Items?

A.

One Bill of Material can represent a phantom subassembly for one parent Item, but It cannot be a stocked subassembly for another parent Item.

B.

The full cost rollup process sets the pending phantom assembly burden to 1.

C.

A phantom subassembly is a nonstocked subassembly that enables you to group the material needed to produce an assembly.

D.

Oracle Work In Process explodes through a phantom subassembly to the components as If the components were tied directly to the parent assembly.

E.

You cannot define routing for phantom assemblies the same way as other assemblies.

F.

You can compute manufacturing and cumulative lead times for phantom assemblies that have routings.

Full Access
Question # 10

Exhibit.

1z0-244 question answer

In a manufacturing environment where Oracle Shop Floor Management Is used, the production process with Information about Yield (Yld), Net Planning Percent (NPP), Cumulative yield (CY), Reverse Cumulative Yield (RCY) is displayed for a product.

If the order quantity is 100, what is the raw material quantity and resource requirement ASCP will schedule respectively at operation sequence 10?

A.

Raw material qty 97.37 and resource requirement for 117.63

B.

Raw material qty 100 and resource requirement for 100

C.

Raw material qty 98 and resource requirement for 98

D.

Raw material qty 113.63 and resource requirement for 113.63

E.

Raw material qty 117.63 and resource requirement for 113.63

Full Access
Question # 11

Exhibit.

1z0-244 question answer

You define a Supply Chain plan of type "Manufacturing Plan." In the Plan Options Main tab, you select Planned Items as "Demand schedule items and all sales orders" and select the Include Critical Components check box.

The Exhibit shows Bills of Material for Items A and B. It also shows the settings for the Include Sales Order check box on the Plan Options Organizations tabbed page.

Item A has Demand Schedules and Sales Orders for Organizations Ml and M2. Item B has only Sales Orders for Organizations Ml and M2.

Which three statements are correct in the above plan scenario?

A.

The critical components of Items A and B (Al, A3, and B3) along with the sandwiched Items A2 and B2 are planned in both Organizations. The noncritical components (A4, B1, and B4) are Ignored.

B.

All components of Items A and B are planned in both Organizations.

C.

The critical components of Items A and B (Al, A3, and B3) are planned. The sandwiched Items

(A2 and B2) and the noncritical components (A4, B1, and B4) are Ignored.

D.

Item A with Demand Schedules in Organizations Ml and M2 is planned.

E.

Sales Order demands of Items A and B for Organization Ml are planned and for Organization M2

are ignored.

Full Access
Question # 12

Exhibit.

1z0-244 question answer

In the Distribution Network, the RDC5 and RDC6 Regional Distribution Centers source material from the DC3 Central Distribution Center.

The matrix in the Exhibit shows allocation for a supply quantity of 300 In the first allocation bucket.

Which Fair Share Allocation method was applied by the Distribution Plan?

A.

Safety Stock Ratio

B.

Demand Class

C.

Order Size

D.

Fixed Percent

E.

Current Demand Ratio

Full Access
Question # 13

Identify three correct ways to manage Personal and Public Queries In Advanced Supply Chain Planning (ASCP).

A.

Default Queries: In the Tools > Managers window, there Is a field to specify the name of a query to autoexecute after you navigate to the query tab in the left navigation tree.

B.

Accessing Saved Queries: All saved queries show up In their respective query type folders in the left navigation tree. You can easily pick a saved query and view the query, rename it, or view Its results, and so on.

C.

Grouping: You designate query criterion as the group by criterion, such that the results of the query are displayed based on that criterion. While looking for late replenishment for forecast, you can designate that the results be grouped by Org.

D.

Planner Workbench Navigator: The slider in the Planner Workbench Navigator helps in collapsing the window so that the left navigation tree can be hidden. You can then expand the results window to the permitted full size and focus on the query results.

Full Access