We at Crack4sure are committed to giving students who are preparing for the PMI CAPM Exam the most current and reliable questions . To help people study, we've made some of our Certified Associate in Project Management (CAPM) exam materials available for free to everyone. You can take the Free CAPM Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
When can pre-assignment of project team members occur?
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
What is the name of a graphic display of project team members and their reporting relationships?
Which process is included in the Project Integration Management Knowledge Area?
Which of the following techniques is used during Control Scope?
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
Which is a communication method used in the Report Performance process?
The staffing management plan is part of the:
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
A tool and technique used during the Perform Qualitative Risk Analysis process is:
Which of the following is an input to Direct and Manage Project Execution?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Which document includes the project scope, major deliverables, assumptions, and constraints?
When does Monitor and Control Risks occur?
Work performance information and cost forecasts are outputs of which Project Cost Management process?
An input to the Create WBS process is a:
What type of reward can hurt team cohesiveness?
In an organization with a projectized organizational structure, who controls the project budget?
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?
The scope management plan is a subsidiary of which project document?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
When is a Salience Model used?
Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
An input required in Define Scope is an organizational:
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
The Define Scope process is in which of the following Process Groups?
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
The individual or group that provides resources and support for a project and is accountable for success is the:
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
Which provides the basic framework for managing a project?
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
Which of the following is an output of the Perform Integrated Change Control process?
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
"Tailoring" is defined as the:
Which of the following is an information gathering technique in Identify Risks?
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
During which process would stakeholders provide formal acceptance of the completed project scope?
Which type of chart is a graphic representation of a process showing the relationships among process steps?
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
Which is the correct formula for calculating expected activity cost for three-point estimating?
Which of the following statements is true regarding project and product lifecycles?
In which process might a project manager use risk reassessment as a tool and technique?
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
Which piece of information is part of the WBS Dictionary?
Managing procurement relationships and monitoring contract performance are part of which process?
Which of the following is an input to the Direct and Manage Project Execution process?
Which of the following correctly explains the term "progressive elaboration'?
Which tool or technique is used in Close Procurements?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following events would result in a baseline update?
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
The process of identifying the stakeholders' information needs is completed during:
In which process is a project manager identified and given the authority to apply resources to project activities?
A required input for Create WBS is a project:
What causes replanning of the project scope?
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which process occurs within the Monitoring and Controlling Process Group?
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
Which process involves identifying and documenting the logical relationships between project activities?
A method to manage stakeholder expectations in the scope statement is to clearly:
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
Which of the following reduces the probability of potential consequences of project risk events?
Labor, materials, equipment, and supplies are examples of:
The definition of operations is a/an:
In a weak matrix, the project managers role is:
Which tool or technique is used in Manage Stakeholder Expectations?
Which of the following is an output from Control Scope?
Which of the following is a tool or technique of the Define Activities process?
Documented identification of a flaw in a project component together with a recommendation is termed a:
Which standard has interrelationships to other project management disciplines such as program management and portfolio management?
Which process determines the risks that might affect the project?
Which of the following is an input to the Perform Qualitative Risk Analysis process?
Which type of analysis is used as a general management technique within the Plan Procurements process?
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
Which Process Group contains those processes performed to define a new project?
Tools and techniques used for Plan Communications include the communication:
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Types of internal failure costs include:
Which of the following is an input to Develop Human Resource Plan?
An intentional activity to modify a nonconforming product or product component is called:
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:
A tool and technique used in the Develop Project Charter process is:
The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:
At the start of a typical project life cycle, costs are:
A project manager who communicates to the project team though email is using which type of communication?
During which process does the project team receive bids and proposals?
An input to the Perform Integrated Change Control process is:
A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
An input to the Control Quality process is:
Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?
Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
Variance and trend analysis is a tool and technique used in which process?
When the business objectives of an organization change, project goals need to be:
In which type of organizational structure are staff members grouped by specialty?
Which of the following is a group decision-making technique?
Which Project Time Management process includes bottom-up estimating as a tool or technique?
Which Manage Communications tool or technique focuses on identifying and managing barriers?
Project management processes ensure the:
While processes in the Planning Process Group seek to collect feedback and define project documents to guide project work, organizational procedures dictate when the project planning:
High-level project risks are included in which document?
Technical capability, past performance, and intellectual property rights are examples of:
Analytical techniques are a tool and technique of which process in Project Procurement Management?
The following is a network diagram for a project.
The free float for Activity H is how many days?
The following is a network diagram for a project.
The total float for the project is how many days?
Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?
The primary benefit of the Plan Schedule Management process is that it:
In project management, a temporary project can be:
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour, how many hours are required to produce 12,000 units?
For a stakeholder with low interest and high power, the project manager should:
Which element does a project charter contain?
Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?
In the Define Activities process, the schedule management plan is used to:
A project manager requesting industry groups and consultants to recommend project intervention is relying on:
A complete set of concepts, terms, and activities that make up an area of specialization is known as:
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
Which tool or technique is required in order to determine the project budget?
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:
Project Scope Management is primarily concerned with:
Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?
The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:
Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?
Which type of dependency used in the Sequence Activities process is sometimes referred to as preferred logic, preferential logic, or soft logic?
Requirements documentation will typically contain at least:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedule performance index (5PI) for Task 4?
Every project creates a unique product, service, or result that may be:
The following is a network diagram for a project.
What is the critical path for the project?
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
The lowest level normally depicted in a work breakdown structure (VVBS) is called a/an:
Which quality tool incorporates the upper and lower specification limits allowed within an agreement?
The degree, amount, or volume of risk that an organization or individual will withstand is called risk:
Expected monetary value (EMV) is computed by which equation?
What is project management?
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
In the basic communication model, which term refers to the method that is used to convey the message?
The correct equation for schedule variance (SV) is earned value:
Which of the following is an output of Close Procurements?
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
When cost variance is negative and schedule variance is positive, the project is:
Which technique is utilized in the Control Schedule process?
Plan-do-check-act is also known as:
Who determines which dependencies are mandatory during the Sequence Activities process?
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Which quality control technique illustrates the 80/20 principle?
An input of the Create WBS process is:
Which of the following is an input to the Develop Project Charter process?
What happens to a stakeholder's project influence over time?
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
Which is one of the determining factors used to calculate CPI?
The process for performing variance analysis may vary, depending on:
The diagram below is an example of a:
Which is an output of the Collect Requirements process?
The process of identifying specific actions to be performed to produce project deliverables is:
Exhibit A is an example of which of the following types of Sequence Activities?
Which process requires implementation of approved changes?
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
The total of the planned value (PV) is also known as:
Which tool or technique can a project manager use to select in advance a team member who will be crucial to the task?
Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?
Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?
Which statement is true about the project management body of knowledge?
During project selection, which factor is most important?
The risk shared between the buyer and seller is determined by the:
Which of the following are three inputs to the risk register?
The process to ensure that appropriate quality standards and operational definitions are used is:
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
After Define Activities and Sequence Activities, the next process is:
Which of the following is a project constraint?
Which type of dependency is contractually required or inherent in the nature of the work?
Which knowledge area includes the processes to identify, define, and unify the various project management processes?
The project manager is distributing project communications, collecting and storing project information, and retrieving documents when required. In which process is the project manager involved?
Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
The probability and impact matrix is primarily used to:
Inputs to the Plan Risk Management process include the:
Identify Stakeholders is the process of identifying all of the people or organizations impacted by the project and documenting relevant information regarding their interests in, involvement in, and impact on the project:
Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?
Which of the following change requests can bring expected future performance of the project work in line with the project management plan?
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Which of the following is an output of the Conduct Procurements process?
Which characteristics do effective project managers possess?
What are the identified risks for doing excessive decomposition in a WBS?
Which risk response strategy is common for both positive and negative risks?
In a project using agile methodology, who may perform the quality control activities?
During the planning phase, a project manager must create a work breakdown structure (WBS) to improve management of the project's components. What should be included in the WBS?
How should a project manager plan communication for a project which has uncertain requirements?
A project manager is assigned to a strategic project Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project.
Which entities will the project manager attempt to influence?
What are the objectives of Initiation processes?
A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?
Which task will a project manager undertake while conducting Project Resource Management?
How can a project manager evaluate project team development?
A project manager is monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations. Which output is the project manager using?
Match the project life cycle type with its corresponding definition.
Which is an example of analogous estimating?
What scenario describes when a project must be created due to market demand?
What is a tool or technique used in the Control Quality process?
A project manager is determining the amount of contingency needed for a project. Which analysis is the project manager using?
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the Importance of creating the project management office?
What is the first step in the Stakeholder Management process?
Which of the following describes the similarities of the process groups and project life cycle?
A project manager has just completed several brainstorming sessions and has gathered the data to show commonality and differences in one single place. What technique was followed?
A project is just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
Which statement summarizes the role of the change control board?
A project manager is working in an environment where requirements are not very clear and may change during the project. In addition, the project has several stakeholders and is technically complex.
Which strategies should the project manager take into account for risk management in this environment?
Given the following information.
Activity A takes one week.
Activity B takes three weeks.
Activity C takes two weeks.
Activity D takes five weeks.
Activity A starts at the same time as Activity B.
Activity C follows Activity B and Activity A.
Activity D follows Activity C.
How long will it take to complete the project?
Responsible, accountable, consult and inform (RACI) is an example of which of the following?
Which are examples of processes that may be used once or at predefined points in the project life cycle?
Which set of competencies should a project manager have?
Match the influence with its corresponding category of influence.
Which of the following can a project manager use to represent dellned team member roles in a group of tasks?
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
It you established a contingency reserve including time, money, and resources, how are you handling risk?
What tool should a project manager use to efficiently manage project resources?
Which of the following set of elements is part of an effective communications management plan?
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
A tool and technique used during the Collect Requirements process is:
What does expert judgment provide as an input to the resource management plan?
According to the PMI Talent Triangle. leadership skills relate to the ability to:
Which of the following sets are inputs to the Collect Requirements process?
When managing costs in an agile environment, what should a project manager consider?
What is the difference between quality metrics and quality measurements?
The project manager and the project team are having a meeting with the purpose of identifying risks. Which tools and techniques might help in this process?
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
Which format can a network diagram take?
A project manager Is addressing risks and potential concerns related to stakeholder management, and Is clarifying and resolving previously Identified issues. In which process is the project manager engaged?
A project manager is preparing to meet with three crucial project stakeholders on a new project Which tools and techniques can the project manager use to capture stakeholder interest?
The project leam is brainstorming on approaches to deliver the upcoming product launch for which the project has been chartered. The project manager is laying out hybrid, adaptive, iterative methods. What is the team trying to address?
A project stakeholder is requesting changes to the project plan. Which process group addresses this?
The project manager is using co-location and providing training to the project team. On which of the following Project Resource Management processes is the project manager working?
Which is an example of leveraging evolving trends and emerging practices in Project Integration Management?
Which of the following is an example of an internal factor that influences the outcome of the project?
The project manager is working with some functional managers and stakeholders on the resource management plan Which elements may be included in this plan?
The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?
Which statement about identification and engagement of stakeholders during a project is correct?
In which Project Cost Management process is work performance data included?
Which of the following tasks focuses on decomposing work packages?
During which process of Project Cost Management does a project manager produce the cost baseline?
An organizational structure that standardizes the project-related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques is referred to as:
The project manager is working in an agile/adaptive environment. The project manager is considering different approaches for applying Project Integration Management in this environment. How can the project manager ensure that this will work for the project?
A project's business analyst has to understand the newly acquired technology and the impact it will have on the organization. Which tool should be used to understand the new technology?
The initial development of a Project Scope Management plan uses which technique?
Which two of the following can be used as communication tools between the business analyst and the rest of the project team? (Choose two)
In an interactive communication model, how is the sender ensured that the message was understood by the receiver?
What CPI > 1 and SPI < 1 mean?
A project manager is in the process of onboarding resources to start work on a project. Which of the following components of a project management plan will the project manager update after completing this activity?
Which kind of communication should the project manager use when creating reports for government bodies?
What is the common factor among portfolios, programs, and projects, regardless of the hierarchy within an organization?
Which is an example of an internal enterprise environmental factor?
In one of the project meetings during project execution, a new stakeholder attends and highlights a new risk. What should the project manager do next?
A project manager can choose from several techniques to resolve conflicts between team members. Which technique can result in a win-win solution?
An adaptive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning.
Which two of the following items should be included in the planning? (Choose two)
An adaptive team is in the process of merging a legacy system from an acquired company. In order to check the project status and manage the flow of work, they are using a scrum board for this project. What data should be included in this information radiator?
An adaptive team is working on a mobile banking application. The team conducted their sprint demo, which included 12 stories that were completed. This was the last sprint before the product was to be launched in the beta phase. One of the attendees from marketing noticed that a requested enhancement to share on social media was still in the product backlog.
Why was the product still determined to be ready for delivery?
Project managers plan a key role performing integration on the project what are the three different levels of integration?
Which of these statements is true of subsidiary management plans?
During a kickoff meeting, the project sponsor presents a very ambitious project. Unfortunately, the stakeholders are not very excited as the work associated with the new project seems inefficient.
What could be missing from the business case?
It’s time to perform code review on a software project that has over three million lines of code written. Which management tool should the project manager use?
Which of the following set of items belongs to the communications management plan?
Which are the competing constrains that project manager should address when tailoring a project?
What important qualities should project managers possess for strategic and business management?
Match the process with its corresponding Process Group:
A project manager has a project schedule baseline. How can the critical path be determined from the finalized schedule?
A quality management plan describes how the project and product scopes are managed in accordance with which of the following items?
What prototyping technique shows a sequence or navigations through a series of images or illustrations?
Which subsidiary management plan.... during the project ilfe cycle?
Which Subsidiary management plan would a project manager create to manage Information dissemination during the project life cycle?
How should the project manager obtain the maximum engagement from stakeholders that have recently changed to become more connected to social media?
Which statement describes the Monitor Communications process?
Given the following information, what is the schedule variance (SV) for this project?
Early start date (ES): 16 weeks
Actual time: 12 weeks
Schedule performance index (SPI): 1.3
A community project with a large number of stakeholders is scheduled for delivery in six months. The project manager asked the business analyst to ensure effective requirements elicitation. What should the business analyst do?
An adaptive project manager is handling a five-sprint cycle to deliver a minimum viable product (MVP). After the third sprint, the productivity of the team drops to 30% due to a change in the way the team operates.
Which of the following changes has caused this loss in productivity?
A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence.
What should the project manager do first?
During the requirements verification process, stakeholders are finding many errors in the requirements definition. What could the business analyst have done to avoid these errors?
A project manager needs information to finish their work on the project charter for a clinical trial.
Which procedure is used to obtain the requirements information?
What specific quality considerations should be examined while completing Quality Management plan?
How can a project manager ensure effective project stakeholder engagement?
The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should plan the project manager consult?
Which of the following is the key construction to controlling the costs and achieving the schedule in projects with high variability?
A project manager is calculating the current budget. The earned value (EV) of the project is lower than the actual cost (AC) of the project.
How should the project manager report the status of the project?
A project lead asks the team to create a work breakdown structure (WBS) of the project's scope. The team is confused about how far they should break down the scope.
What should the project lead tell the team?
A business analyst sent multiple meeting requests via instant message to a subject matter expert (SME) working in another country but did not receive a response. What should the business analyst do to reduce the likelihood of this occurring in the future with other stakeholders distributed across multiple locations?
An example of a group decision-ma king technique is:
A practitioner organized a requirements workshop with the client's frontline application users. The users explained that one of the challenges of the current application is that they must click on each input before entering data, which happens thousands of times a day.
Which technique did the practitioner use to identify this pain point?
A project manager is seeking assistance from the business analyst for an IT project. What assistance can the business analyst provide?
During a project's execution phase, the project manager reviews the communications management plan for communication technology factors. What can affect the choice of communications?
How can working in iterations increase the quality of the product being built?
A Project manager is using agile in a project. As development life cycle is adaptive, how does the project manager handle key stakeholder involvement?
What three strategies are used to respond to threats?
A technical project manager uses a directive approach with the team. Some team members are growing increasingly frustrated when their recommendations are not adopted by the project manager.
What should the project manager do to address this issue?
Match the method for categorizing stakeholders with its corresponding description
Which additional considerations should the project manager make when managing risks in an agile/adaptive project?
What is the purpose of the Manage Quality process?
A project team working on an automobile manufacturing project is detailing the parts needed for a car door design. The door is composed of several parts that have to be developed in sequence, as the frame is needed before other parts can be designed and built. What activity is the team involved in?
When paying a consultation fee to a technical expert, what type of contract is often used'?
Which process determines the correctness of deliverables?
The project team is inspecting the completed project scope to determine if the requirements have been satisfied. What is the result of this inspection?
What should a project manager consider to address the full delivery life cycle for large projects?
A stakeholder is reading project documents given by the project manager. The stakeholder is
curious about the difference between a verified deliverable and an accepted deliverable.
Which of the following definitions can the project manager use to explain the difference?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:
After an internal deliverable review session with the team, the project manager indicates some issues that need to be fixed before submitting the deliverable for formal approval. The project manager will need to manage the additional costs and the required network. How would the project manager define extra costs?
Which process numerically analyzes the effect of identified risks on overall project objectives?
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
A project manager builds consensus and overcomes obstacles by employing which communication technique?
Reserve analysis is a tool and technique used in which process?
The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
A project charter is an output of which Process Group?
Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
The organization's perceived balance between risk taking and risk avoidance is reflected in the risk:
The Perform Integrated Change Control process occurs in which Process Group?
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Which cost is associated with nonconformance?
The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Scope, schedule, and cost parameters are integrated in the:
Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?
The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?
Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
The process of identifying and documenting relationships among the project activities is known as:
Enterprise environmental factors are an input to which process?
Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:
An input to the Plan Procurement Management process is:
Which grid shows which resources are tied to work packages?
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
Which item is a formal proposal to modify any document, deliverable, or baseline?
Which document defines how a project is executed, monitored and controlled, and closed?
The ability to influence cost is greatest during which stages of the project?
An input to the Plan Cost Management process is:
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
The business needs, assumptions, and constraints and the understanding of the customers needs and high-level requirements are documented in the:
Which Process Group and Knowledge Area include the Sequence Activities process?
Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?
Which tool or technique is an examination of industry and specific vendor capabilities?
Which tools or techniques are used in the Plan Schedule Management process?
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Which process develops options and actions to enhance opportunities and reduce threats to project objectives?
An output of the Plan Quality Management process is:
Inputs to the Plan Schedule Management process include:
A reward can only be effective if it is:
External organizations that have a special relationship with the enterprise and provide specialized expertise are called:
The Identify Stakeholders process is found in which Process Group?
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
Risk categorization is a tool or technique used in which process?
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
During which process group is the quality policy determined?
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
What is the number of stakeholders, if the project has 28 potential communication channels?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
Which is an example of Administer Procurements?
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
Which action should a project manager take to ensure that the project management plan is effective and current?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
What is an objective of the Develop Project Team process?
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
Which activity is an input to the Conduct Procurements process?
Outputs of the Control Communications process include:
What is the difference between the critical path and the critical chain?
The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
Assigned risk ratings are based upon:
3 Months Free Update
3 Months Free Update
3 Months Free Update