Summer Special - 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: c4sdisc65

PMI-SP PDF

$38.5

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PMI-SP PDF + Testing Engine

$61.6

$175.99

3 Months Free Update

  • Exam Name: PMI Scheduling Professional
  • Last Update: Oct 16, 2025
  • Questions and Answers: 323
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PMI-SP Engine

$46.2

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

PMI-SP Practice Exam Questions with Answers PMI Scheduling Professional Certification

Question # 6

You are the project manager for your project. Your project is scheduled to last for one year and you are currently forty percent complete with the project. Based on your current performance measurements you have an SPI of .95 and a cost variance of -$24,000. You need to report this information to the management, but you will also need a solution to present with the variance information. Which one of the following can you present to the management as a part of the control schedule tools and techniques for variances?

A.

Work performance measurements

B.

Corrective actions

C.

Trim the project scope

D.

Causes of variances

Full Access
Question # 7

Which of the following processes involves the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress and performance as well as to forecast the project results?

A.

Identify stakeholders

B.

Performance reporting

C.

Plan communications

D.

Stakeholder analysis

Full Access
Question # 8

Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.

A.

Conflict resolution should focus on issues, not personalities.

B.

Conflict is natural and forces a search for alternatives.

C.

Openness resolves conflict.

D.

Conflict is an individual issue.

Full Access
Question # 9

You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity.

PMI-SP question answer

What is the latest your project team can complete Activity I?

A.

Day 29

B.

Day 26

C.

Day 25

D.

Day 30

Full Access
Question # 10

You are the project manager for the GHY Project. This project has stakeholders, both internal and external, that need to receive performance reports from you on a regular basis. You have decided that in addition to emailing the weekly performance report, you will also keep the performance reports available on your secured project management Website. The Website is an example of what type of communication reporting?

A.

Pull

B.

Push

C.

Passive

D.

Asynchronous

Full Access
Question # 11

You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?

A.

Direct expense

B.

External requirement

C.

Temporary resource

D.

Expert judgment

Full Access
Question # 12

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

A.

48

B.

55

C.

54

D.

40

Full Access
Question # 13

Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project activities with soft logic. What is soft logic?

A.

Soft logic describes activities that do not have particular resources assigned to them.

B.

Soft logic describes activities that can be completed in any order.

C.

Soft logic describes activities that can have lead time added to them.

D.

Soft logic describes activities that can be crashed because they are effort-driven.

Full Access
Question # 14

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

A.

Quality inspections and compliance

B.

Location, logistics, and resource availability analysis

C.

Labor productivity studies from previous similar projects in the area

D.

The average price of general labor in the area

Full Access
Question # 15

You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The activity list is based on the work packages defined in the project's WBS. Activities provide a basis for all of the following information except for which one?

A.

Scope baseline

B.

Executing

C.

Scheduling

D.

Estimates

Full Access
Question # 16

Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

PMI-SP question answer

If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?

A.

$35,000

B.

$41,700

C.

$6,700

D.

$14,000

Full Access
Question # 17

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's planned value?

A.

$2,025,000

B.

There is not enough information to know

C.

$4,500,000

D.

$2,250,000

Full Access
Question # 18

Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop the project schedule. Which of the following is a tool and technique for the Schedule Development process?

A.

Schedule compression

B.

Reserve analysis

C.

Variance analysis

D.

Expert judgment

Full Access
Question # 19

Once the project's WBS has been created what process may happen next?

A.

Estimate activity resources

B.

Define activities

C.

Estimate activity durations

D.

Sequence activities

Full Access
Question # 20

You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the project set aside for the risk contingency reserve?

A.

$142,000

B.

$232,000

C.

$41,750

D.

$23,750

Full Access
Question # 21

You are the project manager of the NHG. The following figure represents your project network diagram.

PMI-SP question answer

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I. The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

A.

The critical path will now take 26 days.

B.

The critical path will now take 17 days.

C.

The critical path will now take 23 days.

D.

The critical path will now take 20 days.

Full Access
Question # 22

You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?

A.

$566,305

B.

$787,504

C.

$1,312,504

D.

$733,456

Full Access
Question # 23

Ned is the project manager of the HYQ Project. In Ned's project, the management has requested that he enforce resource leveling so that the maximum amount of hours in the project per worker will not exceed 25 hours per week. Ned's pay is based on how quickly he can complete the project work. What must Ned do to accommodate the change in the resource allotment if he has to finish the project on time?

A.

Crash the project.

B.

Add more risk mitigation.

C.

Reduce the amount of labor.

D.

Reduce the project scope.

Full Access
Question # 24

Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?

A.

Analogous

B.

Hanger

C.

Fragment network

D.

Parametric

Full Access
Question # 25

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

A.

Work performance information

B.

Change requests

C.

Work performance measurements

D.

Forecasting method

Full Access
Question # 26

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?

A.

Total float is the amount of time an activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

B.

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project successors.

C.

Total float is the amount of time an activity can be delayed without delaying the project completion date, whereas free float is the amount of time an activity can be delayed without delaying any project predecessors.

D.

Total float is the amount of time a non-critical activity can be delayed without delaying any project successors, whereas free float is the amount of time an activity can be delayed without delaying the project completion date.

Full Access
Question # 27

You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

A.

It means the largest schedule variance you can have is five percent.

B.

It is the earned value divided by the planned value for your project.

C.

It is the expectation of management to be 95 on schedule at 95 percent of the project.

D.

It means you will need to earn at least 95 cents per dollar invested in the project.

Full Access
Question # 28

Fill in the blank with the appropriate word. When activities are logically linked, they become the . __________

Full Access
Question # 29

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

A.

Resource calendar conflict

B.

Matrix network

C.

Organizational process assets

D.

Activity resource requirements

Full Access
Question # 30

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Full Access
Question # 31

You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based on your aggressive scheduling you should at the 45 percent milestone today, but due to some early delays you're running late. What is the schedule variance of your project?

A.

-$29,350

B.

-$117,282

C.

-$938,260

D.

-$11,740

Full Access
Question # 32

Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identify stakeholders process?

A.

Communications management plan

B.

Stakeholder register

C.

Requirements

D.

Stakeholder management strategy

Full Access
Question # 33

The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?

PMI-SP question answer
A.

Static

B.

Deterrent

C.

Noise

D.

Barrier

Full Access
Question # 34

You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You investigate the cause and determine that the project team is not starting their assignments early enough to finish their work on time. While the duration of the assignments may be in synchronization with the duration estimates, the completion time is causing the project schedule to slip from the baseline. What can you do to rectify this problem?

A.

Increase the duration estimates for each activity.

B.

Discipline the project team.

C.

Add management reserve.

D.

Corrective actions.

Full Access
Question # 35

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget-to-date. What is your schedule performance index for this project?

A.

80

B.

1.02

C.

102

D.

0.80

Full Access
Question # 36

You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90. What time will you record for this activity?

A.

48

B.

20o, 45m, 90p

C.

90

D.

45

Full Access
Question # 37

Which one of the following estimate types is a form of expert judgment?

A.

Parametric estimate

B.

Analogous estimate

C.

Bottom-up estimate

D.

Definitive estimate

Full Access
Question # 38

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

PMI-SP question answer

You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?

A.

Five days

B.

Four days

C.

Eleven days

D.

Zero

Full Access
Question # 39

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

A.

Functional Management

B.

Project sponsor

C.

Whomever the communications management plan directs her to

D.

Project customer

Full Access
Question # 40

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment factors and the organizational process assets, you will need seven other inputs to this process. Which one of the following is NOT an input to the Develop Schedule process?

A.

Resource calendars

B.

Schedule data

C.

Activity list

D.

Project scope statement

Full Access
Question # 41

You are the project manager of a project that has a budget of $675,000 and you have completed 40 percent of the project work. Your project is supposed to be 60 percent complete but you are actually only 40 percent complete. Due to some errors, however, you have actually spent $335,000 of the budget. Management wants to know what the project's cost performance index (CPI) is. What value do you report?

A.

-$135,000

B.

.67

C.

.81

D.

-$65,000

Full Access
Question # 42

You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never worked with the technology, as is in this project. During the define activities process, you rely on your project team and two consultants to coach you and identify the type of activities the project will include. Which tool and technique are you using in the define activities process in this scenario?

A.

Templates

B.

Rolling wave planning

C.

Decomposition

D.

Expert judgment

Full Access
Question # 43

Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your project budget to reach this point and you are worried about the project not being able to complete based on your current project budget. What is the to-complete performance index for this project?

A.

0.98

B.

-$16,677

C.

1.07

D.

0.94

Full Access
Question # 44

Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channels will Ben's project have next week?

A.

140

B.

10

C.

325

D.

5

Full Access
Question # 45

Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document must be updated to reflect this change to the approach?

A.

Develop schedule process

B.

Risk register

C.

Project risk management plan

D.

Activity attributes

Full Access
Question # 46

You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project timings for your schedule. Which calendar will communicate to the project stakeholders, when the project work will take place within the organization?

A.

Project calendar

B.

Resource calendar

C.

Organizational calendar

D.

Company calendar

Full Access
Question # 47

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

A.

$176,675

B.

$122,845

C.

-$85,000

D.

-$51,000

Full Access
Question # 48

Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?

A.

Idea/mind mapping

B.

Delphi technique

C.

Nominal group technique

D.

Affinity diagram

Full Access
Question # 49

You are the project manager of the NHGQ project for your company. You must create and distribute performance reports every week to your key project stakeholders. What communication technique do you normally use to distribute reports?

A.

Push technique

B.

Many-to-many

C.

One-to-one

D.

Pull technique

Full Access
Question # 50

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Full Access
Question # 51

You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of report would you create for management, if these instances develop in your project?

A.

Cost variance report

B.

Exceptions report

C.

Performance management report

D.

Schedule variance report

Full Access
Question # 52

You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?

A.

Increase the working hours.

B.

Level the project schedule.

C.

Add more workers.

D.

Reduce the project scope.

Full Access
Question # 53

Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?

A.

Scope of statement

B.

Project charter

C.

Statement of work (SOW)

D.

WBS

Full Access
Question # 54

Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule variance for her project. If Amy's project has a BAC of $750,000 and she has spent $485,000 to date, what is the schedule variance value?

A.

-$75,000

B.

-$42,000

C.

-$45,000

D.

-$65,000

Full Access
Question # 55

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the cost variance for this project that Fred needs to report to management?

A.

$122,845

B.

-$51,000

C.

-$85,000

D.

Zero

Full Access
Question # 56

You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project management plan will guide how and when project resources will be released from the project team?

A.

Project Human Resources Management Plan

B.

Project Staffing Management Plan

C.

Project Communications Management Plan

D.

Project Schedule Management Plan

Full Access
Question # 57

You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:

PMI-SP question answer

Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?

A.

One

B.

Five

C.

Four

D.

Zero

Full Access
Question # 58

You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You decide on to create a new schedule for the project. What project management process are you working with when you create a new target schedule?

A.

Estimate activity durations

B.

Estimate activity resources

C.

Control schedule

D.

Develop schedule

Full Access
Question # 59

Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?

A.

Diane

B.

Project sponsor

C.

Risk owner

D.

Subject matter expert

Full Access
Question # 60

Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still unknown. In her project, Beth is planning in detail only the activities that are most imminent in the project work. This approach to project management planning is known as what?

A.

Imminent activity management

B.

Rolling wave planning

C.

Predecessor-only diagramming

D.

Decomposition

Full Access
Question # 61

Fill in the blank with the appropriate word. ____ management sets the boundaries for the project and is the foundation on which the other project elements are built.

Full Access
Question # 62

Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, he has spent $725,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should Jack tell the management?

A.

$1,087,497.74

B.

$755,000.56

C.

$1,112,978.45

D.

$790,988.76

Full Access
Question # 63

You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special hardware to electronically lock and open the doors. You've gathered the project team before they begin the installation for a hands-on training. As a group you and the project team install 50 doors following a checklist of instructions so that every door will be installed exactly the same throughout the campus and with minimal waste. This is an example of what project execution technique?

A.

Preventive action

B.

Defect repair validation

C.

Implemented corrective action

D.

Quality control

Full Access
Question # 64

Samuel works as a project manager in Bluewell Inc. He is performing constructability analysis in one of the initial planning phases. Which of these does constructability take into account during analysis? Each correct answer represents a complete solution. Choose three.

A.

Quality inspections and compliance

B.

Location, logistics, and resource availability analysis

C.

Labor productivity studies from previous similar projects in the area

D.

The average price of general labor in the area

Full Access
Question # 65

You are the project manager of the QAQ Project. The QAQ Project has a BAC of $2,786,121. You are currently 20 percent complete with this project, though you should be 25 percent complete with the project work. The project has consumed $595,000 of the project budget to date. Management has asked you, based on the current project performance, what the project's estimate to complete will be considering the current project schedule variance. What is the ETC for this project?

A.

$2,975,000

B.

1.02

C.

$139,306

D.

$2,380,000

Full Access
Question # 66

You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?

A.

Project is behind the schedule.

B.

Costs are higher than planned.

C.

Costs are right on target.

D.

Costs are lower than planned.

Full Access
Question # 67

Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?

A.

-$11,000

B.

.96

C.

There is not enough information to know.

D.

1

Full Access
Question # 68

You are the project manager of the GHQ Project. You have to prioritize activities for the effective management of project. For this, you have created a network diagram to schedule a set of project activities as shown in the figure:

PMI-SP question answer

Based on this figure, what is the critical path of this project?

A.

ABEHJ

B.

ACFIJ

C.

ADGJ

D.

ACFGJ

Full Access
Question # 69

Anna is the project manager of the NHQ project. Her project has 1,500 stakeholders, some of which are external to her organization. In this project, Anna wants to create a method to classify the stakeholders based on their level of authority and their level of concern regarding the project outcomes. This model will help Anna determine the communication demands and when information should be distributed. What does Anna want to create in this instance?

A.

Power/interest grid

B.

Salience model

C.

Power/influence grid

D.

Communications matrix

Full Access
Question # 70

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?

A.

$163,626

B.

$130,901

C.

-$985,040

D.

0.16

Full Access
Question # 71

You work as a project manager for BlueWell Inc. You are going through a project with your project team. Some of your project team members are reporting that their activities are running late because there are lag times between activities that do not need to be there. You examine the schedule and see that the lag times have been incorporated into the project schedule for quality control reviews. You also learn that the quality control reviews are not being completed as planned. What is the best approach in this scenario?

A.

Since the quality control inspections are not being completed, remove the lag time from the project.

B.

Take corrective action and determine when the quality control inspection has happened so far in the project, perform quality control on the deliverables where the inspection was skipped, and ensure that quality control will happen from this point forward.

C.

Since the quality control inspections are not being completed, take corrective action and ensure that the inspections continue from this point forward.

D.

Discuss with the project team that the lag times should not affect the project schedule because they were built into the project schedule to begin with. Even if the quality control inspections were happening the time was allotted in the schedule for the inspections.

Full Access
Question # 72

Which of the following group activity techniques allows a large number of ideas to be sorted into groups for review and analysis?

A.

Idea/mind mapping

B.

Nominal group technique

C.

Delphi technique

D.

Affinity diagram

Full Access
Question # 73

You are the project manager of the GYG Project. A new scope change is being considered for your project. You are concerned, however, that the scope change may add costs, risks, and adversely affect the project schedule. What project management process is responsible for evaluating the full effect of a proposed scope change on your project?

A.

Scope change control

B.

Schedule change control

C.

Integrated change control

D.

Change Control Board approval process

Full Access
Question # 74

Virginia is the project manager for her company. She has used a previous project as a basis for her current project because they are similar in nature. Virginia has adapted nearly all of the previous project plans for her current project - including the project schedule, risk register, and communications management plan. She has worked with management to update the plans to adapt them to the current project. What are the previous project management plans called in this instance?

A.

Expert judgment

B.

Analogous estimate

C.

Templates

D.

Parametric estimate

Full Access
Question # 75

Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.

Full Access
Question # 76

Alicia works as a project manager for NacTec project. She is undergoing the project monitoring phase in her project. Which of the following will she choose to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

A.

Reports

B.

Meetings

C.

Diaries

D.

Future planning

Full Access
Question # 77

You are the project manager for your organization. Your project will be utilizing a piece of equipment during its process of completion. There is some concern that your project's use of the equipment may conflict with another project. What document will help you determine when and how long you will use the shared equipment?

A.

Project schedule

B.

Project scope

C.

Project calendar

D.

Resource calendar

Full Access
Question # 78

Which of the following is an output of the Identify Stakeholders process?

A.

Scope baseline

B.

Project scope statement

C.

Project charter

D.

Stakeholder register

Full Access
Question # 79

Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.

A.

Forecast by analogy

B.

Technology forecasting

C.

Autoregressive moving average

D.

Scenario building

Full Access
Question # 80

Harry works as a project manager for BlueWell Inc. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. Who among the following is responsible for implementing the risk responses or contingency plan?

A.

Risk owner

B.

Harry

C.

Project sponsor

D.

Subject matter expert

Full Access
Question # 81

Terri is the project manager for her organization and she is working with her project team to develop the project schedule. She has identified the float in her project although some of the activities where float exists may be susceptible to risk in the project execution. She is also concerned that the critical path may change during the project if the risk events come into execution. What scheduling method is Terri using in this example?

A.

Critical chain method

B.

Risk analysis method

C.

Activity on the arrow method

D.

Critical path method

Full Access
Question # 82

What formula would you use if your project had a BAC of $450,000, you have spent $191,000, and you are 40 percent complete though you are supposed to be 55 percent done and management wants to know your project's schedule performance index?

A.

($450,000 - $180,000) / ($450,000 - $191,000)

B.

$450,000 - $477,500

C.

$180,000 / $247,500

D.

$180,000 - $247,500

Full Access
Question # 83

Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

A.

Mandatory dependencies

B.

Required dependencies

C.

Discretionary dependencies

D.

External dependencies

Full Access
Question # 84

You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft project. Microsoft project as a scheduling tool is an example of what tool and technique for the Develop Schedule Process?

A.

Organizational process asset

B.

Scheduling tool

C.

Project Management Information System

D.

Project office software

Full Access
Question # 85

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty-four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

A.

Fred should add twenty-four hours of lead time to each of the 456 rooms painting activity to account for the primer's curing time.

B.

Fred should add twenty-four hours of lag time to each of the 456 rooms painting activity to account for the primer's curing time.

C.

Fred should add an intermediary task with a duration of twenty-four hours.

D.

Fred should schedule all 456 hotels rooms to be primed first and then schedule all 456 rooms to be painted to ensure time for the curing.

Full Access
Question # 86

Amy works as a project manager for BlueWell Inc. She is working on the SDI project, which has a BAC of $2,816,000. She is currently 20 percent complete with this project, though she should be 25 percent complete with the project work. The project has consumed $495,000 of the project budget to date. Management has asked her the project's Estimate To Complete (ETC) based on the current project performance. What is the ETC for this project?

A.

$1,312,504

B.

$1,979,952

C.

$1,541,544

D.

$2,474,952

Full Access
Question # 87

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

A.

$227,140

B.

0.75

C.

0.95

D.

-$56,789

Full Access
Question # 88

Bonnie is the project manager for her organization. She is developing a strategy to manage the project stakeholders. She wants to identify the key stakeholders, their influence over the project, their interest in project, and an assessment of methods. What can Bonnie create to gain support from the stakeholders in her project?

A.

Stakeholder identification tools

B.

Expert judgment

C.

Stakeholder Analysis Matrix

D.

Communications management plan

Full Access
Question # 89

You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson's Law state about this scenario?

A.

Work expands to fulfill the amount of time allotted to it.

B.

Risks will be allowed into activities in which management creates risk provisions.

C.

Laborers will create errors when time has been allotted for errors to exist.

D.

Errors will be allowed into assignments when management creates error opportunity.

Full Access
Question # 90

Which of the following techniques is used in businesses to determine the effect different costs or investments have on profit and other financial indicators?

A.

Schedule analysis

B.

Resource leveling

C.

What-if scenario analysis

D.

Root cause analysis

Full Access
Question # 91

You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

A.

Stakeholder classification

B.

Project management team's classification

C.

Assessment information

D.

Identification information

Full Access
Question # 92

You are the project manager of a software development project. Your project team will be creating a web-based software application that will allow your company's customers to browse your website, search inventory, and place orders among other things. Your project team will, on a regular basis, need to update their computer virus prevention software, update their operating systems, and perform other maintenance on their computers in order to complete the project. This maintenance work is not directly tied to the project deliverables, but it is needed in order for the project to be completed. What term best describes this maintenance work?

A.

Project management overhead

B.

Discrete effort

C.

Level of effort

D.

Cost of conformance to quality

Full Access
Question # 93

You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization.

PMI-SP question answer

How much float can you use on Activity G if Activity B actually takes eight days to complete?

A.

Four

B.

Three

C.

Seven

D.

Zero

Full Access
Question # 94

A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.

A.

Performance control

B.

Execution scheduling

C.

Leadership

D.

Feasibility planning

Full Access
Question # 95

You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your project performance to date. Where can you find a list of the project milestones to anticipate management's request?

A.

Scope baseline

B.

Milestone list

C.

Project charter

D.

Project Schedule Management Plan

Full Access
Question # 96

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. Based on the budget at completion, what is this project's to-complete performance index?

A.

-$108,120

B.

0.98

C.

$2,500.000

D.

1.02

Full Access