Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free ISO-21502-Lead-Project-Manager PECB ISO 21502 Lead Project Manager Exam Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the PECB ISO-21502-Lead-Project-Manager Exam the most current and reliable questions . To help people study, we've made some of our PECB ISO 21502 Lead Project Manager Exam exam materials available for free to everyone. You can take the Free ISO-21502-Lead-Project-Manager Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

To whom does the project manager report?

A.

Only to organization’s top management

B.

Key stakeholders

C.

Project sponsor and project board

Question # 7

Which methodologies below are more flexible in nature and provide an iterative approach for project management?

A.

Change management

B.

Traditional

C.

Agile

Question # 8

What are proposal requests?

A.

Requests from the contractor to the supplier to provide solutions for an intricate scope

B.

Requests when the solution is determined and when the price is the sole criterion for choosing the supplier

C.

Requests used to obtain supplier proposals when the buyer needs a proposed solution, approach, or offer for the required work

Question # 9

According to ISO 21502, when is positive value created?

A.

When the investment of resources is similar to the benefits enabled by the project

B.

When the benefits enabled by the project exceed the investment of resources

C.

When the project produces deliverables, regardless of the resources allocated for its implementation

Question # 10

Scenario:

Oakniture is a furniture manufacturer located in Bristol, England. It is known for its kitchen tables made out of different types of wood, such as chestnut, walnut, and oak. In early 2022, Lana, one of the senior researchers of the company, conducted a feasibility study to determine if there is a market for oak wood coffee tables, which indicated that the demand for oak wood coffee tables is relatively high. As such, Lana prepared a project brief and presented it to the top management of the company. The project brief included information on the project context and project objectives. After several discussions, the top management agreed that the project should be undertaken, but lastly, they asked Lana about the project duration. Lana claimed that the project duration cannot be determined and such information was not provided in the project brief; however, she added that the project duration will mainly depend on the competencies of the project team and on Oakniture’s suppliers of wood.

Following that, the top management initiated the project and assigned Tom, the operations director, as the project manager, and Lana as the project sponsor. To manage the project, they decided to use the guidelines of ISO 21502.

Initially, Tom defined the governance and management framework alone, and then he mobilized the team and assigned the roles and responsibilities to each team member. In addition, Tom and the project team identified the stakeholders and developed the project plan. To ensure effective management of each project phase, Tom used a work breakdown structure (WBS) to organize project activities. Tom presented the project activities in the WBS by linking task dependencies and showing project milestones. In addition, Tom calculated the duration of each work package by determining the early start and early finish dates. Regarding the relationship between work packages, Tom required the project team to perform tasks in the predetermined order, regardless of any resource shortages they might experience.

A week after the project implementation began, Tom collected and analyzed data regarding the progress of the project. To keep everyone up to date, he held a meeting with Lana and project stakeholders.

Question:

Based on scenario 4, the governance and management approach was defined by Tom alone. Is this acceptable?

A.

Yes, the governance and management approach should be defined only by Tom, the project manager

B.

No, Tom should have defined the governance and management approach in cooperation with the project team

C.

No, Tom should have defined the governance and management approach in cooperation with Lana, the project sponsor

Question # 11

Scenario:

Mallebare is an American company which designs and manufactures gaming accessories. Apart from keyboards, mice, and controllers, the company also manufactures high-quality headsets for which it is widely known. Recently, upon the request of numerous gamers, the company decided to manufacture mousepads too. For this project, Luke, the CEO of the company, assigned Ross, a senior designer of the company, as the project manager, whereas Smith, a senior engineer, was assigned as project sponsor. In addition, Luke stated the project should be complete within three months, as the company is aiming to promote the mousepads in a major gaming tournament. Lastly, Luke required them to utilize the guidelines of ISO 21502 to manage the project.

Initially, Ross mobilized the team and held a meeting with them to discuss and develop the project plan. He asked the team members to ensure that major functional aspects of the project are covered in the project plan and to identify any issue that might arise throughout the project life cycle. Ross explained that this request comes as a result of the tight deadline of the project and the team must develop a concise plan. Ross added that the plan will not be changed in any circumstance and will be followed in detail.

Following that, Ross and the team discussed the engagement of all relevant stakeholders throughout the project. Ross used a power/interest matrix to categorize all stakeholders in four different groups, where the tournament organizers were categorized as stakeholders with low interest but high power in the project. On the other hand, end users, the gamers, were categorized as stakeholders with high interest and high power in the project, so the project team created a survey to determine their needs and requirements.

Moreover, Ross was aware of the importance of effective communication for the success of the project. Therefore, he developed a communication plan which would ensure that each individual involved in the project gets the right information in a timely manner. The plan indicated that ad hoc discussions would be conducted in more complex and personal cases, whereas notes and text messages would be used for transmitting simple and factual information. Ross claimed that this model had been successful in previous projects conducted by the company because it allows faster processing of information and includes natural use of language. In addition, Ross determined that a relationship among project team members needs to be established to ensure productive work.

Question:

Ross required the team to develop a concise plan which will be followed in detail and that will not be changed in any circumstance. Is this compliant with ISO 21502?

A.

Yes, the project plan cannot be changed at any case once it is developed

B.

No, the project plan should be monitored and can be changed only prior to the execution phase

C.

No, the project plan should be monitored and can be updated, when required

Question # 12

What is an advantage of using ISO 21502?

A.

Organizations enhance their strength through project implementation

B.

Organizations have advancing opportunities to transform ideas into tangible and intangible deliverables, outputs, outcomes, and benefits

C.

Both A and B

Question # 13

Scenario:

Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in-flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.

Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.

Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.

While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.

A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.

Question:

According to scenario 3, the business case was updated to reflect the changes made regarding the project delivery. Is this acceptable?

A.

Yes, the business case should be updated to reflect changes in the project’s context

B.

No, the business case can be updated only during pre-project activities

C.

Yes, the business case can be updated to reflect changes on the project delivery, but not to reflect changes on other aspects of the project

Question # 14

Scenario:

Exhibix is a video game developer headquartered in Zagreb, Croatia, which is known for producing therapeutic video games for children dealing with ADHD. In order to improve users’ experience, Exhibix suggested undertaking a project that would enable users to interact with the virtual content in the form of holograms through augmented reality glasses in the video games. For this project, the management decided to follow the guidelines of ISO 21502 on project management.

Prior to formalizing project management, the management of Exhibix assessed, among others, the potential impacts that the project management approach may have on both internal and external stakeholders. In addition, they determined if there were sufficient resources, both human and financial, for the formalized project management. Furthermore, during this period, the management decided to assess only the nature of previous projects, due to their successful delivery.

After formalizing project management, the project board organized a meeting during which they delegated their responsibilities to the project sponsor. Following this meeting, the project sponsor and project manager proceeded to define the project phases and their time frames. Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project.

The preparations began in June, and the project manager and the team, consisting of 20 highly skilled professionals, had approximately six months to implement the project. During the implementation of the project, the project team noticed that the low maturity level of the company’s project management and the limited availability of resources were likely to have a negative impact on the performance of the project. With the deadline approaching, the team was also under a lot of pressure to close the project on time.

They were confronted with numerous challenges with the AR software, which led to the extension of the deadline for the project completion. During this period, the project office assisted the project manager and the team by providing administrative support and managing information regarding the project. Following these events, the project manager and the team were able to complete the project within the new set deadline. After the project sponsor confirmed the project closure, the AR glasses were released for use.

Question:

Based on the fourth paragraph of scenario 2, what factors did the project team notice that were likely to have a detrimental impact on the project’s performance?

A.

Internal

B.

External

C.

Both A and B

Question # 15

Why is it important to define the project governance and management framework?

A.

To ensure the commitment of project stakeholders

B.

To obtain the approval from the project sponsor to execute the project plan

C.

To provide direction and working methods to the parties involved in the project

Question # 16

What is a work package?

A.

The smallest unit of a work breakdown structure for which the cost and duration are estimated and managed

B.

A method that uses a set of measures associated with scope, schedule, and cost to determine the cost and schedule performance of a project

C.

The sequence of stages determining the minimum time needed for completing the project

Question # 17

Scenario:

Exhibix is a video game developer headquartered in Zagreb, Croatia, which is known for producing therapeutic video games for children dealing with ADHD. In order to improve users’ experience, Exhibix suggested undertaking a project that would enable users to interact with the virtual content in the form of holograms through augmented reality glasses in the video games. For this project, the management decided to follow the guidelines of ISO 21502 on project management.

Prior to formalizing project management, the management of Exhibix assessed, among others, the potential impacts that the project management approach may have on both internal and external stakeholders. In addition, they determined if there were sufficient resources, both human and financial, for the formalized project management. Furthermore, during this period, the management decided to assess only the nature of previous projects, due to their successful delivery.

After formalizing project management, the project board organized a meeting during which they delegated their responsibilities to the project sponsor. Following this meeting, the project sponsor and project manager proceeded to define the project phases and their time frames. Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project.

The preparations began in June, and the project manager and the team, consisting of 20 highly skilled professionals, had approximately six months to implement the project. During the implementation of the project, the project team noticed that the low maturity level of the company’s project management and the limited availability of resources were likely to have a negative impact on the performance of the project. With the deadline approaching, the team was also under a lot of pressure to close the project on time.

They were confronted with numerous challenges with the AR software, which led to the extension of the deadline for the project completion. During this period, the project office assisted the project manager and the team by providing administrative support and managing information regarding the project. Following these events, the project manager and the team were able to complete the project within the new set deadline. After the project sponsor confirmed the project closure, the AR glasses were released for use.

Question:

Considering the complexity of the project, the project manager suggested leaving open the possibility of overlapping certain phases of the project. Is this acceptable?

A.

No, project phases should not overlap with one another

B.

Yes, because it is possible that project phases can overlap

C.

No, only the project sponsor has the authority to make a decision regarding project phases

Question # 18

Scenario:

Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in-flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.

Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.

Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.

While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.

A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.

Question:

Scenario 3 indicates that Michaele authorized the project initiation. Is this acceptable?

A.

No, the project initiation should be approved by the project manager in consultation with work package leaders

B.

No, the project initiation should be approved by the project manager

C.

Yes, the project initiation should be approved by the sponsoring organization

Question # 19

Which of the following statements regarding lessons learned is correct?

A.

They provide answers only about what really happened and not what was planned to happen

B.

They should be captured, compiled, formalized, and stored

C.

They should be disseminated and used only after all project activities are completed

Question # 20

Which of the following belongs to adaptive changes?

A.

Introducing a practice new to the practitioners

B.

Reintroducing a familiar practice

C.

Introducing a practice that is new to the organization, but not the industry

Question # 21

Who should be consulted as part of project management progress evaluations?

A.

Project sponsors and project managers and their teams

B.

Project board and project assurance

C.

Work package leaders only

Question # 22

Scenario:

Headquartered in Geneva, Switzerland, DND is one of the largest worldwide automakers. It first gained global recognition after introducing a sports car, which quickly became highly demanded by sports car lovers around the world. Alec Law, the CEO of DND, and his management team recently decided to embark on a new project, i.e., the production of alternative fuel cars, which would use an alternative fuel source instead of traditional petroleum fuels, as the other cars of the company do, in order to promote sustainable and low-carbon transportation. For the implementation of this project, the company decided to follow the guidelines of ISO 21502 on project management.

During the development of the project governance framework, the company took into account several factors, including, among others, the legal context of stakeholders. In the project governance, the company also included oversights on the management frameworks and the project life cycle. In order to determine the project life cycle, the external environment was considered, including information on studies that related to similar projects. In addition, the company decided to separate this project governance from its overall governance.

Moreover, the company developed a project organization, where the roles, responsibilities, and authorities in the project were defined. In addition, the responsibilities of the project office and project assurance, among others, were defined. The project organization also included a customer representative. Once the project organization was developed and approved by the project board, it was communicated only to the project team.

As the project was entering its design stage, the project board made a change in the structure of the project organization since one of the work package leaders had resigned from the project in order to be involved in another project of the company.

Question:

According to scenario 1, the project organization was communicated only to the project team. Is this compliant with ISO 21502?

A.

Yes, according to ISO 21502, the project organization should be communicated only to the project team

B.

No, according to ISO 21502, the project organization should be communicated only to the project office and project assurance

C.

No, according to ISO 21502, the project organization should be communicated to everyone involved in the project

Question # 23

Scenario:

Headquartered in Geneva, Switzerland, DND is one of the largest worldwide automakers. It first gained global recognition after introducing a sports car, which quickly became highly demanded by sports car lovers around the world. Alec Law, the CEO of DND, and his management team recently decided to embark on a new project, i.e., the production of alternative fuel cars, which would use an alternative fuel source instead of traditional petroleum fuels, as the other cars of the company do, in order to promote sustainable and low-carbon transportation. For the implementation of this project, the company decided to follow the guidelines of ISO 21502 on project management.

During the development of the project governance framework, the company took into account several factors, including, among others, the legal context of stakeholders. In the project governance, the company also included oversights on the management frameworks and the project life cycle. In order to determine the project life cycle, the external environment was considered, including information on studies that related to similar projects. In addition, the company decided to separate this project governance from its overall governance.

Moreover, the company developed a project organization, where the roles, responsibilities, and authorities in the project were defined. In addition, the responsibilities of the project office and project assurance, among others, were defined. The project organization also included a customer representative. Once the project organization was developed and approved by the project board, it was communicated only to the project team.

As the project was entering its design stage, the project board made a change in the structure of the project organization since one of the work package leaders had resigned from the project in order to be involved in another project of the company.

Question:

According to scenario 1, the project board made a change in the project organization structure after the project entered the design stage. Is this acceptable?

A.

Yes, the project organization can change throughout the project life cycle

B.

Yes, the project organization can change only during the design stage of the project

C.

No, once the project organization is developed and approved, it cannot be changed

Question # 24

What does ISO 21502 provide?

A.

Guidance on the principles of project and program portfolio management

B.

High-level descriptions of effective practices for project management

C.

Guidance on the management of projects, programs, and portfolios

ISO-21502-Lead-Project-Manager PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

ISO-21502-Lead-Project-Manager PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: PECB ISO 21502 Lead Project Manager Exam
  • Last Update: Jul 2, 2026
  • Questions and Answers: 80
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

ISO-21502-Lead-Project-Manager Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included