Halloween Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

PMP PDF

$119.7

$399

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PMP PDF + Testing Engine

$179.7

$599

3 Months Free Update

  • Exam Name: Project Management Professional (2025 Version)
  • Last Update: Oct 31, 2025
  • Questions and Answers: 2040
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PMP Engine

$134.7

$449

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

PMP Practice Exam Questions with Answers Project Management Professional (2025 Version) Certification

Question # 6

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

Full Access
Question # 7

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Full Access
Question # 8

A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

A.

Use an agile approach and engage a vendor that delivered well in a previous organization.

B.

Consult the product owner and engage a vendor that is recommended by them.

C.

Consult the development team and engage a vendor that is recommended by them.

D.

Use a formal approach using procurement policies, procedures, forms, and work instructions.

Full Access
Question # 9

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

A.

Keep the project focused and executed in silos for better outcomes.

B.

Report the concern to the agile project management office (PMO),

C.

Inform the product owner of the concern so that i can be addressed.

D.

Open up to the team to work collaboratively to achieve the outcomes.

Full Access
Question # 10

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.

What should the project manager do?

A.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.

B.

Suggest the team member postpone their enrollment in the master's program until the project is completed.

C.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.

D.

Assess the team member's commitment to the master's program and its impact on project performance.

Full Access
Question # 11

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

A.

Calculate the payback period (PBP) for building a new branch in each location versus renting an existing building.

B.

Calculate the costs for each option in each location and compare the net present value (NPV) for each.

C.

Perform a Kano analysis on building a new branch versus renting in each of the locations.

D.

Perform a gap analysis on renting in each of the locations.

Full Access
Question # 12

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Full Access
Question # 13

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,

B.

Send emails with information about the project deliverables on the first day of the project.

C.

Connect with every location and check their preferred methods of communication.

D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.

Full Access
Question # 14

A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager

expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project

manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.

What engagement model should the project manager use for the technical architect role to ensure project success?

A.

Hire a new technical architect who would be solely dedicated to the current project.

B.

Share the existing technical architect so they can be allocated to the current project and other projects.

C.

Hire a new technical architect who would be shared between the current project and other projects.

D.

Assign the existing technical architect to solely be dedicated to the current project.

Full Access
Question # 15

A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the

obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.

What should the project manager have done to avoid this issue?

A.

Prioritized blockers on the critical path

B.

Distributed the daily standup meeting agenda beforehand

C.

Followed the quality control measurements

D.

Developed the team members’ competences:

Full Access
Question # 16

A customer wants to launch a new product in the market and an agile team is set up to work on this project for 9 months After 1 month the customer feels that it would be better to release the product 2 months earlier than the planned date. The task is now assigned to the most talented resource in the organization to this project tor an early finish.

Which risk management strategy has been adopted in this scenario?

A.

Shared

B.

Accepted

C.

Enhanced

D.

Exploited

Full Access
Question # 17

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

A.

Rebaseline the project schedule to absorb the delay.

B.

Report the delay with rectifying actions to the project management office (PMO).

C.

Notify the project steering committee about the cause of the delay.

D.

Report the delay with rectifying actions to the change control board (CCB) for review,

Full Access
Question # 18

A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.

In which project document should the project manager record the concern?

A.

Request for information

B.

Scope statement

C.

Issue log

D.

Risk register

Full Access
Question # 19

After reviewing the lessons learned database, a project manager realizes that the current team may not be knowledgeable enough about organizational processes for the needs of a new project. What should the project manager do?

A.

Develop the team members to work as a cross-functional team.

B.

Ask a functional manager to provide the right team members.

C.

Review the project charter to see if the scope can be modified.

D.

Ask the portfolio manager to reassign the project to another team.

Full Access
Question # 20

Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.

What should the project manager do to address this concern?

A.

Schedule a dedicated session to review the team charter.

B.

Set up a meeting with the team member to review the team charter.

C.

Ask another team member to meet with this team member for a discussion.

D.

Send a reminder to the team member about the rule being violated.

Full Access
Question # 21

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

PMP question answer

Full Access
Question # 22

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Full Access
Question # 23

A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?

A.

Explain to the stakeholder that any modifications require additional budget

B.

Review the missed program deliverables with the project team

C.

Review the project charter for the project approval criteria

D.

Speak with the team's manager to get extra hours from the team

Full Access
Question # 24

A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on

weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.

What should the project manager do?

A.

Implement the call center with internal staff to ensure the work is performed according to the company’s culture.

B.

Work with 50% of the people internally and contract the other 50% to an outside company.

C.

Delegate the analysis to the human resources (HR) department in order to organize the call center operations.

D.

Conduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.

Full Access
Question # 25

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)

A.

Strive toward continuous improvement

B.

Work together daily as a team

C.

Only share suggestions at the end of the sprint

D.

Follow the sprint planning

E.

Send communications to the entire team

Full Access
Question # 26

A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.

What should the project manager do next?

A.

Review organizational process assets (OPAs) for clarity.

B.

Document lessons learned before closing.

C.

Consult the project charter for next steps.

D.

Confirm the definition of done (DoD) has been met.

Full Access
Question # 27

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

A.

Inform the functional manager that self-organization includes task allocation.

B.

Confirm with the team members that the functional manager is responsible for the delivery.

C.

Ask the product owner to clarify the roles and responsibilities of the project team.

D.

Inform the functional manager that task allocation is the responsibility of the product owner.

Full Access
Question # 28

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Full Access
Question # 29

An agile project is in its early iterations, but the project manager already realizes that

more resources will be needed to achieve the expected time lines. There are no internal

resources. available.

What vendor strategy should the project manager use to maximize project delivery?

A.

Use compression techniques to break down the scope and assign the scope pieces todifferent vendors with a fixed-price contract.

B.

Use the contingency budget for hiring additional vendor resources to mitigate any projectrisk.

C.

Engage in a time and materials (T&M) contract and hire a local vendor to supportdevelopment.

D.

Establish a solid view of the scope and requirements and engage a vendor with a fixed price contract.

Full Access
Question # 30

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

A.

Instruct the team members involved to resolve the issue among themselves

B.

Discuss the issue with the steering committee to determine the proper course of action.

C.

Coordinate a video conference with the offending team member to resolve the issue

D.

Reassign the offending team member to a different project

Full Access
Question # 31

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

A.

Discuss the vacation plan and include scheduling changes in the change log database.

B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.

C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.

D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.

Full Access
Question # 32

A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?

A.

Work with the product owner to evaluate and prioritize the requirements

B.

Ask the lead developer to run a meeting with the stakeholders to agree on an ordered list

C.

Determine the expected benefits of each requirement to maximize the overall business value

D.

Prioritize the requirements based on the hierarchical level of the requesting stakeholders

Full Access
Question # 33

A CEO has requested that the project manager provide a budget estimate for a long-term project that will be executed over the span of 4 years What should the project manager do?

A.

Include enterprise environmental factors (EEFs)

B.

Conduct a bottom-up estimate

C.

Include projected inflation rates

D.

Conduct an analogous estimate

Full Access
Question # 34

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

PMP question answer

Full Access
Question # 35

During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables

How should the project manager mitigate this risk without compromising the completion date?

A.

Review the integrated change control process to restrict the number of changes

B.

Focus on delivering incremental value through multiple smaller deliveries

C.

Request sponsor support to get buy-in from the users and stakeholders

D.

Restart the stakeholder engagement process by collecting user requirements again

Full Access
Question # 36

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important

milestone in a week.

What should the project manager do next?

A.

Ask the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

B.

Perform market research to find out if there are other vendors that can produce similar kinds of materials.

C.

Submit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.

D.

Involve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.

Full Access
Question # 37

A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution

phase and will affect a few key workers’ licenses, which will become noncompliant.

What should the project manager do?

A.

Start scheduling the training for key workers now to ensure compliance.

B.

Maintain the current key workers since the project has already started.

C.

Update the project charter to ensure the new legislation is addressed,

D.

Start a recruitment drive for new workers with the licenses required.

Full Access
Question # 38

A project manager is assigned to a project that has a tight schedule. Due to recent market changes the marketing team has identified that a few features that were initially in the scope are no longer required

What should the project manager do?

A.

Advise the marketing team that at this stage of the project changes to the scope are no longer accepted

B.

Escalate the issue to the project management office (PMO) and make sure they understand the impact on the schedule due to the change

C.

Update the risk register with input from marketing and sales and highlight the benefits of the features m discussion

D.

Review the change request with the project stakeholders and evaluate the impact of the scope reduction

Full Access
Question # 39

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Full Access
Question # 40

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?

A.

Review the benefits management plan

B.

Refer to the lessons learned from the first phase

C.

Consult the project reports from the previous project manager

D.

Collect information from related departments

Full Access
Question # 41

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Full Access
Question # 42

A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?

A.

Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible.

B.

Ask the sponsor for support regarding the allocation of additional resources to finish on time.

C.

Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources.

D.

Meet with the customer to agree on the components of the solution and the priorities.

Full Access
Question # 43

In a geographically distributed project team, the project team members continue to email status reports and update schedules after their weekly meeting discussions. However, the team is having difficulty tracking the changes and progress made.

What should the project manager do?

A.

Maintain a central repository of artifacts with a version control system.

B.

Maintain separate document control via regions to avoid discrepancies.

C.

Develop a document management software for version control.

D.

Facilitate training on version control and project artifacts,

Full Access
Question # 44

A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?

A.

Escalate the situation to the customer management team.

B.

Ask the customer to discuss these changes with the product owner.

C.

Request that the customer to meet with the team only at the weekly meeting.

D.

Ask the customer to discuss these changes with the management team.

Full Access
Question # 45

During the final iteration of the execution phase, the project has a cost performance

index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.

How should the project manager avoid a budget shortfall?

A.

Follow the risk management plan.

B.

Reduce the team effort utilization.

C.

Look for cost-saving opportunities.

D.

Submit a change request to add to the management reserve.

Full Access
Question # 46

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.

What should the project manager do?

A.

Organize a brainstorming session with the project team to address the issue.

B.

Advise the project team on the importance of team engagement,

C.

Invest in coaching and training for all project team members.

D.

Escalate the issue with the human resource (HR) department to take action,

Full Access
Question # 47

A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.

The project team will be virtual and will include members from different countries around the world.

What should the project manager do to ensure effective team building occurs?

A.

Coordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and culturalobservance information.

B.

Explain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.

C.

Update the communications management plan and determine an issue resolution process for when furture conflicts arise.

D.

Colocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overallproject governance.

Full Access
Question # 48

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours. However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

A.

Allow the most senior team members to decide the time that works for the team.

B.

Reassess the team's hours collaboratively so that the team is not impeded by the issue.

C.

Discuss the lack of dedication with the team member and their functional manager.

D.

Remove the team member from the project team to be fair to the other members.

Full Access
Question # 49

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk ofbeing noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurityrequirements.

Full Access
Question # 50

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Full Access
Question # 51

A procurement team lead has been reported as getting into conflicts with other project team members on a weekly basis, The project manager engages with the team lead and discovers that other team members do not believe the team lead is right for this position.

What should the project manager do to resolve these recurring conflicts between the team lead and the other team members?

A.

Receive details of the conflicts from all involved, issue all a warning notice, and send all to leadership training.

B.

Organize a meeting to discuss emotional intelligence with the team, and establish a rule of respect and special treatment for the team lead.

C.

Issue the team lead a warning, and consider recommending the team lead for emotional intelligence training.

D.

Find ways to reduce the tension, increase cooperation, and understand the emotions of all team members involved.

Full Access
Question # 52

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

A.

Ask the team to solve the issue internally and review the underperforming resource's situation

B.

Meet with the team member privately to discuss the problem and work together to find a solution

C.

Contact the functional manager and request to replace the team member with a better resource

D.

Discuss various options to improve the team member's performance with their functional managers

Full Access
Question # 53

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Full Access
Question # 54

A project team has finished participating in an iterative product increment planning session. After the planning session, the team returns with a list of features to deliver.

How should the project manager ensure the product increments deliver the anticipated requirements?

A.

Appoint a dedicated product manager for the duration of the release

B.

Have the customer approve the product increment features.

C.

Ensure every user story has acceptance criteria.

D.

Track business outcomes for planned user stories.

Full Access
Question # 55

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools

In order to deliver the project successfully, what should the project manager focus on as part of the plan?

A.

Align with the organization's project management office (PMO) to inform and make them aware of the new approach

B.

Explain and communicate the new approach to the project sponsor and key stakeholders

C.

Develop a detailed schedule for the entire project m the planning phase and communicate that to the stakeholders

D.

Communicate with other project managers to see how they manage hybrid projects

Full Access
Question # 56

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

Full Access
Question # 57

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Full Access
Question # 58

A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?

A.

Review the deliverable carefully and determine the right status

B.

Assign one person to be responsible for the task

C.

Establish a clear definition of done (DoD) for each task

D.

Encourage team members to work together

Full Access
Question # 59

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add n as an issue m the issue log

C.

Escalate the issue to the functional manager

D.

Direct the sales team to speak with accounting to resolve the issue

Full Access
Question # 60

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Full Access
Question # 61

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Full Access
Question # 62

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Full Access
Question # 63

A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be

enough to add business value.

With the project on a fixed budget, what should the project manager do next?

A.

Plan the project based on the available resources and submit a change request upon completion.

B.

Gather all stakeholders and provide recommendations on a smaller, more feasible project scope,

C.

Identify the technical requirements and request that management hire external resources,

D.

Document the problem in the issue log and suggest a change request to decrease the scope.

Full Access
Question # 64

During a standup meeting, a team member raises the issue that they have blockers and impediments preventing them from moving on to the next task. How should the project lead

handle this situation?

A.

Support the team member by removing the blockers and impediments.

B.

Allocate the blockers and impediments to the product owner to resolve.

C.

Insist that the person who raised the blockers and impediments take ownership.

D.

Add any blockers or impediments to the risk register,

Full Access
Question # 65

A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.

How should the project manager resolve this situation in their new role as servant leader?

A.

Review the organizational process assets (OPAs) to find similar situations and review the resolution actions taken,

B.

Request that the team use the next sprint to complete all technical debt remaining from the previous sprints.

C.

Extend the sprints to 3 weeks to allow the work requested by the product owner to be completed.

D.

Encourage the whole team to be empowered and accountable for the decisions made according to their roles,

Full Access
Question # 66

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Full Access
Question # 67

A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.

What should the project manager do?

A.

Meet with this team member.

B.

Review this method with the team.

C.

Accept this task-based estimation.

D.

Reject this task-based estimation.

Full Access
Question # 68

A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.

What should the project manager do next?

A.

Explore the minimum requirements of the product and their feasibility.

B.

Explain the resource constraints of the project to management.

C.

Outsource the management of the product to an external team.

D.

Conduct a detailed risk analysis to highlight the risks in the project.

Full Access
Question # 69

A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country's economy is struggling, and some stakeholders cannot agree on this transformation need

What should the project manager do'?

A.

Escalate the issue to the sponsor and ask for stakeholder engagement

B.

Review the project business case and update it periodically

C.

Plan for strategic program management

D.

Implement a communications management plan

Full Access
Question # 70

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

PMP question answer

Full Access
Question # 71

A project is approaching its project closure phase, and the project manager receives

an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.

Which three actions should the project manager ask the project specialist to take? (Choose

three)

A.

Create a quality assurance plan for the documentation.

B.

Identify the components of the project documentation.

C.

Archive only the initial and draft versions of the documents.

D.

Ensure that the documents are in an easily retrievable form.

E.

Collect the documents at the time of their creation.

Full Access
Question # 72

A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements.

The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.

What should the project manager do?

A.

Update the communications matrix to ensure that client team member is included.

B.

Submit a change request to cover extra hours associated with project meetings.

C.

Increase the project meeting frequency and duration to allow for the extra work required.

D.

Speak with the client team member about the continuous delays during project meetings.

Full Access
Question # 73

A new solution is being deployed in countries A B and C. This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market

What should the project manager in charge of the deployment in country A do?

A.

Accept the change request from country A and reschedule the deployment project for country A.

B.

Take the request into account and ask the sponsor to inform countries B and C about the change

C.

Ask country A to submit a change request that will be analyzed along with countries B and C

D.

Refuse country As request as there is no time for the change as deployment has already begun

Full Access
Question # 74

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety

approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

A.

Complete development with all functionalities in perfect condition prior to demonstrating to stakeholders to ensure a great first impression.

B.

Complete development for each sprint and demonstrate the product increment to internal stakeholders and the government, without engaging other externalstakeholders.

C.

Complete development for the must-have functionalities only prior to demonstration in order to fail fast and get early feedback.

D.

Complete development for must-have functionalities only and demonstrate it to a focus group, but wait until all development is complete to demonstrate it to thegovernment.

Full Access
Question # 75

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Full Access
Question # 76

A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?

A.

Review the project scope to align the project teams

B.

Review the resource management plan to align the project teams

C.

Review the project integration plan to align the project teams

D.

Review the work breakdown structure (WBS) to align the project teams

Full Access
Question # 77

A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.

In order to help the team, what should the project leader do?

A.

Recommend that the product owner reviews the backlog refinement processes.

B.

Recommend that the team reviews the length of the iteration with the stakeholders.

C.

Recommend limiting the work in progress to improve the team’s focus.

D.

Recommend a review of the team members’ individual performances.

Full Access
Question # 78

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Full Access
Question # 79

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

A.

Propose using a compliance review board that will be responsible for approving allproduct features prior to their release to the public.

B.

Liaison with the compliance group, making them responsible for understanding therequirements and keeping them prioritized in the backlog.

C.

Meet with the compliance team and make sure that their requirements are covered in thedefinition of done (DoD) for each story.

D.

Ensure that the peer review process also covers compliance requirements, creating asecond layer of security for the project.

Full Access
Question # 80

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

A.

Assign the marketing executive's tasks to another project team member

B.

Review the executive's declining performance with human resources (HR)

C.

Show empathy and praise the marketing executive's strengths

D.

Make the marketing executive accountable for their work and output

Full Access
Question # 81

A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?

A.

Developing new product lines

B.

Complying with new regulations

C.

Establishing company processes

D.

Certifying sustainable products

Full Access
Question # 82

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Full Access
Question # 83

A software development provider reports an issue that is blocking the other remaining deliverables What should the project manager do?

A.

Ask the provider to seek options to solve the issue

B.

Add the issue to the issue log and report it at the next review meeting

C.

Review the current plan and consolidate if necessary

D.

Schedule a meeting with the provider to collaborate on the options

Full Access
Question # 84

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

A.

Request approval from the company director to conduct training for the team.

B.

Ask the senior developer to rewrite all the stories.

C.

Engage with the customer and rewrite all the stories.

D.

Rewrite the stories to include the technical vision of the product.

Full Access
Question # 85

A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team

What should the project manager do?

A.

Add a user story during sprint planning that gives recognition to behaviors that are aligned with the new values

B.

Send a standard email to the team prior to every daily standup containing the new values

C.

Organize a team meeting focusing on the new values associated with the transformation

D.

Give recognition to team members' behaviors that are aligned with the new values during the sprint retrospectives

Full Access
Question # 86

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member Is crying about the pressures of an upcoming deadline.

What should the project manager do?

A.

Ask the team member to send their concerns in writing.

B.

Empathize with the team member and discuss next steps.

C.

Review the organization's human resources (HR) policy.

D.

Schedule a meeting with the team member for the next work day.

Full Access
Question # 87

A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for

the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.

Which stakeholders should the project manager include in the stakeholder engagement plan?

A.

Stakeholders who have been identified and who have needs and a potential impact on the project.

B.

Stakeholders who are selected by the project sponsor who have a potential impact on the project.

C.

Stakeholders who disagree with the project so as to proactively manage their expectations.

D.

Stakeholders who are supporting the project in order to obtain additional resources.

Full Access
Question # 88

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

Full Access
Question # 89

A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously, this defect negatively affected the project schedule.

What should the project manager do first?

A.

Update the risk management plan.

B.

Extend the timeline of the project.

C.

Check the organizational process assets (OPAs).

D.

Acquire knowledgeable resources.

Full Access
Question # 90

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Full Access
Question # 91

A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market

How should the project manager address this issue?

A.

Assess the business value impact and review the product roadmap to include any changes

B.

Schedule a retrospective to understand why the new requirement was not included in product backlog previously

C.

Stop the product release and start adding new user stones to the product backlog for any new requirements

D.

Proceed with product delivery as planned and start a new requirement analysis for the next iteration

Full Access
Question # 92

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Full Access
Question # 93

A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.

How will the project manager be able to complete this task?

A.

Tell the owner that a rough order of magnitude will be provided.

B.

Contact a subject matter expert (SME) for advice and consultation.

C.

Call a meeting with the project team to identify the most appropriate approach.

D.

Tell the owner that the task requires more time and expertise

Full Access
Question # 94

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members' supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

Full Access
Question # 95

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Full Access
Question # 96

A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and

delay new feature development.

Which action should the project manager take to resolve the quality issues?

A.

Plan for continuous validation of the product.

B.

Discuss adding business scenario tests with the customer.

C.

Discuss adding additional test cases with the product owner.

D.

Add more test scenarios based on the issues found.

Full Access
Question # 97

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

A.

Dedicate the next sprint to completing the missing details.

B.

Apply fast-track techniques to work on the missing details in parallel,

C.

Continue iterating and monitoring quality aspects sprint by sprint.

D.

Create a new risk entry for the delay in the risk management plan.

Full Access
Question # 98

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a

critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining

that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

A.

Communicated a new delivery date to the customer along with the news about the delay

B.

Disclosed to senior management in confidence, then communicated the delay to the customer

C.

Assessed the situation with the project stakeholders first and communicated the impact to the customer

D.

Spoken to the customer on the phone and explained the reason for the delay instead of writing an email

Full Access
Question # 99

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

A.

Performed a stakeholder analysis when the sponsor joined the project

B.

Held a governance meeting to review the project increment

C.

Conducted a product iteration review with the new project sponsor

D.

Escalated the issue to ensure the increment would be approved

Full Access
Question # 100

While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because

of that, each feature is taking longer than initially estimated.

What should the project manager do to address the issue?

A.

Escalate the issue to the project sponsor.

B.

Address the issue during the next sprint planning meeting.

C.

Initiate a change request to extend the project end date.

D.

Extend the dates for future project milestones.

Full Access
Question # 101

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

Full Access
Question # 102

A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.

What should the project manager have done*?

A.

Confirmed that the communication was understood and solicited feedback from the team

B.

Sent the roles and responsibilities matrix along with the project management plan

C.

Discussed the roles with the managers to help explain them to their team members

D.

Briefed each team member on their roles before sending the project management plan

Full Access
Question # 103

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

A.

Escalate the team member's disruptive behavior to their functional manager.

B.

Collaborate with the team to arrive at team ground rules and publish the rules to the team.

C.

Observe to ensure this typical forming stage behavior does not escalate beyond what is acceptable.

D.

Request team members document their decisions independently and share with each other.

Full Access
Question # 104

A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.

How should the project manager ensure the acceptance criteria are ret?

A.

Perform tests and routinely track results as per the quality management plan.

B.

Make sure the stakeholders are aware of the acceptance criteria.

C.

Negotiate to obtain approval if most of the tests have passed.

D.

Modify the acceptance criteria before the official delivery.

Full Access
Question # 105

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

A.

Manage the risks associated with the proposed approach.

B.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.

C.

Coordinate with the business unit to get detailed requirements.

D.

Work closely with the marketing team on market research and product segments

Full Access
Question # 106

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress

What should the project manager do first?

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

Full Access
Question # 107

A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.

What should the project manager do next?

A.

Foster knowledge sharing and coaching among team members.

B.

Arrange for external training amid the tight project schedules.

C.

Add new members for the underperforming team.

D.

Seek an external expert to review the framework.

Full Access
Question # 108

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

A.

Modify the project management plan and get approval from relevant stakeholders

B.

Add more resources to recover the schedule without making changes to the baseline.

C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.

Negotiate with the project sponsor immediately and establish a new project charter.

Full Access
Question # 109

A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.

What should the project manager do?

A.

Start working on the resource management plan in order to identify the best team for the project.

B.

Utilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.

C.

Review the competitor's app to understand the functionalities that the project scope should consider.

D.

Define the project scope with the stakeholders and determine how formal acceptance will be obtained.

Full Access
Question # 110

A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.

What should the project manager do?

A.

Place the new team member on a performance improvement program.

B.

Ask another team member to take some of the new team member's work.

C.

Assign easier activities to the new team member.

D.

Allocate time within the iterations to mentor the new team member.

Full Access
Question # 111

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?

A.

Project sponsors

B.

Other project managers

C.

Business unit managers

D.

Program managers

Full Access
Question # 112

Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.

What should the project manager have done to avoid this situation?

A.

Ensured that communications were sent to all stakeholders when requirements change

B.

Ensured procurement contracts were able be canceled when situations like this arise

C.

Ensured project requirements were validated and communicated with the procurement team

D.

Ensured changing stakeholder needs and requests were properly monitored

Full Access
Question # 113

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Full Access
Question # 114

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

Full Access
Question # 115

A project manager is leading an agile team. The daily standups and iteration meetings are currently facilitated by the product owner. A team member contacts the project manager and mentions that they are looking to improve their facilitation skills.

How should the project manager respond to this request?

A.

Ask the team member to review the lessons learned on facilitation from previous projects.

B.

Suggest that the team member facilitate an upcoming iteration and review the outcomes in the iteration retrospective.

C.

Engage their functional manager to determine if there is alignment to their development plan before agreeing.

D.

Add new elements to the project backlog to account for the training needs of the team member.

Full Access
Question # 116

A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module.

The marketing department believes that a main competitor is working on a similar product.

Which delivery approach should the project manager use for this project?

A.

Traditional delivery, to ensure high quality and that the product meets market demands

B.

Extreme Programming (XP) delivery, to mitigate the high risk related to a new product

C.

Iterative delivery, to ensure that user feedback is incorporated into the second iteration

D.

Incremental delivery, to ensure that mobile capability is released fast to the users

Full Access
Question # 117

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

A.

Select members for their skill or potential.

B.

Establish the project scope and set clear team objectives.

C.

Set performance standards and direction.

D.

Hold early kick-off meetings and regular weekly meetings.

Full Access
Question # 118

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

A.

Reschedule the project taking this new information into account.

B.

Refer to the project's resource management plan.

C.

Ask the project sponsor for external resources.

D.

Create a change request to be validated by the project sponsor.

Full Access
Question # 119

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

A.

Forward the client's request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

Full Access
Question # 120

A company's project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has

identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.

What should the project manager do first?

A.

Investigate the reasons for the disagreement to understand the gap among the stakeholders and search for consensus.

B.

Discuss the situation with the stakeholders to evaluate other adaptive tools for the project.

C.

Schedule training sessions for the stakeholders on the benefits of the adaptive tools.

D.

Update the risk register and escalate the disagreement to the project sponsor and distribute the status to the team.

Full Access
Question # 121

A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.

What should the project manager do?

A.

Invite the sales manager to the next sprint meeting to clarify requirements.

B.

Create a new item in the sprint backlog to determine the appropriate algorithm.

C.

Ask the scrum master to choose an algorithm based on the pros and cons of each option.

D.

Request a meeting with the product owner to help clarify the user story.

Full Access
Question # 122

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

A.

Prioritize other items for the team and deal with the conflicting requirements later.

B.

Allow the project team to decide what is the most appropriate requirement to follow.

C.

Escalate to the project management office (PMO) and request a solution for the requirements.

D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.

Full Access
Question # 123

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

A.

Ask the experienced members to lead the junior members to facilitate skill transfer.

B.

Encourage team members to focus on delivering results with their specialized skills.

C.

Organize networking sessions to allow the team members to get to know one another.

D.

Ask the team to self-organize and escalate any issues to the project manager.

Full Access
Question # 124

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Full Access
Question # 125

A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.

What should the project manager do first to verify alignment?

A.

Ask the project team to delay the kick-off while resolving the concern.

B.

Request a copy of the project assumptions log for more insight.

C.

Meet with the project sponsor to obtain more information.

D.

Consult with the project team members to gain their opinions.

Full Access
Question # 126

During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.

What should the project manager do next?

A.

Escalate the situation again to the project sponsor.

B.

Review this obstacle during the daily standup meeting.

C.

Request a new resource to execute the activities.

D.

Provide feedback to the resource at the sprint review.

Full Access
Question # 127

A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.

What should the project manager do to create a positive environment?

A.

Establish the team ground rules and share them with the team for strict adherence.

B.

Copy the ground rules established by another project and provide them to the teams.

C.

Extract the organization's policies and processes, customize them, and give them to the teams to adhere to.

D.

Help the teams in establishing and adhering to their ground rules and revisit after regular intervals.

Full Access
Question # 128

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Full Access
Question # 129

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

A.

Fast track this dependency to avoid delaying the project.

B.

Perform Integrated Change Control.

C.

Include the dependency in the project schedule.

D.

Ask IT to prioritize the needed system to meet the schedule.

Full Access
Question # 130

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

A.

Convene an impact analysis meeting.

B.

Escalate the issue to the product owner.

C.

Consult the communications management plan.

D.

Review the stakeholder register.

Full Access
Question # 131

A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?

A.

Ask another team member to redo the proof of concept using the current technology to ensure It is truly not an option.

B.

Use a root cause analysis (RCA) technique like Ishikawa diagrams to determine why the current technology is not supportive.

C.

Add this item to the issue log and explore possible resolution options with the team.

D.

Update the risk register indicating that a new technology must be chosen by the team lead.

Full Access
Question # 132

At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

A.

Defer all actions until the next workshop to keep the team focused on other higher priorities

B.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.

C.

Review the critical path and update the project schedule with the newly identified tasks.

D.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.

Full Access
Question # 133

A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

A.

Reassess the risk log to ensure it is up to date.

B.

Monitor quality metrics to ensure the project continues as planned.

C.

Perform lessons learned to ensure the issue does not happen again.

D.

Schedule a team meeting to review the issue,

Full Access
Question # 134

During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail

the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.

What should the project manager do next?

A.

Escalate the issue to the engineer's functional manager.

B.

Discuss the issue with the engineer and determine how to prevent another problem.

C.

Document the task on the kanban board and make it the highest priority.

D.

Assign another engineer to the task due to the urgency.

Full Access
Question # 135

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

Full Access
Question # 136

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Full Access
Question # 137

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

A.

Assume the role of the product owner while the product owner gets familiar with the product.

B.

Schedule time to share insights with the new product owner about the product and project information.

C.

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

Full Access
Question # 138

A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee,

* Actual progress = 2 units

* Planned progress = 3 units

* Actual cost (AC) = 2 units

* Budgeted cost = 3 units

What statement should the project manager make to the project steering committee?

A.

The project is currently behind schedule with a corresponding lower cost, and every effort is being made to expedite the delayed activities.

B.

The project is currently behind schedule with a corresponding cost savings, and no further actions should be taken.

C.

The project is currently behind schedule but at a lower cost, and an application for a time and budget extension will be submitted.

D.

The project is currently behind schedule but is under the planned expenditure, and the project manager is pleased to declare a project cost savings,

Full Access
Question # 139

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.

Full Access
Question # 140

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical

complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

A.

Tell the client about the chance for the potential delay.

B.

Work with the project team to evaluate the potential delay.

C.

Do not disclose the likelihood of a delay as it is yet to happen.

D.

Ask the project sponsor to inform the client in the next update.

Full Access
Question # 141

After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?

A.

Ask management to replace the new sponsor with the previous sponsor.

B.

Request the previous sponsor to discuss changes with the project team.

C.

Explore ways to share the project vision and outcome with the new sponsor.

D.

Find ways to bypass the new sponsor and reach management for support.

Full Access
Question # 142

A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.

What should the project manager do?

A.

Conduct a performance review and define and document the goals for the team member.

B.

Clarify decisions and request that the project team follows the project manager's decisions.

C.

Understand what the team member wants and find possible opportunities to address it.

D.

Remove existing ground rules and create new ground rules that support the project manager.

Full Access
Question # 143

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

Full Access
Question # 144

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

A.

Invite the stakeholders to the retrospective meetings.

B.

Invite the stakeholders to the sprint review meetings.

C.

Hold a meeting every 2 weeks with the stakeholders.

D.

Negotiate by sending an informative email to stakeholders.

Full Access
Question # 145

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

A.

Use the team's connections with international colleagues to get early warnings on future changes.

B.

Keep the focus on the priority items while the change goes through the change control process.

C.

Reject the change request since it may negatively impact the project's performance.

D.

Implement the change request as soon as possible to avoid accumulating new scope.

Full Access
Question # 146

A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a

previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help.

How should the project manager leverage this information?

A.

Ask the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.

B.

Recognize the stakeholders skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.

C.

Request the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.

D.

Send a request to the project sponsor to hire the stakeholder and have them become part of the project team.

Full Access
Question # 147

A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a

dependency missing between:

+ Test the product

+ Release to customer

According to the quality management plan, the product must be tested before being released.

How should the project manager enter this dependency?

A.

Finish to start

B.

Start to start

C.

Start to finish

Full Access
Question # 148

An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.

How should the project manager improve team dynamics?

A.

Require that all team members be physically present for the weekly project review.

B.

Offer the team member an incentive to stay until the end of the project.

C.

Replace the team member with someone who has similar qualifications and is located closer.

D.

Set up a weekly video conference to monitor the progress of the team member's work.

Full Access
Question # 149

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Full Access
Question # 150

A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The

engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to

complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete

items with associated regulatory components as they are essential items.

How should the project manager prioritize the work items?

A.

Complete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to complianceregulations.

B.

Ensure that the team assesses opportunities to deliver the highest business value items incrementally.

C.

Ensure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.

D.

Complete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.

Full Access
Question # 151

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.

A hybrid approach will allow the project manager to revise the product specifications.

D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Full Access
Question # 152

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

A.

The human resources (HR) department—to ask for more resources to add to the project team.

B.

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.

The stakeholders—to have them prioritize the requirements in the product backlog.

Full Access
Question # 153

A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going

well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference

to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.

Which two things should the project manager do to help the teams collaborate better? (Choose two)

A.

Schedule weekly progress meetings with all three teams and have them take turns as key players.

B.

Plan for team members to temporarily work at each other's locations to better provide a sense of community.

C.

Update the communications management plan and encourage the teams to review it promptly and proactively.

D.

Create a status reporting template and share it with all team members before the day ends.

E.

Schedule daily meetings with each team to understand their progress and concerns in detail.

Full Access
Question # 154

A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically

last 45 minutes with many misunderstandings due to language barriers.

How should the project manager resolve this issue for the next iteration?

A.

Transfer half of the backlog items to the next iteration to allow more time to complete the meetings.

B.

Extend the meeting to 1 hour and request that all of the participants bring up all of the issues.

C.

Instruct the meeting participants to speak only about blockers during the meeting.

D.

Train the three team leads to conduct a local meeting, then run an overall status meeting.

Full Access
Question # 155

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.

What should the project manager do?

A.

Escalate this issue to senior management, as the supplier is not following the procurement contract.

B.

Request a revision of the procurement contract to include specifications for the parts.

C.

Request a cancellation of the procurement contract with the supplier and impose a penalty.

D.

Review the procurement contract and ask the supplier to negotiate a solution.

Full Access
Question # 156

During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager

react to ensure the project remains successful?

A.

Focus the discussion on recovery and ways to get back on track.

B.

Act in a way to highlight the criticality of the situation.

C.

Punish the team member for providing negative data that will affect the team's morale.

D.

Thank the team member for raising this issue, log it, and move on to the next topic.

Full Access
Question # 157

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

A.

Validate if the project charter changed from the original one.

B.

Meet with these stakeholders to review the project charter.

C.

Check if these stakeholders attend regular project meetings.

D.

Review the project charter to validate this claim.

Full Access
Question # 158

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Full Access
Question # 159

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.

B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.

C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.

D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.

Full Access
Question # 160

A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project. During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.

How should the project manager establish the delivery model for this project?

A.

Organize the project into multiple subsets based on business functions and deliver each subset as a component of the final product.

B.

Reestablish the project as a program with multiple small projects, as each project will be delivered as a product of its own.

C.

Communicate the latest status to the steering committee and provide a demo of the features completed.

D.

Schedule routine demos on features completed and deliver a single product once all features are completed.

Full Access
Question # 161

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings,

the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.

How should the project manager ensure that project risks are reported accurately in the risk register?

A.

Review the risks throughout project execution.

B.

Plan to update the risks at project closure.

C.

Update the risks in the risk management plan.

D.

List the project risks identified in the kick-off meeting.

Full Access
Question # 162

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Full Access
Question # 163

A project team is executing a large regulatory project comprised of a multitude of internal and external stakeholders. An initial impact analysis revealed several systems, including an enhancement to existing modules as well as new builds. After completion of the initial design workshop, the team conducted a brainstorming session to better understand the types of likely users.

Which technique will best serve this purpose?

A.

Personas

B.

Power influence grid

C.

Power user grid

D.

Salience model

Full Access
Question # 164

A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to

water. What should the project manager do next?

A.

Hire local contractors who are familiar with the environment.

B.

Start project planning and develop the project management plan.

C.

Face the challenge immediately and start sending relief to the town.

D.

Process a change request for additional funding due to project urgency.

Full Access
Question # 165

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

A.

Retrieve the documentation that shows the resource allocation.

B.

Examine ways of modifying the scope of the project.

C.

Adopt a resource leveling procedure to level the resources.

D.

Perform an impact analysis to see the effect on the project.

Full Access
Question # 166

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.

B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.

C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.

D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems

Full Access
Question # 167

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

A.

Design an updated status report.

B.

Request a meeting with the stakeholder.

C.

Escalate this to the project sponsor.

D.

Forward the project status reports.

Full Access
Question # 168

When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a

result, the team ground rules favor these two team members.

What should the project manager have done to avoid this situation?

A.

Come to the meeting with suggested ground rules

B.

Ask all team members to send new ideas prior to the meeting

C.

Extend the meeting to allow everyone to speak

D.

Set expectations for contributions ahead of the meeting

Full Access
Question # 169

A project manager notices during project meetings that some team members repeatedly threaten to resign when they do not agree with something. Which phase of conflict escalation is the project in?

A.

Beginning

B.

Resolution

C.

Intensification

D.

Final

Full Access
Question # 170

A functional team member often becomes disruptive during status meetings and attempts to derail progress with the key stakeholders. This team member often discusses why the project will not be successful.

What should the project manager do?

A.

Investigate alternatives for team member needs.

B.

Evaluate the engagement needs for stakeholders.

C.

Identify the root cause of the team member's misunderstanding.

D.

Build trust and influence stakeholders.

Full Access
Question # 171

A project manager has been assigned to an important project that will help set the future of the company. Meanwhile, the project management office (PMO) is implementing

adaptive tools in a mostly predictive environment and has requested that the project manager follow this process as well. However, the functional manager has expressed concerns about the use of new tools on such an important project.

What should the project manager do?

A.

Review the adaptive tools' impact and obtain agreement from the functional manager.

B.

Follow the functional manager's recommendation to implement only predictive tools in the project.

C.

Make the decision on which project approach to use that would best fit the project.

D.

Follow the project management office's (PMOs) request to implement the adaptive tools in the project.

Full Access
Question # 172

A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.

What should the project manager do?

A.

Develop a plan for individual team members' growth and organize more team-building events.

B.

Recommend that the project director appoint project managers for each continent.

C.

Set up ground rules for team engagement, taking into consideration different cultures.

D.

Take differences in time zones into consideration when scheduling team meetings.

Full Access
Question # 173

A project manager has been assigned to an existing infrastructure project. The current project manager, who is retiring, and the project sponsor have had a good working relationship for many years. The project sponsor has expressed dissatisfaction with having a new project manager assigned to the project.

What should the project manager do?

A.

Set up a new communication plan and stakeholder engagement plan and submit to the project sponsor.

B.

Discuss the strategic benefits of the project and schedule communication with the project sponsor.

C.

Send weekly project reports to the project sponsor to provide an opportunity for engagement and feedback.

D.

Set up a detailed meeting with the project sponsor and brief them about the project's progress.

Full Access
Question # 174

A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.

What should the project manager do next?

A.

Review the key existing project documents with the new project sponsor.

B.

Ask the team to estimate the time it will take to update the documentation.

C.

Address the issue during the lessons learned session of the closing phase.

D.

Set up a meeting with the new project sponsor to understand their concerns.

Full Access
Question # 175

An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.

What should the project manager do first to resolve this dispute?

A.

Escalate to the project sponsor to provide a solution to the conflict.

B.

Interpret the source and stage of the conflict and select a resolution approach.

C.

Apply a compromising resolution approach, involving both groups.

D.

Ask the functional managers of both groups to help find a workable solution.

Full Access
Question # 176

A project manager notices that the project team is encountering product issues while coding client-specific developments. The project manager foresees delays to the project's timeline because of these product issues.

Which methods should the project manager use to communicate project delays and other difficult messages to stakeholders?

A.

Oral feedback, project meetings, and reporting

B.

Project meetings and reporting

C.

Project meetings and oral feedback

D.

Written feedback, project meetings, and reporting

Full Access
Question # 177

A team member is not getting along with one of the project sponsors. The sponsor has requested to move the team member to another project.

What should the project manager do next to resolve the situation?

A.

Meet with the team member and identify areas of improvement to satisfy the sponsor.

B.

Review the resolution of a similar past situation and apply the same strategy for the team.

C.

Identify the reasoning behind the behavior of the sponsor and team member.

D.

Hold a meeting with the team and explain the ground rules for the project.

Full Access
Question # 178

A project management office (PMO) is following the execution of an organization's critical project. Some of the project phases are experiencing serious delays due to an international supply chain crisis. Project team members suggested revisiting the planned project phases to maintain the project's value delivery.

What should the project manager do?

A.

Schedule a meeting with the project sponsor to report and discuss the issue.

B.

Update the project schedule in response to the external crisis.

C.

Develop a contingency plan and seek alternative suppliers.

D.

Assess and consolidate projects phases and update the project management plan.

Full Access
Question # 179

During a contract renewal meeting, an organization's commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?

A.

Reinforce the initial rules of the negotiations.

B.

Engage a facilitator to support the negotiations.

C.

Concentrate on meeting the customer's requests.

D.

Set clear expectations among the participants.

Full Access
Question # 180

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

A.

Execute the smaller estimated activities.

B.

Resize the story points.

C.

Negotiate the estimation so it gets smaller.

D.

Break down the larger activities into smaller ones.

Full Access
Question # 181

A project team is not motivated and is producing the bare minimum. The team has no interest in keeping pace with the aggressive project schedule.

What should the project manager do first to get the team energized and performing efficiently?

A.

Seek to understand the sentiments of each team member and then work with them to address their concerns.

B.

Bring the team together on a phone call to explain the criticality of the project and the impact of schedule delays.

C.

Contact the functional manager to request a replacement for team members who are not able to meet the schedule.

D.

Begin holding daily meetings and ask each team member to share their status and demand that they remain on schedule.

Full Access
Question # 182

A project manager of an infrastructure development project receives multiple issues from the customer validation team close to the product launch date.

What should the project manager do to manage such a situation for upcoming phases?

A.

Revise the project schedule to accommodate fixing discovered issues.

B.

Ensure customer validation occurs more frequently during the life cycle of the project.

C.

Review the customer validation team's test plan early in the life cycle.

D.

Ask the project team to increase unit testing of the deliverables.

Full Access
Question # 183

In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.

What should the project manager do first?

A.

Escalate the issue to the change control board (CCB).

B.

Ask the project team to analyze the impact.

C.

Register the risk and document the contingency plan.

D.

Have the project team brainstorm alternatives.

Full Access
Question # 184

During a requirements review session with a customer, a team member gets upset when questioned by the customer and responds angrily.

What should the project manager do next?

A.

Discuss with the whole team the root cause of this issue

B.

Meet with the team member to reset expectations

C.

Provide the team member with space to manage their emotions

D.

Follow up with the whole team to find the best approach

Full Access
Question # 185

A project manager was assigned to lead a global project with a virtual team that is globally dispersed. The project manager has difficulties communicating with the team members and there seems to be frequent misunderstandings and conflicts.

What should the project manager do?

A.

Ask the team members to refamiliarize themselves with the communications management plan.

B.

Organize effective communication training for team members.

C.

Listen to team members actively and change the communication practices accordingly.

D.

Model servant leadership by adapting to team requirements.

Full Access
Question # 186

A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.

How should the project manager handle the situation?

A.

Inform the team member that decisions were already made and feedback should have been provided in the past.

B.

Schedule a meeting to review the team member's concerns and revisit the decisions if required.

C.

Explain to the team member that it is mandatory that they increase their participation in project meetings.

D.

Add the team member's concerns to the risk register and discuss them during the next regular meeting.

Full Access
Question # 187

A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.

What should the project manager do first?

A.

Evaluate the schedule performance index (SPI) trend for slack to enable all five sprints while maintaining the cost performance index (CPI).

B.

Instruct the scrum master to suspend the current sprints and initiate the critical sprints immediately.

C.

Ask the scrum master to identify why sprints are in process for work that is not on the critical path.

D.

Contact the project sponsor to request adjustment to the completion date and to enable the current workflow.

Full Access
Question # 188

A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.

What should the project manager do to address the issue?

A.

Share a work performance report with the team member's supervisor.

B.

Assign a mentor to work with the senior team member.

C.

Speak with the senior team member to identify the difficulties.

D.

Collect feedback from all team members about team performance.

Full Access
Question # 189

A project team is using an iterative and incremental delivery approach. The sprint's duration is 1 month with a production release every 3 months. In the last sprint review, the users communicated that they want the functionality presented and deployed in 5 weeks. The project lead is working on the next release plan.

When should the project lead have their team deploy the functionality?

A.

In 1 month

B.

In 5 weeks

C.

In 12 weeks

D.

In 2 months

Full Access
Question # 190

A software delivery project is in the execution phase. The project team has identified a need for an additional server as the software requires more data storage space than planned for. Without the additional server, the project delivery cannot continue.

What should the project manager do?

A.

Use the project budget and procure a new server before raising a change request.

B.

Request that the requirement is funded with the business operational expenses.

C.

Apply contingency reserves to procure a server that fits the requirement.

D.

Raise a change request and obtain approval from the project owner.

Full Access
Question # 191

The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.

Which document should the project manager use to resolve this situation?

A.

Requirements traceability matrix

B.

Risk management plan

C.

Project scope statement

D.

Requirements management plan

Full Access
Question # 192

A project lead was asked to support the team by subdividing the project tasks as necessary to help define the minimum viable product (MVP).

Which two steps should the project lead take to define the MVP? (Choose 2)

A.

Hold a team meeting to generate a work breakdown structure (WBS).

B.

Create a responsible, accountable, consulted, informed (RACI) chart.

C.

Develop a project management plan, including subtasks, to meet the requirements.

D.

Conduct an information gathering session to determine the project value.

E.

Refer to the stakeholder register to determine who should be consulted.

Full Access
Question # 193

A project manager has been assigned to a new project. The project sponsor has requested a detailed timeline, but the project includes some deliverables that are not yet clearly defined.

Which project management approach should the project manager advise using?

A.

As the project includes elements that are not yet clearly defined, an agile approach is the best option.

B.

As the project sponsor has requested a detailed timeline up front, an agile approach is the best option.

C.

As the project appears to have both agile and predictive elements, a hybrid approach is the best option.

D.

As the project includes elements that are not yet clearly defined, a predictive approach is the best option.

Full Access
Question # 194

At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.

What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?

A.

Facilitate a conflict discussion and find a win-win situation for both parties so that they can continue to work together.

B.

Allocate additional key resources and document who will be held accountable for the various aspects of the team's workflow.

C.

Clarify the role ambiguity and define resource responsibilities with the team using a responsibility assignment matrix (RAM).

D.

Set up a group discussion after each requirement is discussed to understand the dependencies that can impact workflow.

Full Access
Question # 195

A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.

What should the project manager do?

A.

Hold separate retrospective meetings for both the vendor team and the internal team.

B.

Schedule a preliminary meeting with the account manager from the vendor and the test manager.

C.

Establish a clear agenda for the meeting and remind the vendor and internal teams that the scope is to improve the process.

D.

Invite the procurement manager and a representative from the vendor to manage the current tense relationship.

Full Access
Question # 196

A project team has obtained additional team members from different time zones. As a result, there are full-day delays in the work being completed because there are questions from team members from opposite time zones.

What should the project lead do?

A.

Meet each team member during their work hours to ensure all questions are answered in a timely manner.

B.

Inform all team members that they are required to check for messages every few hours to ensure fast response times.

C.

During daily check-ins, compile questions, coordinate with all team members, and agree to meet.

D.

Escalate to the project sponsor and request to replace certain team members so the time zones are aligned.

Full Access
Question # 197

A project manager has an engineering team mostly comprised of new hires. The project manager has to carefully predict in which stage of the project they will need to spend most of their time to ensure the team is properly integrated and performing well.

In which stage of the project would the project manager need a greater effort to lead them?

A.

Performing

B.

Storming

C.

Norming

D.

Forming

Full Access
Question # 198

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?

A.

Contact the human resources (HR) department to find new resources to replace this critical resource.

B.

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.

C.

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.

D.

Discuss the resource management plan with the project team for effective utilization of critical resources.

Full Access
Question # 199

A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.

What should the project manager do first?

A.

Gather additional information and ask the team to perform a root cause analysis.

B.

Update the master schedule to reflect the reprioritized deliverables.

C.

Ask the team to work with the product owner to reprioritize the backlog.

D.

Request additional information and discuss the feasibility options and impacts with the team.

Full Access
Question # 200

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?

A.

Relocate the project to another country that is not shutting down.

B.

Evaluate the possibility of having another country complete the task.

C.

Identify additional team members who are able to complete the task.

D.

Determine if the project has built-in slack to remain on schedule.

Full Access
Question # 201

A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.

What should the project lead advise?

A.

During the sprint review, ensure that the completed items deliver business benefits.

B.

Present in detail the business benefits delivered in the sprint during the sprint retrospective.

C.

During the daily standup, ensure that each item meets the definition of done (DoD) before accepting it.

D.

Review in detail the criteria for the definition of done (DoD) for each item during the sprint planning.

Full Access
Question # 202

A project manager is in the middle of executing the construction of a high-rise plaza when the government regulatory agency announces an increase in the price of fuel. The project still has seven months left on the schedule.

What should the project manager do first?

A.

Meet with the vendors to evaluate the impact on the budget.

B.

Implement crashing to mitigate the impact on the budget.

C.

Review the organizational process assets (OPAs) as a reference.

D.

Request the release of management reserve for the project.

Full Access
Question # 203

A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.

What should the project manager do to ensure effective communication?

A.

Plan to implement a united communication platform, where all information about the project will be shared and updated regularly.

B.

Ensure all the information about the project implementation is provided to all of the different stakeholders in a unified communication format.

C.

Define communication target groups and provide information, messages, channels, and the frequency of communication for each group.

D.

Arrange an information session for all of the stakeholders about the plans for handling their various communication needs.

Full Access
Question # 204

A project manager works for an IT consulting firm that has submitted a bid during the request for proposal (RFP) process for a contract that focuses on data center migration and optimization. However, the consulting firm has little experience in data center optimization.

What should the project manager do?

A.

Send the team to a data center optimization training workshop.

B.

Partner with a company that is an expert in this area.

C.

Outsource the data center optimization work to a vendor.

D.

Request a budget to build this competency among project team members.

Full Access
Question # 205

The project manager is planning a project with several legal aspects for the city's municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city's court.

What three actions should the project manager do? (Choose 3)

A.

Leverage the project governance system to track and manage the project artifacts.

B.

Create a central repository system to assess the effectiveness of the project artifacts.

C.

Review the execution roadmap and ask the legal team to manage the artifacts.

D.

Ensure the project artifacts are kept up to date and accessible to all stakeholders.

E.

Work with the team to determine the process to manage the project artifacts.

Full Access
Question # 206

A project leader is preparing to facilitate a sprint retrospective. The sales manager sends the project leader an email asking how a feature planned for the next shipment is being implemented.

What should the project leader do next?

A.

Organize a meeting between the product owner and the sales manager.

B.

Invite the sales manager to the next sprint review.

C.

Organize a demo for the sales manager with the development team.

D.

Invite the sales manager to the sprint retrospective.

Full Access
Question # 207

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)

A.

Develop the project management plan based on the requirements requested by the customer.

B.

Develop the application as requested by the customer, based on the approved project requirements.

C.

Plan a minimum viable product (MVP) to get early feedback from the customer.

D.

Facilitate a focus group to assess the functionality before development.

E.

Use an agile approach to deliver the product based on sprints.

Full Access
Question # 208

A project manager has taken over a project and realizes a number of the suppliers responsible for the delivery have not done an implementation as complex and large as this project. The project manager reviews the risk log and logs this as a risk. Three months later, two suppliers have missed key milestone dates and delivered substandard work.

What should the project manager do?

A.

Support the suppliers by providing them with additional resources.

B.

Execute the risk response plan and update the issue log.

C.

Ask suppliers to submit a revised plan and schedule.

D.

Execute the risk response plan and update the action register.

Full Access
Question # 209

A company has decided to create a new product to prepare itself for the changing economy. The technology required for the new product is not well understood yet, and the requirements are still being debated.

Which approach should the project manager advise for this project?

A.

Lean

B.

Predictive

C.

Agile

D.

Hybrid

Full Access
Question # 210

A key stakeholder of a project wants to include additional work before completion.

What should the project manager do?

A.

Request the additional work through governance.

B.

Meet with the stakeholder and explain that additional work cannot be added.

C.

Prioritize the additional work in the backlog.

D.

Collaborate immediately with the stakeholder to complete the additional work.

Full Access
Question # 211

The project sponsor wants to obtain quick feedback from end users for a product under development. The roadmap is extensive and will not be completed for quite some time.

What should the project manager do?

A.

Advise the stakeholders that they will need to wait until development is completed in order to get actual end-user feedback.

B.

Hire additional resources to accelerate the schedule and deliver the product faster in order to get actual end-user feedback.

C.

Advise the stakeholders to share images of the finished product in order to obtain valuable feedback from end users.

D.

Work with the stakeholders to determine the minimum requirements needed to get valuable end-user feedback and revise the project schedule.

Full Access
Question # 212

A railroad construction project is in the planning stage. During a monthly progress meeting, an external project manager from the sponsoring organization mentioned there is a potential delay in the design completion date. The external project manager wants to know the impact of this delay on the overall project completion date in the next monthly meeting.

Which three actions should the internal project manager take next? (Choose 3)

A.

Perform variance analysis.

B.

Validate the critical path method (CPM).

C.

Establish what-if scenario analysis.

D.

Determine the schedule performance index (SPI).

E.

Execute a Monte Carlo simulation.

Full Access
Question # 213

The project lead is very concerned about the quality of a specific design feature and how the product will perform. What should the project lead focus on to ensure project success and customer satisfaction?

A.

Confirm that the deliverable will meet the defined acceptance criteria.

B.

Update acceptance criteria while the deliverable is being developed.

C.

Ask stakeholders to test against the defined acceptance criteria.

D.

Plan extra tests if acceptance criteria are not met.

Full Access
Question # 214

A project feature from the development team was rejected due to low quality. Over the past few weeks, the testing team has become concerned because the development team has not yet responded to the rejection. As a result, the testing team has escalated the conflict to the project manager.

What should the project manager do?

A.

Remove the development team's rejected feature from the backlog.

B.

Reassure all team members that the development team will fix the issue.

C.

Initiate an improvement plan for the development team to follow.

D.

Evaluate the context for the conflict with the development team.

Full Access
Question # 215

A project team has experienced deliverable delays in the last few iterations. During the retrospective, the team realizes that the quality issues identified are because the quality process is outdated.

Who should the project manager ask to update the process?

A.

Project team

B.

Project management office (PMO)

C.

Quality lead

D.

Product owner

Full Access
Question # 216

After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?

A.

Log the issue and see if improvements show in the second iteration.

B.

Log the issue and ask a senior member to coach these team members.

C.

Hire new team members to implement the correct way of testing.

D.

Check lessons learned and use the testing process from previous projects.

Full Access
Question # 217

An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.

What should the project manager do next?

A.

Have the kick-off meeting as scheduled and capture any new requirements raised in the meeting.

B.

Have a one-on-one interview with the new senior manager before the kick-off meeting.

C.

Ask the new senior manager to send any new requirements before the kick-off meeting.

D.

Ask the project sponsor to hold the kick-off meeting after the new senior manager has onboarded.

Full Access
Question # 218

During a risk review meeting early in a project, the project team flags the possibility that a key team member might be away during the implementation of a key work package. Unfortunately, this team member is currently the only resource with the knowledge to perform this work, although it is possible someone else could do it with training.

What should the project manager do?

A.

Establish a long-term training program for the junior team members.

B.

Reassign the tasks among team members to allow them to split the workload.

C.

Ask team members to document knowledge assets for all the tasks.

D.

Ensure team members collaborate throughout the project to share knowledge.

Full Access
Question # 219

In an organizational upper-level management meeting, the CEO shows interest in a project of which they were not previously aware. After the meeting, what should the project manager do to ensure the CEO's support?

A.

Update the stakeholder engagement plan to include the CEO.

B.

Meet with the CEO to review the current deliverables for the project.

C.

Identify the CEO's preferred method of communication.

D.

Send the updated project management plan and documents to the CEO.

Full Access
Question # 220

A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.

What should the project manager do?

A.

Assign the issue to a senior developer and schedule training for the junior developer after the due date.

B.

Assign the rework to the junior developer after consultation with the senior developer.

C.

Reassign the issue to the senior developer and assign the junior developer to assist in fixing the issue.

D.

Reassign the issue to the senior developer after explaining the situation to the junior developer.

Full Access
Question # 221

A company is transitioning from using a predictive approach to using an agile framework on a project. The project sponsor is concerned about the level of uncertainty and how to determine the time and budget required to complete the scope.

What should the project manager do to address this situation?

A.

Communicate to the key stakeholders that the project baseline could not be estimated due to the new framework being used.

B.

Ask the project team to create a high-level budget baseline for the project and provide more detail only for the first project stages.

C.

Review organizational process assets (OPAs) for similar projects to determine the schedule, costs, and resources required to execute them.

D.

Refine the amount of work required for the project with the project team and perform a detailed project baseline accordingly.

Full Access
Question # 222

A project lead is managing an agile project. The project activities, which have been placed in a backlog, still need to be refined and prioritized.

What should the project lead use for backlog refinement considering the sprints are 2 weeks long?

A.

Sixty minutes every sprint going through stories with higher story points.

B.

Ninety minutes every three sprints going through stories that are higher priority.

C.

Sixty minutes every sprint going through stories that are higher priority.

D.

Ninety minutes every three sprints going through stories with higher story points.

Full Access
Question # 223

A virtual product development team is working well together and is on schedule. One team member wants to take 1 week off to attend a training.

What should the project manager do?

A.

Decline the team member's request as it might jeopardize the schedule.

B.

Approve the team member's request as it will increase motivation.

C.

Decline the team member's request since the goal is not individual team member advancement.

D.

Approve the team member's request on condition they work additional hours when they return from training.

Full Access
Question # 224

A project manager is planning the fifth sprint of a project when the sponsor requests a report on the business value gained to date. What should the project manager show to the sponsor?

A.

The cumulative flow diagram

B.

The data of the metrics defined to track benefits

C.

The metrics plan to track benefits

D.

The fifth sprint retrospective report

Full Access
Question # 225

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor's concerns?

A.

Document the team member's mistake in the lessons learned.

B.

Train the team member to improve their performance to avoid future mistakes.

C.

Talk with the team member to identify the reason for the mistake.

D.

Relocate the team member to another project due to the mistake.

Full Access
Question # 226

A product owner has indicated there is strong customer interest in adding a new set of functionalities to a product. Using agile approaches, the project manager evaluates the new functionalities of the product.

What should the project manager do?

A.

Negotiate with the product owner to determine which functionality should be pushed out of the scope of the project.

B.

Discuss with the team how this change in scope impacts development at the next retrospective to determine next steps.

C.

Negotiate with the product owner to determine what might be removed from the backlog that is of similar size.

D.

Add the functionality to the product backlog for inclusion once a change request is created and approved.

Full Access
Question # 227

A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?

A.

Ask the least experienced team members to work as assistants to the more experienced team members so they can gain some project experience.

B.

Ask the project sponsor to replace the least experienced team members with more experienced ones.

C.

Identify how the team members with no experience can contribute according to their capabilities and provide training if needed.

D.

Assign critical project tasks to the most experienced team members as they are the only ones with the knowledge.

Full Access
Question # 228

A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.

A.

Find a way to accommodate the requested additions.

B.

Schedule a meeting to gain better understanding.

C.

Politely refuse the request stating the project baselines.

D.

Initiate a change request for the additional scope.

Full Access
Question # 229

A project manager is planning a project to build a research center with the installation of scientific equipment. Since the research topic is new and unfamiliar, the equipment required might change during project execution.

How should the project manager plan this project?

A.

Use a different project life cycle approach for the different parts of this project by adopting a hybrid approach.

B.

Separate the tender into two parts, one for the building and one for the equipment, with careful selection of contractors.

C.

Lock down the requirements for the equipment early and avoid any changes during further phases of the project.

D.

Put a fixed price contract out to tender for the research building and issue a cost-reimbursable contract for installing the equipment.

Full Access
Question # 230

A project manager has just been designated to lead an approved project with a virtual team. The team members are from several countries and have never met before.

In order to promote team engagement and introduce the project team, what should the project manager do?

A.

Share a presentation with information about each project team member.

B.

Share all members' resumes and photographs in a sharing digital platform.

C.

Schedule multiple one-on-one meetings between team members.

D.

Schedule a kickoff meeting to present the whole project team.

Full Access
Question # 231

A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.

What should the project manager do to address this concern?

A.

Recommend the functional lead meet with the project team members to convince them to accept the change.

B.

Document the additional step from the functional lead and adjust the timelines to accommodate the change.

C.

Ask the functional lead to remove this additional step as it is not vital to the project.

D.

Advise the team that the functional lead's preference should be taken into consideration.

Full Access
Question # 232

While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.

What should the scrum master do?

A.

Determine the average of the two estimates and assign that amount.

B.

Ask the product owner to rewrite the story so the final estimate can be agreed upon.

C.

Consult the lessons learned for insight into the correct estimate.

D.

Select the junior member's estimate since they will most likely be doing the work.

Full Access
Question # 233

A multinational company is embarking on an ambitious organizational change project. The objectives of the project include the complete transformation of the organization's structure, role catalog, and global locations in which supporting services are to be delivered.

What should the project manager advise as an essential component of the project?

A.

A communications management plan and a change management plan to convey the need for change and support the organization.

B.

A panel of subject matter experts (SMEs) that can be consulted for their opinions on how to implement the change project.

C.

A project risk management plan to evaluate and mitigate the risks of change on the performing organization.

D.

A project stakeholder map to assist in understanding which senior executives need to be consulted on the communications management plan.

Full Access
Question # 234

A project manager is asked to manage an agile project, allowing the company to comply with a new upcoming regulation. After the project kickoff, the scope is modified to have the project team work on specific tasks, while a global team will manage the program for several countries in parallel. The project management plan has not yet been shared, and the deadline to complete the project is fixed.

What should the project manager do to handle the scope change?

A.

Define an initial backlog and start working on the clearest tasks, then incrementally refine the scope.

B.

Create a risk entry in the risk management plan due to the lack of a global project management plan.

C.

Review the organizational process assets (OPAs) from past projects with similar scope changes.

D.

Formalize the change in the scope with the project sponsor to limit accountability for the specific tasks.

Full Access
Question # 235

A project team used agile approaches to create a minimum viable product (MVP). Currently, the team is discussing the possible next steps.

What should be the next step?

A.

Break down the user stories into the smallest size possible.

B.

Ensure user stories provide the steps necessary for implementation.

C.

Prioritize the work at the user-story level.

D.

Use scope cards in conjunction with story points.

Full Access
Question # 236

A project manager was notified about a new regulatory requirement that could impact the project schedule.

What should the project manager do first?

A.

Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.

B.

Update the schedule and project risk register according to the regulatory requirement.

C.

Consult the project management plan for guidance on addressing the regulatory requirement.

D.

Assess the impact of implementing the potential regulatory requirement on the project.

Full Access
Question # 237

The sponsor calls the project manager and questions why the stakeholders have not received updates for over 1 month. The project recently implemented a project management information system (PMIS) that provides real-time access to various project status measurements and information. The project manager is certain that all stakeholders have the opportunity and permissions for status updates.

How should the project manager proceed?

A.

Call and apologize to the team members and provide an update on how this issue was caused.

B.

Review the communications management plan and stakeholder engagement plan for the project.

C.

Request the operations support team to troubleshoot and determine the root cause of the issue.

D.

Obtain a list of the affected stakeholders and email the current status information to them.

Full Access
Question # 238

Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?

A.

Verify the total float of each activity of the consolidated project schedule.

B.

Verify the critical path of the consolidated project schedule.

C.

Verify successors and predecessors of each activity of the consolidated project schedule.

D.

Verify the free float of each activity of the consolidated project schedule.

Full Access
Question # 239

A project is starting with a team that is located all over the world. None of the team members have worked together before. The project goal is ambitious with an aggressive timeline.

What should the project manager do?

A.

Ask for financial support to set up a physical meeting for the team.

B.

Create a virtual room for the team to facilitate their collaboration.

C.

Schedule quarterly in-person meetings to enhance the team's relationships.

D.

Facilitate a virtual session with the team to start planning as soon as possible.

Full Access
Question # 240

A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.

What should the project manager do?

A.

Escalate the issue to the board with opportunities to recover the delay as soon as possible.

B.

Work with the product owner and the Scrum team to add 2 weeks to the release schedule.

C.

Work with the product owner and the Scrum team to recover the delay before the last release.

D.

Escalate the issue to the board and plan for the engagement to be terminated.

Full Access
Question # 241

Due to an anticipated expansion, a company procured new technology. The project team responsible for using this technology does not have experience with it.

What should the project manager do?

A.

Assess the benefit of using new technology versus old technology.

B.

Hire project resources with experience using the new technology.

C.

Propose training for the project team in batches on the new technology.

D.

Request incentives for the team to use the new technology.

Full Access
Question # 242

During a daily meeting of a challenging project, two team members started to argue on the preferred solution based on their assumptions. The situation prevented the progress to the next phase of development, which could impact the finish date of the project.

What should the project manager do next?

A.

Divide the team into small groups to avoid future arguments and delays.

B.

Ask the human resources (HR) department to replace the team members.

C.

Make a decision based upon the project manager's knowledge and expertise.

D.

Meet with the team members to discuss the priority of the project schedule.

Full Access
Question # 243

An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?

A.

Incentivize the team with prizes for increased performance and engagement in order to persuade the team member to resume previous performance.

B.

Ask the direct manager to reach out and try to identify the problem, then provide that information back to the project manager.

C.

Inform the team member that a change in performance and engagement is noticed and work together to develop a solution for improvement.

D.

Meet with human resources (HR) to determine the problem and develop a recommendation based on the results.

Full Access
Question # 244

A project manager is leading a team and wants each team member to produce their deliverables and be held accountable for the work product. What should the project manager do first?

A.

Engage with each project team member to explain the individual consequences of late delivery.

B.

Establish a daily standup meeting where each project team member reports their progress.

C.

Create a plan of action and milestones (POAM) to detail the deliverables for each project team member.

D.

Empower each project team member with ownership of a particular aspect of the project.

Full Access
Question # 245

A sales director is upset that progress has been slow on the delivery of critical features to the customer. After consulting with the team, the project manager learns that a subject matter expert (SME) on the customer side is not cooperative in providing the input needed to complete the definition of ready (DoR).

What should the project manager do to avoid the same problem in future projects?

A.

Review the responsibility matrix at the customer kick-off meeting.

B.

Rely on internal SMEs for expert input on implementing the user stories.

C.

Include a contractual penalty for delays created by the customer.

D.

Require customer SMEs to attend at least half of the daily meetings.

Full Access
Question # 246

A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.

What should the project manager do to have a high-performing team?

A.

Set up regular project status meetings and invite all team members.

B.

Encourage the team to define the ground rules for performance.

C.

Set up individual calls to follow up on each team member's progress.

D.

Invite team members to an informal meeting to get to know one another.

Full Access
Question # 247

A new offshore call center project is vital for a company's branch offices. The project is at the end of the planning phase when the project manager is informed by the sponsor that the project will be delayed due to reprioritization.

What should the project manager do?

A.

Create a messaging group chat with the branch office stakeholders to inform them about the project delay.

B.

Schedule a video conference to inform the branch office stakeholders about the project delay.

C.

Send an official project memo to inform the branch office stakeholders about the project delay.

D.

Include the project delay in the monthly progress report for the branch office stakeholders.

Full Access
Question # 248

A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.

What should the project manager do in this situation?

A.

Review the risk register for this unforeseen circumstance.

B.

Utilize virtual teams for meetings and deliverables.

C.

Use the contingency reserve and subcontract the work.

D.

Ask for an extension of time on the project deliverables.

Full Access
Question # 249

A government approved the construction of a river dam to enable year-round farming in a community. At the project kickoff meeting, a key stakeholder in the community disagrees with the location of the dam.

What should the project manager do first?

A.

Review the stakeholder engagement plan to confirm that all key stakeholders were consulted.

B.

Explain to the key stakeholder that final approval has already been obtained.

C.

Meet with the key stakeholder to review the stakeholder engagement plan.

D.

Schedule a meeting with all stakeholders to discuss the view of this key stakeholder.

Full Access
Question # 250

Two experienced team members in a hybrid project are having a conflict about a technical solution. The project manager has already spoken individually to the two team members without successfully resolving the conflict.

What should the project manager do next?

A.

Discuss the topic with the team members in a team meeting.

B.

Replace the two team members with other resources.

C.

Contact the functional managers of each team member.

D.

Schedule a meeting with both team members.

Full Access
Question # 251

A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.

What should the project manager do?

A.

Recommend that the team use industry-accepted guidelines.

B.

Contact the chief information officer (CIO) and request the enterprise development guidelines.

C.

Contact the previous team and ask for a copy of their guidelines.

D.

Recommend that the team develop their own guidelines.

Full Access
Question # 252

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?

A.

Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.

B.

Ensure that the project change log is up-to-date with the stories based on the missed requirements.

C.

Ensure that the project backlog has the features and stories prioritized correctly.

D.

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.

Full Access
Question # 253

A new project manager took over a project that has been ongoing for a while. Some project team members are not clear on when the project will end and feel the project has already transitioned into business as usual.

What should the new project manager do first?

A.

Meet with the team and gather their input on the completion rate.

B.

Revisit the timelines of the deliverables and the project.

C.

Consult the sponsor and secure approval to complete the project.

D.

Transition to an agile delivery so project closure will be faster.

Full Access
Question # 254

A project schedule's risk level continues to increase during project execution because sprints are consistently delivering less than the intended results. The project manager becomes concerned that the deliverable will be delayed and cost more than the project sponsor intended.

What should the project manager do first?

A.

Engage with the project team to understand the schedule risk problem and present a solution to the project sponsor.

B.

Conduct a risk review meeting to gain a better understanding of the schedule, then document the results.

C.

Schedule a meeting with the scrum master to explain that adding additional sprints is necessary to reduce risks.

D.

Notify the project sponsor of the schedule risk and request support to increase the project budget.

Full Access
Question # 255

The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?

A.

Assign a project team member to document exchanged communication for future reference.

B.

Assign the project sponsor as the point of contact for all provider communication.

C.

Ensure that all project stakeholders participate in the scope definition meetings.

D.

Establish a common language of terms with which to communicate with the provider.

Full Access
Question # 256

A project manager is working on a global project and realizes that one team member is not performing as expected. The project manager meets with the team member to find out what is causing this low performance. The project manager discovers the team member is experiencing conflict and feels uncomfortable with the team. The team member then asks to be moved to another project.

What should the project manager do?

A.

Request human resources (HR) to help.

B.

Move the team member to another project.

C.

Confront the issue with the rest of the team directly.

D.

Ask other team members to be more welcoming.

Full Access
Question # 257

A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.

What duration should the project manager use?

A.

11 days

B.

12.5 days

C.

12 days

D.

11.5 days

Full Access
Question # 258

A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.

What should the project manager do first?

A.

Formalize the product owner assignment.

B.

Review similar projects in the company.

C.

Set the project's purpose, mission, and vision.

D.

Carry out the product backlog creation.

Full Access
Question # 259

A project manager has noticed that the performance of a new team member has increased dramatically over the past few months The project manager has been measuring this team member's performance through the cost performance index (CPl) and schedule performance index (SPl) of work packages. The project manager has also assigned new. unrelated work packages to this team member The project manager wants to formally record the team member's success in the project documentation

What should the project manager do?

A.

Attach a note to the project management plan about the team member

B.

Hold a project team meeting about the team member's contribution and take minutes

C.

Record the team member's contribution in the responsibility assignment matrix (RAM)

D.

Send a communication to management recognizing the team member's contributions

Full Access
Question # 260

A project is ending and the final deliverables have been accepted by the customer. The project team is pleased that the project was a success: however, some groups within the customer's organization believe the objective of the project was not met.

What should the project manager have done to avoid this issue?

A.

Distributed a detailed quality management plan to the key stakeholders.

B.

Included the final report during the closing phase to ensure common understanding.

C.

Identified key stakeholders and included all of them in project agreement discussions.

D.

Performed project reporting according to the communications management plan.

Full Access
Question # 261

A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?

A.

Project stakeholders and the team

B.

External subject matter experts (SMEs) and the team

C.

Project sponsor and the team

D.

Project sponsor and the external SMEs

Full Access
Question # 262

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Full Access
Question # 263

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Full Access
Question # 264

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

    Approved Work Package Cost Estimates: US$9,500

    Contingency reserves: $500 %

    Management reserves: 10% of contingency reserves

    Percent complete of the project: 50%

    Planned percent of the project: 40%

    Actual costs of the project: US$4,500

What is accurate about the project status?

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

Full Access
Question # 265

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.

Which release strategy should the project manager recommend?

A.

A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity

B.

An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country

C.

A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues

D.

A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time

Full Access
Question # 266

A project manager works for a large software development company that has multiple strategic business groups. The project manager has been assigned to develop maintenance planning software for a power plant. The project manager heard that a similar project that was executed by another business group in the company recently failed. The project manager is concerned about the project's performance and wants to take steps to help the project succeed. What should the project manager do?

A.

Evaluate the project risk and try to replace the project with another one within the organization.

B.

Inform the project sponsor about the risk and try to convince them to withdraw the project.

C.

Study and apply the lessons learned from the failed project so that this project does not follow the same pattern.

D.

Continue executing the project using the project manager's usual methods as all projects are unique.

Full Access
Question # 267

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Full Access
Question # 268

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design

Full Access
Question # 269

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish anindependent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of differentcultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Full Access
Question # 270

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Full Access
Question # 271

A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders

What document should the project manager use to communicate these requests?

A.

Risk log

B.

Change log

C.

Backlog

D.

Issue log

Full Access
Question # 272

In the past, the project manager and the project team performed well using

predictive methodology. However, the organization recently decided to adopt agile

approaches, and the project sponsor wants to use an agile approach in an upcoming project.

Before initiating the project, what should the project manager do?

A.

Prepare a risk report that captures the probability and impact of risks, and then shareit with the project sponsor.

B.

Share the organization's decision with the team and make plans to adopt an agileapproach in the upcoming project.

C.

Make a request to human resources for new team members who have agileexperience.

D.

Ask the project sponsor to change the approach back to predictive as that is theteam’s strength.

Full Access
Question # 273

The project manager of a hybrid project learns that a stakeholder has approached a team member directly to request a change This change will impact the project m a significant way The project manager should ten the stakeholder that the correct procedure tor new requirements is to provide a request directly to whom?

A.

Product owner

B.

Change control board (CCB)

C.

Project sponsor

D.

Project manager

Full Access
Question # 274

A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.

What should the project manager do?

A.

Seek help from the project sponsor to get an SME from another team in the organization.

B.

Provide an opportunity to one of the existing team members to become an SME.

C.

Hire a contractor from outside of the organization to continue with the project.

D.

Ask team members to document the issue and address it in the next project meeting.

Full Access
Question # 275

A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.

What should the project manager do?

A.

Inform the stakeholder that the new requirement will be considered in the next release planning session.

B.

Inform the sponsor of the latest changes and ask the sponsor to prioritize the features.

C.

Ask the product owner to determine if this requirement needs to be treated as a top priority.

D.

Direct the development team to work on this requirement right away.

Full Access
Question # 276

A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?

A.

Assign the feature to another team member, and have them try to complete the feature by the end of this iteration

B.

Review team capacity and reassign the functionality to additional iterations as required

C.

Determine if the team member can work from home to complete the functionality.

D.

Review the work in progress with the product owner to determine the next step

Full Access
Question # 277

A project manager has taken over an existing project According to the previous project manager, the project is on track and within budget However, stakeholders are unhappy with the recent progress report since the metrics show that the project is delayed and the cost is higher than expected.

What should the project manager do?

A.

Schedule a meeting with the previous project manager

B.

Submit a change request to the change control board (CCB)

C.

Schedule training for project team members

D.

Conduct an earned value analysis (EVA)

Full Access
Question # 278

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?

A.

Check with the team to learn what can be done, and consult an expert

B.

Ask the sponsor to close the project and pay the contracted penalty.

C.

Check that this information was documented correctly

D.

Meet with the sponsor to ask for their support

Full Access
Question # 279

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

A.

Reducing cost for the customer

B.

Delivering value to the customer

C.

Working together as a team

D.

Finishing the project on schedule

Full Access
Question # 280

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Full Access
Question # 281

A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?

A.

Determine a leadership style that is suitable for that location.

B.

Check if resources from headquarters can also be assigned to the project.

C.

Mentor the team members to perform project management.

D.

Assign a local resource to manage communication with the team.

Full Access
Question # 282

A project manager has joined a company m an unfamiliar industry and has been given a strategically important project Being new, and not fully understanding the interdependences of the various departmental work items, the project manager is unsure of how to plan the project

How should the project manager proceed?

A.

Consult the project sponsor and request their feedback

B.

Consult the product owner and request a complete prioritization session

C.

Consult a senior project manager within the organization and request their expert judgement

D.

Consult a senior developer within the organization and request their input.

Full Access
Question # 283

A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.

What should the project manager have done to avoid this situation?

A.

Initiated requirements planning to analyze, document, and manage requirements

B.

Applied requirements elicitation to involve engaging stakeholders consistently in the requirements process

C.

Implemented the change request process to harness change to the stakeholders’ advantage

D.

Used progressive elaboration to enhance the scope management plan with additional details

Full Access
Question # 284

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

Full Access
Question # 285

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

Full Access
Question # 286

A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?

A.

Include key risks in the cost baseline.

B.

Perform an analogous estimate.

C.

Perform a bottom-up estimate.

D.

Include projected inflation rates.

Full Access
Question # 287

A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.

What should the project manager use to document the project deliverables?

A.

Service level agreement (SLA)

B.

Statement of work (SOW)

C.

Scope management plan

D.

Memorandum of understanding (MOU)

Full Access
Question # 288

A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.

Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder

What should the project manager do to resolve the team member's concerns?

A.

Use the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.

B.

Use a problem-solving approach and set up a discussion with the team lead and team member.

C.

Establish guidelines for team leads to ensure that all team members are appropriately treated.

D.

Provide direction to the team lead on how to resolve the issue with the team member directly.

Full Access
Question # 289

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Full Access
Question # 290

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

A.

Review the project plan to evaluate if any updates should be made.

B.

Crash the existing schedule with additional resources to deliver more features.

C.

Stop the project immediately as the market opportunity has already been missed.

D.

Continue with the project plan and target delivery date as expected.

Full Access
Question # 291

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Full Access
Question # 292

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Full Access
Question # 293

A project is behind schedule and over budget, resulting in a problem for the next deliverable. The project manager informs the stakeholders, who are very concerned about the project. What should the project manager do to alleviate the stakeholders' concerns?

A.

Send communications for clarification so there is a full understanding about the situation.

B.

Demonstrate the performance indexes and recommend corrective actions to the stakeholders

C.

Schedule a kick-off session to explain the problems of the project and gain approval and support

D.

Speak with the sponsor and explain the situation so that the sponsor can explain it to the stakeholders

Full Access
Question # 294

A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.

What should the project manager do?

A.

Apply fast-tracking techniques to compress the schedule of the critical project

B.

Analyze both projects to determine the most effective use of common resources

C.

Use resource optimization to justify requesting more resources for the critical project.

D.

Provide schedule optimization training to the project teams to improve their skills.

Full Access
Question # 295

During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.

How should the PMO implement a better way to report the project's health?

A.

Perform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.

B.

Explore reporting the earned value (EV) key performance indicators (KPls) using agile progress as an input.

C.

Ask the project managers to report on their projects using a Kanban board format.

D.

Request the program managers to be more accurate when presenting status reports.

Full Access
Question # 296

A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.

What are the first two actions the project manager should perform? (Choose two)

A.

Create a change request to discuss with the change control board (CCB).

B.

Request additional budget for contingency.

C.

Perform a risk identification process with the project team.

D.

Consult with the project stakeholders.

E.

Discuss the possible impacts with subject matter experts (SMEs).

Full Access
Question # 297

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?

A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments

B.

Incremental delivery and frequent backlog refinement based on user feedback

C.

Iterative development and collection of frequent feedback from project team members

D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented

Full Access
Question # 298

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

Full Access
Question # 299

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Full Access
Question # 300

An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?

A.

Ask for additional team members to maintain the velocity

B.

Implement a checkpoint in the iteration to verify if the team is on track

C.

Conduct a focused retrospective to help the team to discover the root cause

D.

Ask the team to have a lower commitment for the next iteration

Full Access
Question # 301

During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?

A.

Refine and estimate the enhancement so the size is known.

B.

Add it to the product backlog to be completed in the future.

C.

Start working on the enhancement for the customer immediately.

D.

Ask the product owner to prioritize the item with the customer.

Full Access
Question # 302

A project manager for a building construction project is planning to go on vacation

midway through the project execution phase. What should the project manager do first to

ensure the team is empowered and deadlines are met?

A.

Allow the team to make decisions to stay on schedule.

B.

Postpone the vacation to a different time.

C.

Ask the project sponsor to make any necessary decisions.

D.

Analyze the impacts and create a plan for team decision making

Full Access
Question # 303

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Full Access
Question # 304

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

Full Access
Question # 305

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Full Access
Question # 306

A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?

A.

Ask subject matter experts (SMEs) to provide a detailed plan for each phase.

B.

Commit to a detailed global plan from the initiation phase.

C.

Get agreement from stakeholders on high-level deliverables and requirements.

D.

Request the project management office (PMO) to review the initial plan

Full Access
Question # 307

After a project team has been working on a project for several months the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project

How should the project manager handle this situation?

A.

Comply with the project sponsor's request to not archive the project artifacts.

B.

Consult with the project management office (PMO) for guidance on project artifacts.

C.

Archive the project artifacts on the project manager's local computer for future reference.

D.

Document the project sponsor's instructions as the archived project artifacts.

Full Access
Question # 308

An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.

What should the project manager do?

A.

Ask the sponsor to approve inclusion of an additional iteration to the project

B.

Ask the team to include the contingency plan in the iteration backlog

C.

Help the team review the project approach to initiate the corrective actions

D.

Ask the sponsor for money to implement the contingency plan.

Full Access
Question # 309

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

Full Access
Question # 310

A product owner has provided the team with a prioritized backlog for the initial

launch of a new product. After analysis, the team concludes that some work is missing to

support the initial launch and provides this information to the product owner. The product

owner acknowledges the missing work and adds it to the bottom of the backlog. The team is

not happy with the prioritization that the missing work received.

What should the project manager do in this situation?

A.

Let the project team pull the recommended work from the bottom of the backlog tomaximize value creation.

B.

Analyze and reprioritize the backlog and provide the decision to the product ownerand team.

C.

Recommend the product owner prioritize the missing work higher because it isneeded for the minimum viable product (MVP).

D.

Empower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.

Full Access
Question # 311

An agile project has just started, and the backlog is being prioritized. The

customer wants to prioritize business value over identified risks.

How should the customer’s request be managed?

A.

Accept risks as they decrease over a period of time.

B.

Create a risk value profile to track the relative importance of risks.

C.

Log and track risks separately as only business value is important.

D.

Assess risks together with business value during prioritization.

Full Access
Question # 312

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Full Access
Question # 313

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?

A.

Create a lessons learned register to include operations team training for future projects.

B.

Include knowledge transfer sessions between the project and operations teams at every stage.

C.

Change the project management plan to add a final stage for product handoff to the operations team.

D.

Prepare detailed documentation to be shared with the operations team during project closure.

Full Access
Question # 314

A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards

What should the project manager do?

A.

Set up a structured, independent processes to determine if project activities followed the standards.

B.

Schedule training for the project team on the new regulations introduced by the government agency

C.

Evaluate the impact the new regulations will have on the project and submit a change request

D.

Update the lessons learned register and inform senior management of the new standards

Full Access
Question # 315

A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?

A.

Request the team member to move to another team.

B.

Delegate other team members to complete this team member's tasks.

C.

Mentor the team member and provide the necessary training.

D.

Include this team member in an improvement program through a human resources request.

Full Access
Question # 316

Drag the technical practices on the left to the scenario on the right.

PMP question answer

Full Access
Question # 317

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Full Access
Question # 318

A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?

A.

Submit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project

B.

Refer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes

C.

Point out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.

D.

Explain that distribution of important news can only be done using traceable communication methods

Full Access
Question # 319

A subcontracting company is presenting its feature release A key stakeholder is asking to add a new feature to the product How should the project manager deal with the new requirement?

A.

Follow the change management process and work with procurement if needed

B.

Engage an arbitrator to resolve any conflict while handling the new requirement

C.

Add the change to the next sprint to meet the customer's needs

D.

Allocate resources to work on the new feature immediately to complete the request

Full Access
Question # 320

A project manager is leading a council's project that aims to ensure full compliance with health, ecological, and environmental standards.

At the same time, the project's goal is to remain fully adherent to the council's values, policies, and procedures.

How should the project manager ensure project success?

A.

Enforce the project manager's authority over the contracting partner delivering to the council. by

B.

Engage a third-party consulting firm to oversee the project's implementation.

C.

Develop the necessary implementation plan and ask the partners to adjust their plans to meet the project manager's objectives.

D.

Meet with the stakeholders regularly to share project objectives and mutually agree on common goals and plans.

Full Access
Question # 321

A newly hired team member just joined the project team and reports directly to the

project manager. In the first week, this new member tells the project manager that there is a

task priority conflict with hard, dependent tasks on the critical path.

What should the project manager do to handle the conflict?

A.

Guide the team member on how to resolve the conflict.

B.

Analyze the project schedule and look for alternatives.

C.

Perform crashing and/or fast tracking of the schedule.

D.

Meet the team member and try to plan a course of action together.

Full Access
Question # 322

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Full Access
Question # 323

A company is involved in a mining project. There are some external stakeholders with no knowledge of the mining industry.

How should the project manager communicate the organizational culture and project goal to these stakeholders?

A.

Hire a company to advertise the project and company through a media outlet.

B.

Prepare a report outlining the organizational structure and project parameters.

C.

Take the stakeholders out informally and verbally brief them about the organization and project.

D.

Ask a team member to directly address the information needs of the stakeholders.

Full Access
Question # 324

A project manager is assigned to a technical research project. The project team has

already been assigned, and the main subject matter expert (SME) sends the project

manager a list of the technical skills required for the execution of this project.

What should the project manager do next?

A.

Send the list to the project team and ask them to get training on the required skills.

B.

Ask the functional manager to review the resource pool and recommend the right individuals to join the team.

C.

Discuss the list with the project sponsor to confirm that the resources have the required skills.

D.

Meet with the project team to understand their skills and identify potential gaps and training requirements.

Full Access
Question # 325

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

Full Access
Question # 326

A large organization decided to adopt an agile methodology based on the trends

seen in the industry. The organization invested a large amount of money in adopting it, but

after a few months, the implementation failed.

What should the project manager have done differently to avoid the implementation failure?

A.

Conducted agile training for all employees ranging from the project teams throughmid-level to upper-level management.

B.

Conducted a postmortem and captured the learning in organizational process assets(OPAs) for future use.

C.

Assessed the organization's culture, performed a suitability analysis, and determinedthe future state.

D.

Hired a third-party agile delivery team to do the implementation.

Full Access
Question # 327

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

PMP question answer

Full Access
Question # 328

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

A.

Be clear with directions and assignments so people stay focused and engaged with their work.

B.

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Full Access
Question # 329

A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.

What should the project manager do to avoid this situation in the future?

A.

Encourage better team communication by positioning team members closer together.

B.

Implement a project management information system (PMIS)

C.

Update the communications management plan to ensure correct delivery of the latest version

D.

Restrict team members from sending the requirements documents via email

Full Access
Question # 330

For an agile pilot project, the sponsor arranged an early product demonstration for the customer. During the meeting, the customer realizes that a new feature will significantly improve the product

After collecting the new requirements, what should the project manager do?

A.

Assess the impact of the new requirements and initiate the change request process.

B.

Work with the product manager and the rest of the team to update the project backlog.

C.

Assess the impact and communicate the updated product roadmap to the stakeholders.

D.

Follow the change management plan to update the risk register so It accounts for the added scope.

Full Access
Question # 331

In an agile project, the project manager notices that one team member rarely reports blockers during daily check-ins. Additionally, the team member is too shy to participate in team activities and prefers to provide status updates individually to the project manager.

How should the project manager rectify this situation?

A.

Review team culture and the personality traits of the individual to address status update gaps.

B.

Create a safe space for status updates and encourage the team to approach the project manager.

C.

Review the team status updates more thoroughly to address the gaps.

D.

Support team inclusion and change the format of status updates to email.

Full Access
Question # 332

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Full Access
Question # 333

An organization is transitioning to an agile environment. The project manager finds that most of the team members are not familiar with an agile environment.

What should the project manager do to address this concern?

A.

Change the approach with the team.

B.

Meet with an agile coach to handle this issue.

C.

Analyze the level of the team's agile maturity.

D.

Support the team members' growth and development.

Full Access
Question # 334

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Full Access
Question # 335

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Full Access
Question # 336

A project manager is assigned to a strategic communication project that involves

subject matter experts (SMEs), interns, and new recruits. The project manager discovers

that the project is not gaining much traction due to knowledge gaps from the interns. The

budget for training is exhausted and the project needs to be delivered without delay.

Which two actions should the project manager take? (Choose two)

A.

Identify the sources and specifics of the knowledge gap from the interns and newrecruits.

B.

Hire more SMEs and inform the human resources manager to lay off thenonperforming interns and new recruits.

C.

Initiate a project change request for additional budget to train the interns and newrecruits.

D.

Ignore the issues with the project and try to deliver the project successfully withoutasking for training funds.

E.

Put the interns and new recruits into groups and assign a SME as a mentor.

Full Access
Question # 337

A company is planning a digitization project. Which action should the project

manager take first when defining the project scope?

A.

Assess the current state process to define the scope of the digitization.

B.

Digitize the current state process exactly as defined.

C.

Redefine the current state process to scope the supporting software.

D.

Develop the software that will support the current state process.

Full Access
Question # 338

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

Full Access
Question # 339

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?

A.

Accept the change and use contingency funds to implement this change with minimal schedule impacts

B.

Reject the change because it is contrary to what was agreed to during earlier phases of the project

C.

Transfer the change to the steering committee for them to evaluate and decide the appropriate next steps

D.

Evaluate the proposed change with integrated change controls and discuss the change with the project sponsor

Full Access
Question # 340

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Full Access
Question # 341

A major project is unable to access the US$12 million funding allocated for the project. This prevents the start of the procurement process and is already leading to costly delays.

What should the project manager do?

A.

Escalate to the project steering committee.

B.

Invite the finance department to the next project demo.

C.

Review the project requirements.

D.

Use the currently available resources.

Full Access
Question # 342

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Full Access
Question # 343

In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)

A.

Limit the number of iterations for development in the contract.

B.

Establish a governance committee to review the contract delivery

C.

Tier the contract for fixed and agile components

D.

Provide alternatives to scope change at specific project phases within the contract.

E.

Require that only internal resources be utilized for this project

Full Access
Question # 344

A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.

What should the project manager do to address this situation?

A.

Inform the steering committee of the situation and request additional resources.

B.

Coordinate virtual and face-to-face meetings at each site to improve communication

C.

Coordinate virtual meetings to assess the project team's communication needs

D.

Inform the project sponsor of this situation and request cultural orientation training.

Full Access
Question # 345

A team has been working together for several months and has successfully

delivered work. A new team member has joined the team but is having difficulty

contributing.

What should the project manager do to help the new team member integrate effectively?

A.

Give the new team member time to contribute until they ask for help and support.

B.

Assign the new team member tasks so that the team member knows on what to focus.

C.

Approach the team member to identify any issues and then plan a resolution accordingly.

D.

Review the project with the team member to ensure the project scope is understood

Full Access
Question # 346

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?

A.

Discuss with the product owner that the user story will not be completed this iteration.

B.

Meet with the team member's functional manager to try to remove the impediment.

C.

Tell the project team member not to work on the production issue and to inform their manager.

D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.

Full Access
Question # 347

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

A.

Implement the planned risk response to handle the issue.

B.

Review possible alternative documentation methods with team

C.

Update the risk register with the risk and proposed impact.

D.

Ask the team to fix the system to resolve the issue

Full Access
Question # 348

An experienced project manager is managing a multi-million dollar agile project The project manager communicates the ground rules to the team but after 12 iterations, the project manager starts noticing that some team members are not following the ground rules.

What should the project manager do first to ensure team adherence to the ground rules?

A.

Schedule a meeting with the project team to reinforce the ground rules.

B.

Notify the project sponsor about this behavior and ask the sponsor to take disciplinary action

C.

Contact human resources to request a written warning letter be sent to team members not following the ground rules.

D.

Ask the functional manager to replace team members not following the ground rules

Full Access
Question # 349

During the course of a project the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings

How should the project manager handle this?

A.

Communicate directly with the director and inform them of the communications management plan

B.

Communicate directly with the client stating that any scope changes must go through the project manager

C.

Review the stakeholder engagement plan and put in place any existing actionsaccordingly

D.

Discuss the issues with the project team and let them know that the project manager will handle scope changes

Full Access
Question # 350

A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next

Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)

A.

Sprint charter

B.

Burndown chart

C.

Company mission and vision

D.

Product backlog

E.

Sprint goal

Full Access
Question # 351

The project manager just started leading a project team from which the previous project manager resigned After a quick evaluation of the project it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule

What should the project manager do?

A.

Conduct a meeting with the project team to discuss and address the sources of disagreement

B.

Inform the stakeholders that the project will be delayed due to previous team management

C.

Crash the project timeline to ensure the project is back on schedule

D.

Issue a change request to extend the project schedule based on identified delays

Full Access
Question # 352

In a time-critical construction project, a misunderstanding occurred between the supervisor and the technician The misunderstanding turned into a major conflict and the technician has complained to the project manager that they cannot continue to work under the supervisor any longer. The supervisor cites the technicians poor performance as the reason for the conflict

How should the project manager resolve the problem?

A.

Talk to the supervisor to tone down their approach and attitude.

B.

Provide a just-in-time training to the technician to improve their skill set.

C.

Use a direct, collaborative approach with the technician and supervisor.

D.

Replace the technician with a high performing resource as time is critical

Full Access
Question # 353

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

A.

Ensuring that the team is also focused on the overall change management plan

B.

Determining and aligning performance indicators that will help in assessing successful delivery

C.

Planning for regular project updates to cover the status of critical deliverables

D.

Ensuring that the scope management plan is in place to cover all related objectives

Full Access
Question # 354

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people tocompensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Full Access
Question # 355

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

A.

Speak with peers about the need for a project charter

B.

Develop the project charter and send it for approval

C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities

D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan

Full Access
Question # 356

The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project

What should the project manager do to reduce negative impacts to the project?

A.

Modify the communications management plan to account for regional differences

B.

Conduct cultural awareness seminars

C.

Hold a virtual meeting to discuss the political environment.

D.

Conduct a multigenerational management training session

Full Access
Question # 357

A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.

What should the project manager do first?

A.

Develop the resource management plan and ensure adequate training

B.

Replace the current project team members

C.

Outsource the task to be completed by a specialized vendor.

D.

Update the issue log to account for the lack of team member qualifications

Full Access
Question # 358

A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.

What should the project manager do to address this issued

A.

Schedule a meeting with critical stakeholders to review the issue and decide on the next steps

B.

Put the project on hold and release the resources until the issue is resolved

C.

Inform the product owner and log the issue in the risk register to monitor closely for next steps.

D.

Contact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.

Full Access
Question # 359

A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?

A.

Review lessons learned from previous projects that used the same team

B.

Review the organizational culture, structure, and governance

C.

Coordinate a meeting to understand the situation and resolve any conflicts.

D.

Coordinate a meeting with regional managers to ask for support

Full Access
Question # 360

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?

A.

Execute it as a Scrum project

B.

Execute it as a predictive project

C.

Execute it using the same approach as the reference project

D.

Execute it as a project with stage gates

Full Access
Question # 361

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?

A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder

B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan

C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan

D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.

Full Access
Question # 362

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

A.

Support the team as necessary to find the minimum viable product (MVP).

B.

Amend the project budget to include MVP testing

C.

Submit a change request to the project sponsor for accelerated testing.

D.

Develop the product as per the schedule to perform integration and testing

Full Access
Question # 363

A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?

A.

Probability assessments

B.

Collaborative discussions

C.

Workshops for risk avoidance

D.

Interview with the project champion

Full Access
Question # 364

One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?

A.

Start an audit of the vendor's processes and procedures

B.

Review lessons learned from previous projects with this vendor

C.

Make a detailed analysis on vendor issues during the project

D.

Execute a contingency plan to address the issue with the vendor

Full Access
Question # 365

A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.

What should the project manager have done to avoid this perception?

A.

Involved the business stakeholders in the sprint review

B.

Defined product backlog priorities with the sponsor and key stakeholders to deliver business benefits

C.

Implemented a closing survey for key stakeholders

D.

Confirmed that there is a communications management plan in place to make business stakeholders aware of the success

Full Access
Question # 366

A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix

What should the project manager do to improve the stakeholder relationship?

A.

Consult the project scope document to make sure the addition is in scope.

B.

Update the stakeholder engagement plan to ensure the stakeholder is included in the project stakeholder list

C.

Initiate a project change request so the change control board (CCB) can decide if it is in scope.

D.

Engage the stakeholder to solicit more information before responding to the request

Full Access
Question # 367

A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team

How can the project manager ensure knowledge transfer across the team?

A.

Ask the project team to run a deviation log review meeting with the client, highlighting that the project may not be able to go live as scheduled

B.

Ask the project management office (PMO) to provide team members with real-time visibility for deviations and facilitate team members to resolve issues

C.

Ask the SMEs to share the knowledge transfer documents with all other members by placing the documents in the project management information system (PMIS)

D.

Ask the project team to facilitate a lessons learned session during the projectclosure phase to incorporate this issue

Full Access
Question # 368

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

Full Access
Question # 369

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

A.

Updated the risk management plan and registered lessons learned for the project

B.

Reorganized the team for the project based on the work breakdown structure (WBS)

C.

Maintained constant communication with the stakeholders of the other projects

D.

Used the resource management plan to identify the impacts of the other projects

Full Access
Question # 370

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement

What should the project manager do next?

A.

Escalate the issue to the project sponsor and add it to the risk register

B.

Refuse to work on the project because management is not following standard project management practices

C.

Meet with management to explain the potential problems with running a project without a project scope statement

D.

Start the project with inputs from the project charter to save time

Full Access
Question # 371

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43

What should the project manager do?

A.

Ask the project team to perform the modifications since the project budget and schedule can support them.

B.

Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested

C.

Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.

D.

Analyze the reason for the gap in understanding with both sides and negotiate a solution

Full Access
Question # 372

During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization

What should the project manager do first?

A.

Update project documents to include adaptive tools and artifacts and plan the first iterative session

B.

Contact the project sponsor and request new team members who are familiar with adaptive projects

C.

Confirm team capabilities before introducing adaptive tools and artifacts to the project

D.

Freeze the design stage and look for an external resource to run iterative design at extra cost

Full Access
Question # 373

A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.

Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck

PMP question answer

Full Access
Question # 374

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

A.

Allocate and use part of the project's contingency reserves for training purposes.

B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.

C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training

D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community

Full Access
Question # 375

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Full Access
Question # 376

A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished

How should the project manager approach this situation?

A.

Request that the customer reviews and clarifies feature definitions for the current sprint

B.

Send a burndown chart of the current sprint to the customer and seek clarifications.

C.

Educate the customer and have them participate in daily standup meetings.

D.

Schedule weekly meetings and product reviews with the customer to clarify requirements

Full Access
Question # 377

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)

A.

Contact the team member's functional manager and invite them to the next retrospective

B.

Meet with the entire team to review the ground rules about safe environments

C.

Meet with the product owner to talk about the situation.

D.

Contact the team member to explain what information can be shared outside the team

E.

Meet with the sponsor to review the situation.

Full Access
Question # 378

A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required

How should the project manager assist the product owner?

A.

Coach the product owner on how to create a product backlog

B.

Encourage the team to subdivide the project tasks

C.

Create a work breakdown structure (WBS) and explain the deliverables to the product owner

D.

Discuss the product owner's responsibilities within the project team

Full Access
Question # 379

During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.

What should the project manager do to prioritize this critical impediment?

A.

Solve the issue for the team member.

B.

Perform a brainstorming session to address the issue and add the solution to the sprint.

C.

Escalate the issue to the software vendor for technical resolution

D.

Coach the team to come up with their own solution and add it to the next sprint

Full Access
Question # 380

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Full Access
Question # 381

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

A.

Recruit the best resources within the organization to be part of the virtual team

B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls

C.

Identify the types and quantities of resources required for each work package or activity

D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress

E.

Verify if team members are on more than one team and cannot devote enough time to this team

Full Access
Question # 382

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings

How should the project manager handle this moving forward?

A.

Ask that only key decision makers attend the project meetings.

B.

Update the project schedule to cater to this particular stakeholder

C.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

D.

Update the risk register to consider the possible project impacts

Full Access
Question # 383

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.

What should the new project manager do to address the process improvements?

A.

Understand the context and interdependencies of the process from the team members and then define improvements

B.

Continue with the process as is. and wait until the next phase to suggest any improvements

C.

Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework

D.

Define a ground rule to comply with the quality standard and ask the team members to apply it.

Full Access
Question # 384

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Full Access
Question # 385

During project execution, the project manager discovered that a key deliverable was missing from the scope of work After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path

What should the project manager do to avoid future delays?

A.

Submit a change request.

B.

Add additional resources to the project

C.

Update the scope of work.

D.

Review the risk management plan

Full Access
Question # 386

A project manager is leading a large-scale project that involves 70 stakeholders The project manager has heard various comments and expectations from the customers, some of which are contradictory Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

A.

Escalate the issue to the management team for their review and guidance

B.

Create a survey template to collect feedback from stakeholders to reach an agreement

C.

Organize a face-to-face meeting with all stakeholders to understand their interests and concerns.

D.

Leverage expert judgment to determine the requirements that should be considered

Full Access
Question # 387

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?

A.

Increased bum rate

B.

Increased cost

C.

Increased technical debt

D.

Decreased efficiency

Full Access
Question # 388

The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)

A.

Discuss with the construction team alternatives on moving the new train station to another location.

B.

Publish information on the city’s website about the benefits that the new tram station will bring

C.

Have a meeting with the mayor and explain the importance of the new train station to the city.

D.

Conduct regular meetings with the neighbors to get their buy-in for the project

E.

Register this situation as a risk and develop a mitigation plan

Full Access
Question # 389

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)

A.

A team member talking about a user story that is not on the Scrum board

B.

A team member talking about a user story that is on the Scrum board

C.

A technology that blocks agile capabilities

D.

A lack of team empowerment and an inability to self-organize

E.

A review of the backlog at daily standup meetings

Full Access
Question # 390

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

PMP question answer

What should be the priority order in the product backlog?

A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2

B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2

C.

Requirements, Requirement 1, Requirement2

D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Full Access
Question # 391

Team members are having a discussion with the project manager In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project The team recommends buying new equipment because it is critical to the success of the final deliverable

What should the project manager do next?

A.

Check the project budget to verify if there is enough contingency reserve

B.

Review the cost management plan to determine how to address this issue

C.

Tell the team members that more equipment is not part of the project's scope.

D.

Submit a change request to increase the budget and buy new equipment

Full Access
Question # 392

During the course of a project, the team develops negative group behaviors and becomes unmotivated and unproductive. What should the project manager do to improve the project team's performance?

A.

Define and analyze performance metrics

B.

Escalate poor performance to functional managers

C.

Update the stakeholder engagement plan

D.

Conduct a root cause analysis session

Full Access
Question # 393

A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?

A.

Ensure the stakeholder engagement plan is accurate and properly documented.

B.

Review the lessons learned from the previous project

C.

Identify the risk of implementing the new solution and evaluate the impact on the project.

D.

Create a lessons learned document for the initiation phase

Full Access
Question # 394

Drag the communication event on the left to the mam subject discussed during the event on the right.

PMP question answer

Full Access
Question # 395

A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

PMP question answer

Full Access
Question # 396

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?

A.

The team facilitator gets support from external team members.

B.

The team members bring in a specialist to help them

C.

The product owner moves it to the product backlog.

D.

The cross-functional team member work together to complete the activity

Full Access
Question # 397

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Full Access
Question # 398

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?

A.

Ensure the sprint size is appropriate for the iteration duration.

B.

Promote changing the iteration duration in order to commit as planned.

C.

Engage in recruiting a highly skilled resource to reinforce the skills.

D.

Consider using a reward system to encourage timely delivery

Full Access
Question # 399

An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right

PMP question answer

Full Access
Question # 400

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?

A.

Check the approved list of requirements to see if there are any missing items.

B.

Work with the stakeholder to improve the requirements' acceptance criteria

C.

Review the requirements traceability matrix with the concerned stakeholder

D.

Discuss with the stakeholder which additional requirements should be added

Full Access
Question # 401

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Full Access
Question # 402

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?

A.

The project charter and scope statement

B.

The requirements traceability matrix

C.

The business requirement documents (BRD)

D.

The WBS dictionary

Full Access
Question # 403

A new project has been kicked off following a planning session. The project is under direct oversight of an executive in the organization After a review meeting, the project manager overhears an executive request a dashboard from one of the team members to show the overall project status

What should the project manager do?

A.

Update the stakeholder engagement assessment matrix

B.

Update the communications management plan to include informal requests

C.

Ask the team member to develop a dashboard to fulfill the request.

D.

Tell the team member to route the request through the project manager

Full Access
Question # 404

A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard What should the project manager do?

A.

Review the project management plan

B.

Update the stakeholder engagement plan.

C.

Update the communications management plan

D.

Review the configuration management plan.

Full Access
Question # 405

A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget

What should the project manager do next?

A.

Request a replacement resource

B.

Perform a cost-benefit analysis

C.

Implement risk responses

D.

Perform Integrated Change Control

Full Access
Question # 406

The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable

What personality indicators should the project manager consider when determining what communication style to use with this team member?

PMP question answer

Full Access
Question # 407

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

A.

Hold a stakeholder meeting to align timelines and scope expectations.

B.

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.

Reduce the scope of the project by removing activities and shortening the timeline

Full Access
Question # 408

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Full Access
Question # 409

A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.

What should the project manager do to enhance project team effectiveness?

A.

Implement team colocation to improve communication.

B.

Identify the root cause of communication issues

C.

Initiate daily communication of project progress

D.

Schedule a communications control board meeting

Full Access
Question # 410

A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?

A.

Coach those team members lacking hybrid knowledge to learn on the job.

B.

Change the team to include hybrid experts

C.

Assess the required training per team member.

D.

Deliver hybrid training to all team members

Full Access
Question # 411

A Scrum team has committed to delivering a specific capability in their first release Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company

What should the project manager have the Scrum team do to recover from these issues?

A.

Review constraints in the ongoing sprint planning and evaluate options for the release plan

B.

Stop the sprint and replan and prioritize the backlog to reduce resource levels

C.

Consult the resource management plan for an appropriate response

D.

Continue with existing sprint plans to ensure some of the scope will be delivered

Full Access
Question # 412

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Full Access
Question # 413

One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager's concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate

What interpersonal skill did the project manager use?

A.

Networking

B.

Emotional intelligence

C.

Conflict management

D.

Influencing

Full Access
Question # 414

During project execution, a project manager is informed that most of the project team members have enrolled in the newly implemented work-from-home company policy. How should the project manager reflect this change in the project?

A.

Update the communication styles for enrolled team members in the communications management plan.

B.

Update roles and responsibilities for enrolled team members in the responsibility assignment matrix (RAM)

C.

Update the stakeholder engagement plan to include the emergency contact information for enrolled team members.

D.

Update the resource calendar for enrolled team members in the resource management plan

Full Access
Question # 415

The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?

A.

Seek expert legal advice on the interpretation of the clauses in the contract

B.

Hold a meeting with the project team project sponsor and the client to agree to the further work required to close the project and add to lessons learned

C.

Close the project and hand over the deliverables to the client

D.

Hold a lessons learned workshop with the project team and project sponsor to avoid contractual compliance issues arising in future projects

Full Access
Question # 416

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Full Access
Question # 417

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Full Access
Question # 418

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.

C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report

D.

Research which templates of reports were used the most for this framework and incorporate them into the project

Full Access
Question # 419

A company wants to increase the commercial value of one of its products in a highly competitive market In order to do this, the company commissions a project to create a prototype The team constructs the prototype incrementally Which action should the project manager take as a priority?

A.

Emphasize the use of Kanban methodology.

B.

Ensure the project sponsor is aware of the go-to market date

C.

Deliver business value as soon as possible

D.

Implement a plan-do-check-act (PDCA) cycle

Full Access
Question # 420

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)

A.

Define team ground rules

B.

Perform a retrospective session

C.

Implement daily team meetings.

D.

Request a manager performance review

E.

Conduct an annual review.

Full Access
Question # 421

Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings

What should the project manager do?

A.

Schedule a meeting for the project team to review the communications management plan.

B.

Tell the rest of the project team to continue discussions with the new team member

C.

Send an email to the project team outlining the communications strategy.

D.

Mentor the new team member on the methodology the project team is using

Full Access
Question # 422

As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.

What should the project manager do first to decide how to manage this project?

A.

Select a predictive development life cycle based on the team's experience

B.

Determine the most appropriate life cycle approach for the project

C.

Register all requirements into a backlog for further detailed analysis.

D.

Split the requirements, put them into two separate projects, and apply different approaches

Full Access
Question # 423

A project manager just started managing agile projects The project manager realizes that due to the lack of a clear definition of project objectives and definition of done (DoD) their colleague's projects have had many difficulties Sponsors keep asking for more features and the projects have yet to be completed

What should the project manager do to avoid these issues?

A.

Arrange meetings to ensure every necessary task to complete the project is included in the project management plan

B.

Convince the project sponsor to incorporate quality experts so the product can be tested and accepted as completed.

C.

Convince the product owner to approach the team and look for options to find a solution to the problem

D.

Schedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project

Full Access
Question # 424

According to a new product development process, the marketing department will begin adding business and user requirements directly into agile project documents. Drag the product information on the left to the correct documents on the right

PMP question answer

Full Access
Question # 425

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

Full Access
Question # 426

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Full Access
Question # 427

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two)

A.

Issue log

B.

Risk register

C.

Stakeholder register

D.

Change log

E.

Backlog register

Full Access
Question # 428

An organization has historically executed most projects using a predictive approach The organization now wants to change over to an agile approach

Which strategy will be useful to effectively help prepare the organization for this change?

A.

Create a task force of executives who will monitor agile projects on a daily basis

B.

Add multiple layers of managers who will be accountable for the agile execution

C.

Improve organizational readiness by addressing impediments to agile in the organization.

D.

Take a big bang approach of moving the whole organization to agile at once

Full Access
Question # 429

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?

A.

Four iterations

B.

One iteration

C.

Two iterations

D.

Three iterations

Full Access
Question # 430

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project's changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Full Access
Question # 431

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)

A.

Prepare the lessons learned from the project phase.

B.

Obtain official approval on the new process from the various countries

C.

Send a questionnaire to the project participants and seek their feedback.

D.

Refer to the communications management plan

E.

Deliver the project materials to the users and see if they have any comments

Full Access
Question # 432

A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented

What should the project manager do?

A.

Prepare a change request and seek approval from the steering committee regarding the new project framework

B.

Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan

C.

Bring in a third party company to develop and implement a hybrid framework for this specific project.

D.

Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects

Full Access
Question # 433

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

Full Access
Question # 434

A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty

What should the project manager have done to avoid this situation?

A.

Ensured the team charter was developed by the team members

B.

Ensured the team members are fully supportive of all decisions.

C.

Distributed the project charter to all team members.

D.

Used a charismatic leadership style

Full Access
Question # 435

A project manager is leading a project that is in the execution phase. During a team

meeting, the project manager realizes that there are two team members who lack the

technical skills required for some of the upcoming tasks.

What should the servant leader project manager do next?

A.

Recommend to the team members to upskill themselves on the requirements for theproject.

B.

Discuss with the human resource (HR) manager about the possibility of changing teammembers.

C.

Inform the sponsor about a possible delay due to the lack of skills in the team.

D.

Explore a training program that is within the project budget for the team members.

Full Access
Question # 436

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Full Access
Question # 437

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Full Access
Question # 438

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

A.

Explain the impact of the scenario to the project team member.

B.

Remove the project team member from all future meetings.

C.

Talk to the client privately to highlight the situation.

D.

Recommend a performance improvement plan to the project team member.

Full Access
Question # 439

An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client's project manager has no agile experience.

How should the project manager ensure that the client is effectively represented in the daily meetings?

A.

Recommend agile training programs that best suit the client project manager's schedule.

B.

Realign the project to a predictive approach to ensure optimal collaboration between the teams.

C.

Propose a session tor essential agile Knowledge transfer for the client team to align with the daily meeting goals

D.

Provide the client project manager with agile best practice documents and web resources.

Full Access
Question # 440

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Full Access
Question # 441

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

A.

Update the issue log and review the lessons learned register for options

B.

Implement conflict resolution to accommodate the team's needs

C.

Implement decision-making techniques to advance the stones

D.

Empower the team to self-organize and make their own decisions

Full Access
Question # 442

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?

A.

Consult the previous project manager to discuss how they managed these questions.

B.

Ensure all engineers are aware that questions should only be submitted in their weekly reports.

C.

Email the company vision to the engineers and tell them they need to meet deadlines

D.

Reinforce to all engineers the company vision of a safety-first approach to project activities.

Full Access
Question # 443

A project manager is assigned to a digital transformation project for a bank. The company culture is conservative and resistant to transformation or innovation. What should the project manager do first to support the transformation''

A.

Provide a digital transformation guide and explain that the change is unavoidable

B.

Ask the bank executives to officially announce that the project manager is leading the project

C.

Provide proper training sessions to the stakeholders so they understand the purpose of the change

D.

Hire an expert in digital transformation and assign that person as the champion for the change

Full Access
Question # 444

In the planning phase, a project manager receives identified risks from the sponsors

and subject matter experts (SMEs) and wants to develop a risk response strategy for them.

What should the project manager do first?

A.

Perform a risk reserve analysis.

B.

Assign allocated budget to cover key risks.

C.

Agree on the criteria to prioritize risks.

D.

Assign a risk responsibility to each team member.

Full Access
Question # 445

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

A.

Project owner

B.

Agile leader

C.

Agile team

D.

Product owner

Full Access
Question # 446

A project manager writes to the receiving organization to inform them that all

acceptance activities are completed with success and it is time to initiate handover. The

receiving manager replies that the team will not be ready for the handover procedure for

another two weeks.

What should the project manager do?

A.

Deliver to the receiving manager on time, who can then make a knowledge transfer totheir team.

B.

Inform the project sponsor of the two-week delay and replan activities to minimizedelays.

C.

Request that the receiving manager issue a change request to prolong the project bytwo weeks.

D.

Issue an internal change request to secure the resources for an additional two weeks.

Full Access
Question # 447

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

A.

Escalate the issue to the project sponsor, as the decision to add the component bringsmany benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures thatled to the decision to add a component that was not compatible with the productionline.

C.

Meet with the operations manager to explain the background for the change andunderstand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that theproject may deliver late and over budget due to manufacturing difficulties.

Full Access
Question # 448

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

Full Access
Question # 449

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.

Remind the team frequently that the project must be delivered on time and within budget

C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues

Full Access
Question # 450

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

A.

Product backlog, budget, resource management plan

B.

Budget, minimum viable product (MVP), retrospective notes

C.

Resource management plan, retrospective notes, backlog grooming

D.

Backlog grooming, product backlog, minimum viable product (MVP)

Full Access
Question # 451

Eight people have been working on a project for an extended period of time. The

scope has changed significantly and the product owner has been replaced multiple times. The

team members are feeling disassociated from the project.

What should the project manager do to ensure team alignment with the goals?

A.

Ask the new product owner to explain the importance of the project.

B.

Email the team a detailed outline of the business requirements.

C.

Review the project charter with the team.

D.

Facilitate a discussion of the vision for the project.

Full Access
Question # 452

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.

B.

Commit each team member's time and deliverables and aim for overall projectcompletion.

C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.

D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.

Full Access
Question # 453

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

A.

Escalate the situation to the engineer's manager

B.

Request external training for the engineer

C.

Request external training for the engineer and designer

D.

Allow the engineer and designer to cross-train with each other

Full Access
Question # 454

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

A.

Change management plan

B.

Schedule management plan

C.

Scope management plan

D.

Cost management plan

Full Access
Question # 455

A project manager working on a large-scale network implementation is frustrated

with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager's company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.

What should the project manager do first to proceed with this change?

A.

Engage the services of an interpreter who understands the project domain.

B.

Check social media to determine if there are any common connections that use the new supplier.

C.

Request assistance from the procurement department on the next steps.

D.

Become aware of any cultural characteristics of the new supplier that could impactnegotiation.

Full Access
Question # 456

During project execution a project team member resigned and a new junior member joined the team To smooth the transition the project manager assigned a senior project team member to transfer knowledge and support the junior team member The project manager subsequently received feedback from the senior team member saying that the junior member submitted a poor-quality deliverable and should be removed from the team However the project manager checked that deliverable and found it met quality requirements

Which technique should the project manager use to resolve this issue?

A.

Smooth/accommodate

B.

Compromise/reconcile

C.

Force/direct

D.

Collaborate/problem solve

Full Access
Question # 457

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.

B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.

C.

Demand that the business team stop wasting time and define final requirements for the product.

D.

Tell the business team and Scrum team to continue following the initial plan.

Full Access
Question # 458

A project team is experiencing conflict between two team members. Team member A feels that team member B is always talking over team member. A and does not listen to any advice Team member B is not willing to listen to feedback

What should the project manager do to resolve the issue?

A.

Move one of the team members to a different protect team

B.

Review the ground rules for collaboration within the team

C.

Report the performance issue to both of the team members' supervisors

D.

Modify the communications management plan and resend it to the team

Full Access
Question # 459

A key project stakeholder does not attend any of the project meetings and is

providing false information that the project team is not delivering on time. What should the

project manager do to address this situation?

A.

Create a new communication artifact for the key stakeholder.

B.

Email the latest status report to the key stakeholder.

C.

Share the meeting recordings with the key stakeholder.

D.

Discuss communication needs with the key stakeholder.

Full Access
Question # 460

On a project with multiple international locations, a trend for delays has been

flagged. When looking into the issue, the project manager realized that some of the key

activities were scheduled over the holiday periods in the overseas offices.

What should the project manager do next?

A.

Update the schedule to reflect the holidays and share the workload among offices tomitigate schedule slippage.

B.

Hire additional personnel on a temporary basis to cover the extra workload during theholiday seasons.

C.

Request that the offices in overseas locations work overtime to mitigate scheduleslippages.

D.

Update the schedule to reflect the holidays and notify the project sponsor of thedelayed completion.

Full Access
Question # 461

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

PMP question answer

Full Access
Question # 462

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working asexpected.

Full Access
Question # 463

A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?

A.

Establish mentoring and coaching sessions.

B.

Review the knowledge repository for similar projects.

C.

Schedule the project kick-off meeting immediately.

D.

Meet with the project sponsors to align expectations

Full Access
Question # 464

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

PMP question answer

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Full Access
Question # 465

A project has been running successfully for 2 months. At a regular project meeting,

the team raises several potential obstacles to future progress. The obstacles include vendor

delivery performance, technical performance of a subsystem, and conflict with another division of the organization.

What should the project manager do next?

A.

Work with the team and others in the network to assess and prioritize the obstacles.

B.

Engage with the external stakeholders and the other division of the organization toresolve the issues.

C.

Escalate the obstacles to the project sponsor for assistance with resolution.

D.

Determine a change response to identify and resolve the obstacles to move the projectforward.

Full Access
Question # 466

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Full Access
Question # 467

A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype

What should the project manager do to accelerate this solution?

A.

Contact the other project team and ask them to organize a demo of the prototype

B.

Perform iterative planning with the team to use the prototype

C.

Check the burnup charts to see what progress has been made to integrate the solution

D.

Prioritize the backlog with the customer to remove the feature

Full Access
Question # 468

A company is conducting a digital transformation project that has a hard deadline.

The marketing team wants to combine this implementation with a new product, and the newly

assigned project manager is not aware of all the dependencies.

Using a hybrid approach, what should the project manager do to ensure the dependencies are

taken into consideration?

A.

Implement a project newsletter so the different team members can be informed aboutthe progress of each project.

B.

Combine all of the small projects into one big project so the team can collaboratebetter as one big team.

C.

Facilitate communication promoting a Scrum of Scrums so the different teams areaware of the dependencies and progress.

D.

Make sure that each individual project schedule is aligned with the common deadlines.

Full Access
Question # 469

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?

A.

Share unsuccessful results from previous projects with a similar scope

B.

Provide the failed test results along with the agreed-upon acceptance criteria

C.

Show that the acceptance criteria were changed by the vendor without approval.

D.

Document in the risk log that the issues in the system were already identified

Full Access
Question # 470

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

Full Access
Question # 471

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

Full Access
Question # 472

A company is moving to a hybrid approach and conducted capacity activities for all of the project managers. During these capacity-building activities, the focus was on agile approaches and team facilitation skills. When starting the implementation phase, the project managers faced issues motivating the newly hired agile staff.

Why are the project managers having issues motivating the agile staff?

A.

The capacity building activities missed the servant leadership concept transfer.

B.

Transitional periods normally cause this type of problem.

C.

The agile staff is not used to being led by a project manager.

D.

Project managers are expected to become coaches in agile teams.

Full Access
Question # 473

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration

B.

Requested the product owner's approval to add an external expert to define theacceptance criteria

C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject

D.

Increased the communications between the team member and the product owner

Full Access
Question # 474

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

A.

Inform the customer that moving the milestone has a very high impact on project cost.

B.

Escalate the Issue to senior management so they can impose a solution on the customer.

C.

Convince the customer to keep the requirements as is and not move the milestone.

D.

Review the customer's priorities regarding the desired requirements for the milestones.

E.

Discuss which requirements can be delivered faster with the project team.

Full Access
Question # 475

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

Full Access
Question # 476

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.

B.

Escalate the situation to upper management.

C.

Add more team members to make up for any project delays.

D.

Address the issue with the stakeholder and explain the situation.

Full Access
Question # 477

A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects.

What should the project manager do next?

A.

Refer to the previous protect they worked on and base the estimate on that

B.

Use expert judgment to estimate the schedule and then adjust the schedule as the project progresses

C.

Ask the project management office (PMO) by when the project can be completed and use that date as the project time line

D.

Break down the project into smaller tasks and estimate the durations of the activities

Full Access
Question # 478

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?

A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.

B.

Develop a communications management plan for each category in the stakeholder register.

C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.

D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.

Full Access
Question # 479

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

A.

Document the risk register in the project charter.

B.

Speak to the customer and add the issue to the issue log.

C.

Review user roles and update the team charter.

D.

Involve the product owner to rewrite the user stories.

Full Access
Question # 480

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Full Access
Question # 481

An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time

What should the project manager have done to avoid this delay?

A.

Updated the stakeholder engagement plan to reflect a change in the product owner

B.

Communicated the status of the project more frequently with the product owner

C.

Updated the communications management plan to reflect a change in the communication needs

D.

Reevaluated the new product owner's needs for better engagement

Full Access
Question # 482

During the sprint planning of a project, the team members have a disagreement

about the comparative size of the backlog items and if they would fit into the next sprint.

Considering a hybrid approach, what should the project manager do?

A.

Ask an external technical leader to provide input and plan the sprint.

B.

Remove the items from the product backlog since the size couldn't be estimated.

C.

Make the decision about the backlog items based on what makes more sense.

D.

Facilitate the discussion so that the team members can reach a consensus.

Full Access
Question # 483

During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.

What should the project manager do next?

A.

Include additional mitigation actions against feature defects and update the risk management plan.

B.

Assess the relevance of the feature and then analyze the submission of a change request to descope it.

C.

Improve the control quality process by implementing additional testing to minimize the defects before the go-live milestone.

D.

Determine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.

Full Access
Question # 484

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer

B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports

C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop

D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server

Full Access
Question # 485

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

A.

Request a reserve analysis and update the risk management plan

B.

Update the risk response plan to include the needed reserve

C.

Perform a schedule network analysis to avoid any critical path delays

D.

Review the risk response plan to verify inclusion of the needed reserve

Full Access
Question # 486

When a project manager is trying to determine a leadership style to use on a project what should they consider?

A.

Number of tasks on the protect

B.

Culture of the organization

C.

Project timeline

D.

Experience of the project manager

Full Access
Question # 487

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

A.

Send an email update to existing team members about the addition of the new teammembers.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Full Access
Question # 488

A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?

A.

Document the new stakeholders' concerns in the meeting minutes.

B.

Schedule an ad hoc meeting with the new stakeholders to discuss concerns.

C.

Use social media environments to share the project information

D.

Use the project management information system (PMIS) to share information.

Full Access
Question # 489

An agile team has started a new project. When should the project manager organize their first team retrospective?

A.

When the team completes a release of a monumental increment

B.

When the team reaches a major milestone

C.

When more than a few weeks have passed

D.

When the work is progressing well through the team

Full Access
Question # 490

Vendor A submitted a bid for US$500,000. There is a 65% probability that the

vendor will deliver behind schedule with a cost overrun of US$ 100,000. The vendor will come

in ahead of schedule for a savings of US$50,000.

What should the project manager determine as the value of the vendor's bid?

A.

US$650,000

B.

US$452,500

C.

US$547,500

D.

US$582,500

Full Access
Question # 491

A project manager is leading an electrical project that spans five towns. The project

manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.

What should the project manager do?

A.

Change the project scope and seek approval to exclude this town from the overallproject.

B.

Engage with the town's authorities to discuss the reason for the change in commitmentand agree on a solution.

C.

Instruct the team to move to the next town and continue the project to avoid further delays.

D.

Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.

Full Access
Question # 492

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?

A.

Ensured the project team documented lessons learned about the issue

B.

Ensured the project team applied a long-term solution for the issue

C.

Asked the project team to conduct more testing with users

D.

Discussed the issue with the stakeholders

Full Access
Question # 493

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

A.

Engage the project team In implementing and Improving key aspects of the standup meetings.

B.

Ask the product owner to remove team members who do not comply with standup meeting rules.

C.

Send a daily retrospective report to all team members instead of holding standup meetings.

D.

Include a daily brainstorming session In the standup meetings to resolve pending Issues.

Full Access
Question # 494

A project sponsor asks the project manager to explore a hybrid approach for a new

project. The product manager for this project has already prepared a detailed specification for the product.

What should the project manager do to proceed with the project management plan?

A.

Ask the team to assess whether the product specification can be expressed in userstories to enable a Scrum or Kanban approach.

B.

Explore with the product manager to determine if there are viable opportunities todeliver value incrementally and increase business value.

C.

Recommend to the project sponsor that a predictive approach is appropriate for theproject due to the stable product requirements.

D.

Ask the product manager whether they are prepared to act as product owner for theproject in order to participate in iterative planning and reviews.

Full Access
Question # 495

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team

B.

Continue working on the defined scope and review the risk matrix

C.

Have a discussion with the project sponsor and cancel the project

D.

Have a discussion with the sponsor and recommend the project business value be reassessed

Full Access
Question # 496

A company's board of directors announced that a major layoff will occur at the end of the month. When evaluating the impact the protect manager found that 25°© of the project team members are part of the layoff

What should the project manager do first?

A.

Request a meeting with the project sponsor to discuss the viability of the project and determine the next actions

B.

Request a meeting with the customer and discuss trade-offs to reduce the scope and product quality as a result of the lack of personnel

C.

Request a meeting with the finance department to increase the budget of the project to hire temporary personnel to perform the affected activities

D.

Request a meeting with the human resources (HR) department and demand they find a solution to retain the project team members

Full Access
Question # 497

An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.

What should the agile leader do?

A.

Reassign the task to another team member and require the team member to complete training

B.

Use the retrospective meeting to remind the entire team that they must complete all deliverables in each sprint

C.

Review the definition of done (DoD) with the team so that everyone understands what the team must deliver in this sprint.

D.

Speak directly with the team member about improvements and commit to an agreed-upon time frame.

Full Access
Question # 498

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

A.

Request the project team include the stakeholder's details and make sure the projectstatus reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register forincorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Full Access
Question # 499

A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity

How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?

A.

Set up a meeting with the stakeholder to address their concerns directly

B.

Move to a predictive design-and-requirements gathering approach

C.

Talk to the team separately to address the stakeholder's concerns

D.

Schedule a team retrospective and invite the stakeholder

Full Access
Question # 500

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Full Access
Question # 501

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

Full Access
Question # 502

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

A.

Notify all team members that all steps in the process must be completed.

B.

Escalate the issue to the other executive leadership members.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

Full Access
Question # 503

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

A.

Determine the critical requirements.

B.

Document the risks and mitigations.

C.

Define the project schedule.

D.

Create a project scope statement.

Full Access
Question # 504

A project manager is assigned to lead a design for a new version of an existing

product with the technology and operations teams. The project manager organizes a joint

requirements session to determine the most practical ideas. The project manager was advised

that the session may become chaotic.

What should the project manager do to ensure the session is interactive, productive, and

efficient?

A.

Pick the senior and experienced staff members from both teams and arrange face-toface interviews.

B.

Organize a formal session led by a skilled facilitator with defined rules for howparticipants will interact with one another.

C.

Distribute a questionnaire on the key features of the product and encourage the teamsto respond with their design recommendations.

D.

Hold multiple sessions of manageable sizes with participants from both teams todiscuss their ideas.

Full Access
Question # 505

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

A.

Invite the product owner to attend daily standup meetings so they can assessprogress.

B.

Set up a feedback session with the product owner once a week so they can assessprogress.

C.

Instruct the team to refer the product owner to the project manager for information.

D.

Invite the product owner's functional manager to a feedback session to escalate theissue.

Full Access
Question # 506

A new project manager has been assigned to an environmental project. After

reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

A.

Injury or loss incidents could delay project deliverables.

B.

It is imperative that established performance metrics are met.

C.

The project manager is obligated to comply with the project location's regulatoryrequirements.

D.

The project manager must follow their employer's organizational process assets(OPAs).

Full Access
Question # 507

A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities

What should the team do differently during planning for the next iteration"?

A.

Request the product owner and team facilitator to provide the size of the story

B.

Average the story points provided by each team member for a story

C.

Continue multiple rounds of planning poker and arrive at the size of the story

D.

Collaborate with different teams and arrive at the size of the story

Full Access
Question # 508

An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.

What should the project manager recommend?

A.

Ensure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.

B.

Ask the team to prioritize the high-priority items based on what they feel is a logical sequence to build.

C.

Ask the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.

D.

Discard the current categorization of requirements as high, medium, and low and prioritize numerically.

Full Access
Question # 509

A project manager is leading the first agile project for the organization. During the

kick-off meeting, the project manager notices that the team does not have the same

understanding about agile approaches. The project manager is concerned about the impact of that confusion.

What should the project manager do to address this situation?

A.

Evaluate the possibility of managing this project using a predictive approach.

B.

Submit a change request for a new team that has agile experience.

C.

Mentor the team to explain agile principles and create a shared understanding.

D.

Hire a functional manager who is familiar with agile methodologies.

Full Access
Question # 510

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

Full Access
Question # 511

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer

B.

Meet with both integration leads to understand the root cause and determine a resolution

C.

Escalate the issue to the program architect who developed the integration plan

D.

Assign the resolution of this issue to the integration lead who is a SME

Full Access
Question # 512

A customer interacts directly with a Scrum team and continually requests changes in

priorities. This causes confusion among the team members and they complain to the project

manager.

What should the project manager do?

A.

Advise the customer to discuss changes with the product owner.

B.

Document this issue in the sprint backlog for discussion at a team meeting.

C.

Ask the customer to submit a change request to the project sponsor.

D.

Encourage the team to clarify the requests with the customer.

Full Access
Question # 513

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team memberson the project.

B.

Ensure planning has accounted for replacing team members in new project roles whodo not deliver on project goals.

C.

Assess the training requirements and ensure time for professional developmenttraining by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team membersassigned to the project.

Full Access
Question # 514

A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team's knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.

What should the project manager do?

A.

Ask to execute the project with a predictive approach since there is a budget and schedule risk

B.

agile tools and techniques used m the defined hybrid methodology for consistent application by all team members

C.

Use the predictive approach tor team members who are not knowledgeable m agile project delivery practices

D.

Use crashing to reduce the critical path to ensure enough buffer to include the impact of the agile methodology update

Full Access
Question # 515

A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.

Why did this action occur?

A.

Inadequate funds for the automation project

B.

Inadequate engagement of the political stakeholders

C.

Lack of competence to manage the automation project

D.

Lack of a proper legal framework in place

Full Access
Question # 516

A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?

A.

Escalate the change request to the sponsor

B.

Validate the work completed

C.

Inform the stakeholders of the change

D.

Facilitate the update of the product backlog

Full Access
Question # 517

Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.

What should the project manager do to resolve this issue and help the team move on to the next iteration?

A.

Postpone the selection of the technology used until more information is gathered

B.

Suggest their own approach to solve the issue and ask the team to follow it

C.

Call for an open dialogue which the team will arrive at through consensus

D.

Allow the team to decide since the teams should be autonomous

Full Access
Question # 518

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

A.

Schedule team-building activities to encourage collaboration among the team

B.

Coach the team members to resolve the gaps in understanding

C.

Conduct a kick-off meeting and communicate the goals and objectives of the project

D.

Continue the meetings and communicate the goals and objectives to resolve the gaps

Full Access
Question # 519

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

A.

Put the new requirements in the backlog with high priority and implement therequested changes.

B.

Put the new requirements in the backlog and submit a formal change request forapproval.

C.

Put the new requirements in the backlog and let the product owner check their valueand priority.

D.

Put the new requirements in the backlog with low priority and implement the requestedchanges.

Full Access
Question # 520

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

A.

Functional managers, team members, and external consultants with experience in the field

B.

Team members, engineers, and weather experts

C.

Team members, consultants from outside the project with experience in the field, and the customer

D.

Weather experts, functional managers, and team members

Full Access
Question # 521

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

A.

Perform a qualitative risk analysis and update the risk register.

B.

Submit a change request through the Integrated change control process.

C.

Update the issue log and discuss It in the next steering committee meeting.

D.

Estimate the associated costs and increase the project budget accordingly.

Full Access
Question # 522

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.

Which two actions should the project manager leverage to ensure the team is meeting performance expectations?

(Choose two)

A.

Hold daily virtual meetings to review progress.

B.

Implement time-keeping software for team members.

C.

Task functional managers to drive accountability.

D.

Utilize a web-based kanban board.

E.

Require a monthly individual status report.

Full Access
Question # 523

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Full Access
Question # 524

A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be

engaged in how the project will be executed.

How should the project manager proceed?

A.

Create an environment where the agreement is reached by a majority vote.

B.

Create an environment where the agreement is reached through discussion.

C.

Establish recurring brainstorming sessions to discuss project issues.

D.

Allow team members to contribute ideas in a stream-of-consciousness mode.

Full Access
Question # 525

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

A.

Solution architecture

B.

Product backlog

C.

Statement of work (SOW)

D.

Business case

Full Access
Question # 526

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

A.

Facilitate a supportive level of engagement for this stakeholder.

B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C.

Perform a qualitative risk analysis using a probability and impact matrix.

D.

Ensure the key information is accurate and monitor the situation as the project progresses.

Full Access
Question # 527

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?

A.

Update the communications management plan to satisfy the client's request

B.

Request the client to attend the daily meetings with the project team

C.

Encourage the client to interact with the protect collaboration platform

D.

Ask the product owner to frequently communicate with the stakeholders

Full Access
Question # 528

Drag the items on left side to the matching term within the correct project approach on the right side.

PMP question answer

Full Access
Question # 529

A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.

How should the project manager communicate with the local community?

A.

Social media

B.

Email

C.

Meetings

D.

Newspapers

Full Access
Question # 530

A project manager is leading an engineering project. The project manager must obtain some certifications before mass production, which is scheduled in 3 months. The certification process will require at least 6 months.

What should the project manager do next?

A.

Discuss extending the mass production timeline by 3 months with the project sponsor.

B.

Meet with senior management to discuss the possibility of an extension to the project timeline.

C.

Engage a consultant to shorten the certification process to meet the schedule requirement.

D.

Assess and evaluate the certification process and understand the best and worst case scenarios.

Full Access
Question # 531

During the execution of a project, a key stakeholder complains to the project manager about recent communications.

The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.

What should the project manager do?

A.

Explain to the key stakeholder the way in which the project team communicates information.

B.

Ask the project sponsor to hold a meeting with the key stakeholder to ensure that the stakeholder is engaged in the project.

C.

Send relevant information to all key stakeholders simultaneously to ensure consistent communication.

D.

Update the communications management plan to fulfill the key stakeholder's expectations about relevant information.

Full Access
Question # 532

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

A.

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.

B.

Delay developing the indirect tax module until the tax regulation comes into effect.

C.

Assess the impact of the risk with an expert and prioritize further outcomes with the client.

D.

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.

Full Access
Question # 533

A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.

What should the project manager do first?

A.

Evaluate the cost of the additional requested work.

B.

Evaluate the impact and submit a change request.

C.

Discuss the requested change with the sponsor.

D.

Discuss the requested change with the team.

Full Access
Question # 534

A company routinely outsources resources for specific core activities. Due to a sudden, unforeseen risk, all of the team members are needed to work remotely, including the outsourced ones.

How can the project manager address this challenge to assure outsourced vendors deliver?

A.

Review the coordination and communication costs with the supplier.

B.

Develop a new strategy for communication and management of resources.

C.

Review the risk management plan for the mitigation activities.

D.

Submit a change request to increase the contingency budget.

Full Access
Question # 535

A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.

What should the project manager do next?

A.

Modify the PMO template to include the information.

B.

Contact the senior manager and discuss their needs.

C.

Give the senior manager access to the product backlog.

D.

Organize a review of the kanban board with the manager.

Full Access
Question # 536

A company just started managing a project using an agile approach Due to this change, the general manager is worried about the scope definition process for upcoming projects What should the project manager do to ensure the project scope is completely defined?

A.

Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations

B.

Meet with the general manager and convince them to return to using predictive approaches to avoid any risk

C.

Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements

D.

Ask the general manager to review every requirement to ensure an projects will deliver the requested products

Full Access
Question # 537

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

A.

Report that the project has not fulfilled all the expected functionalities.

B.

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.

Communicate the benefit expectations and the action plan for the pending functionalities.

D.

Send an email with the monthly project progress to all relevant stakeholders.

Full Access
Question # 538

An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.

What should the project lead do?

A.

Ask that estimations be provided only by senior developers.

B.

Allocate more time for estimation in the sprint planning.

C.

Review and update the estimations in the daily standup.

D.

Recommend a different estimation method in the retrospective.

Full Access
Question # 539

A project manager is leading a project with strict time constraints. In team meetings, one of the team members is always silent. The project manager determines that this team member is not knowledgeable about the technology solution. The project manager is concerned that this problem will impact productivity.

What should the project manager do?

A.

Assign an experienced team member to work with this member on a daily basis in order to become knowledgeable about the technology.

B.

Arrange formal training for this member to gain sufficient knowledge to reduce the impact on team performance.

C.

Let this team member understand the urgency and encourage them to spend extra time to become knowledgeable about the technology.

D.

Let the team lead the meeting discussions so that every member has a chance to prepare and speak up.

Full Access
Question # 540

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?

A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.

B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.

C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.

D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.

Full Access
Question # 541

A project manager is working on a project to transform the service delivery model in the organization. As part of the scope, this project includes diverse elements that have been well defined by the product owner. The team has expressed that the scope is not clearly defined.

How should the project manager address this situation?

A.

Distribute the release plan among the team members.

B.

Ask the team members to focus only on their assignments.

C.

Ask the product owner to clarify the project's vision with the team.

D.

Meet with the product owner to validate the backlog prioritization.

Full Access
Question # 542

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Full Access
Question # 543

A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of

sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.

What should the project manager do?

A.

Introduce a float.

B.

Adjust the budget.

C.

Adjust the project time line.

D.

Fast track the project.

Full Access
Question # 544

A project manager has been assigned to lead a project with limited funding and resources. During the requirements brainstorming session, several stakeholders request a long list of requirements for a new project, which exceeds the budget.

What should the project manager do first?

A.

Host a requirements workshop and ask the stakeholders to prioritize the requirements based on critical needs.

B.

Review the requirements and determine which of them can be removed, then advise the stakeholders of the changes.

C.

Meet with the sponsor to obtain their feedback regarding critical requirements in the view of senior management.

D.

Reach out to the sponsor and request additional budget and capacity in order to complete the project.

Full Access
Question # 545

A project has recently completed its production go-live, meeting the project's completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.

How should the project manager address the customer's requests?

A.

Inform the customer that the project scope is completed and that further enhancements will require the initiation of a new project.

B.

Tell the client that any extra work will require new scoping and pricing before the team can start additional enhancements.

C.

Adjust the project completion requirements to the proposed enhancements and inform the project team of the additional work.

D.

Explain to the customer that the project has been completed and enhancements will follow the change management process.

Full Access
Question # 546

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

A.

Submit a change request and allocate the budget and resources needed for execution.

B.

Confirm that the budget and resources are available to execute the work request.

C.

Check the alternative resources available in the organization for the request.

D.

Evaluate the nature of the request and plan communication accordingly.

Full Access
Question # 547

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Full Access
Question # 548

A project management office (PMO) director finds that the project managers leading software development projects are not consistently seeking approval from other division leaders in cybersecurity and operations before deploying code into production. The PMO director asks the project manager to develop a solution for this issue.

What should the project manager do to fix this problem?

A.

Establish a daily scrum meeting and invite division leaders to attend so they can be aware of upcoming code releases.

B.

Provide division leaders with a teleconference phone number to call if they have concerns after code is deployed into production.

C.

Create a new policy requiring project managers to email division leaders before deploying code into production.

D.

Launch an enterprise governance structure comprised of division leaders to establish policies for code releases.

Full Access
Question # 549

A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.

Which approach should the project manager use as a servant leader?

A.

Ask stakeholders to find and self-fund education about this new technology.

B.

Allocate resources to provide training about the new technology to the stakeholders.

C.

Contact the project sponsor to get those stakeholders removed from the project.

D.

Escalate the issue with upper management to find a novel solution for this situation.

Full Access
Question # 550

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product

owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer

features or low quality.

What should the project leader have done to ensure success?

A.

Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery

B.

Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints

C.

Asked the team to create an impediment log and keep it updated for use in the next sprint planning

D.

Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

Full Access
Question # 551

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

A.

Reprioritize the backlog based on value and cost of delay divided by duration.

B.

Switch to a predictive approach to prevent any further delays to completion.

C.

Reprioritize the backlog based on story size and competence availability.

D.

Remove low-value items from the backlog to compensate for the higher cost.

Full Access
Question # 552

A vice president has asked a project manager to support a new urgent project and has informed team members that the project will start soon. The CEO of the company has not yet approved the project to start. The vice president is concerned that the project will not be approved by the CEO on time.

What should the project manager do next?

A.

Ask the vice president to approve the project charter to kick off the project

B.

Ask the vice president to define who will be the product owner for the project

C.

Investigate if the value and benefits of the project are identified

D.

Start working on the project immediately and determine the scope later

Full Access
Question # 553

A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.

What should the project manager do?

A.

Ask the project team to meet and document why the stakeholder's approach is incorrect.

B.

Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.

C.

Discuss the issue with the project team during a project status meeting and request that they change the approach.

D.

Ask the project sponsor to meet with the project team and key stakeholder to discuss the approach.

Full Access
Question # 554

A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

A.

Organize the team members into several kick-off sessions based on technology type.

B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.

C.

Ask the human resources (HR) department to arrange interview meetings to select the team.

D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.

Full Access
Question # 555

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.

What should the project manager do next?

A.

Update the lessons learned report and the risk log to reflect that this risk has materialized.

B.

Revise the project management plan and move the task to a time when the technical resource will be available.

C.

Consult the risk register for an appropriate planned risk response and implement.

D.

Review the business requirement with stakeholders and exclude the task assigned to the technical resource.

Full Access
Question # 556

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two)

A.

Discuss the issue with the external supplier's authority.

B.

Review the lessons learned from similar past projects.

C.

Gather additional information and estimate the impact.

D.

Update the risk log and bring this up in the meeting with the client.

E.

Wait for the client to raise a concern and collect more information.

Full Access
Question # 557

A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.

What should the project manager do to address the issue?

A.

Onboard a new project team member who has testing skills.

B.

Provide training to the entire team so they all will be able to perform tests.

C.

Support the team to identify an approach to resolve the problem.

D.

Ask the development team to slow down so the testers can catch up.

Full Access
Question # 558

The project manager of a globally dispersed team evaluates the organization's current virtual engagement tools and strategies. A couple of the remote team members are not participating effectively in virtual meetings.

Which action should the project manager take to improve remote engagement?

A.

Implement a new suite of collaboration tools to provide various communication options for the team.

B.

Organize an in-person, team-building event to improve team engagement and communication.

C.

Schedule one-on-one meetings with the team members to understand their specific needs and challenges.

D.

Survey all team members to identify common issues with virtual engagement and address them systematically.

Full Access
Question # 559

A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?

A.

Reject the request as being too late and leading to major scope creep.

B.

Submit the request to the change control board (CCB) for a decision.

C.

Negotiate with the project sponsor on the possible alternatives.

D.

Determine the possible impact of this change on all aspects of the project.

Full Access
Question # 560

A project team is working on a company restructure that involves team member rotation. There is a concern about how to execute the project within the schedule based on all of the new team members.

What should the project manager do?

A.

Discuss the issue with the project sponsor and advise that the project will probably be delayed.

B.

Advise the new team that the schedule cannot be changed and encourage them to complete the project.

C.

Set up a team alignment session to discuss the remaining work and contract with the team.

D.

Ask the team to analyze the impact and develop a new schedule for a project change request.

Full Access
Question # 561

An organization with a new project management office (PMO) team is now undergoing a restructuring. Additionally, there is a lack of communication from the PMO to the team members.

How should the project manager handle this situation?

A.

Meet the PMO team and explain the importance of communicating with the team members for project success.

B.

Request the PMO team share updates on the restructuring with the team members on an immediate basis.

C.

Set up a meeting with the PMO and project team to discuss and clarify questions related to restructuring.

D.

Inform the team that despite the new PMO and restructuring, the team will not change.

Full Access
Question # 562

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

A.

Inform team B of the dependency and ensure that the deliverable is planned.

B.

Make team Aa part of team B and ensure that the deliverable is ready.

C.

Request team B to immediately start this activity and deliver to team A.

D.

Ask team B to focus on their backlog and deliver based on their priority,

Full Access
Question # 563

A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that

there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.

What should the project manager do?

A.

Refer to the configuration management knowledge base for similar projects delivered in the past.

B.

Arrange for a workshop with the customer to understand the business values expected from the outcomes.

C.

Include a representative from the customer to work collaboratively with the team.

D.

Acknowledge that the current team needs improvement and hire more qualified team members.

Full Access
Question # 564

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?

A.

Ask the stakeholders to develop all of the project artifacts so the project team can continue their scheduled activities.

B.

Create the project management plans with the project team and share the documents with the stakeholders.

C.

Continue working on scheduled tasks to avoid delaying the project and leave the development of project artifacts for later.

D.

Adapt the project management plans and documents from previous executed projects in order to save time.

Full Access
Question # 565

An organization that embraced agile a couple of years ago is looking for a more efficient way to ensure that the increments produced in each sprint meet the end users’ quality requirements. What should the project lead recommend?

A.

Develop a more comprehensive template for the definition of done (DoD).

B.

Increase the percentage allocated for testing each backlog item.

C.

Organize more frequent sprint reviews with a broader audience.

D.

Establish a quality assurance (QA) team separate from the development team.

Full Access
Question # 566

A project manager is reviewing a draft of the project charter with key stakeholders. During the meeting, a conflict occurs between the sponsor and the product owner.

How should the project manager deal with the situation?

A.

Postpone the meeting and invite a subject matter expert (SME) to join the next meeting.

B.

Continue the meeting and ask the project sponsor and product owner to take their discussion offline.

C.

Postpone the meeting and ask the project sponsor and product owner to take their discussion offline.

D.

Continue the meeting and use facilitation techniques to improve communication within the team.

Full Access
Question # 567

A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will

take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6

months.

What should the project manager do to align stakeholders’ needs and expectations?

A.

Work with the stakeholders to create a prioritized backlog and release a roadmap.

B.

Modify the requirements to those that can be completed in 6 months.

C.

Implement fast-tracking and crashing activities to complete the project in 6 months.

D.

Include all stakeholders in daily scrum meetings to keep them informed.

Full Access
Question # 568

A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.

What should the project manager have done to prevent this?

A.

Deployed to production after the first iteration

B.

Reviewed the compliance requirements with stakeholders

C.

Planned smaller iterations to review the results more often

D.

Implemented the authorization in the first iteration

Full Access
Question # 569

A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not

shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.

What is the root cause of this issue?

A.

Lack of team member training on documentation planning

B.

Improper assignment of tasks to team member pairings

C.

Incorrect communication techniques applied during implementation

D.

Team cohesiveness was lost because team members worked in pairs

Full Access
Question # 570

After signing an agreement with a vendor, the project manager notices that the vendor is continuously asking for changes on the procurement statement of work (SOW).

These changes would improve the project outcome.

What should the project manager do next?

A.

Conduct an audit on the procurement process and inform the vendor about the audit's observations.

B.

Assess the situation as an opportunity for improvement and perform a risk analysis.

C.

Consult the list of selected vendors for the bid and evaluate a possible change of vendor.

D.

Revise the procurement control process to avoid undesired changes that might affect the schedule.

Full Access
Question # 571

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

A.

Refuse to let the team proceed with the work based on their decision.

B.

Take the technical team lead aside and try to persuade them to change their vote.

C.

Note the reasons for the disagreement and let the team proceed.

D.

Set up a meeting with the project champion and ask them to intervene.

Full Access
Question # 572

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?

A.

Set up a meeting with the product owner to discuss the stakeholder's concern.

B.

Discuss this with the team and review the project requirements documentation.

C.

Set up a meeting with the sponsor to discuss the details of the deliverable.

D.

Discuss this with the team and put the stakeholder's concern in the issue log.

Full Access
Question # 573

Anew engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the

project manager before acting.

What should the project manager do?

A.

Obtain related training for the new team member.

B.

Determine the appropriate level of decision-making authority and empower the engineer.

C.

Make all of the decisions for the engineer in order to keep the workflow on track.

D.

Replace the resource with an experienced engineer.

Full Access
Question # 574

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

Full Access
Question # 575

A project manager works in a matrix organization and is managing an internal software development project that is intended to reduce conflicts in the company's internal tracking system. During development, the project manager is informed that the software has to account for an unexpected change to government accounting requirements. The development team was able to make the change with no additional cost; however, the project manager notices that the testing costs are beginning

to exceed the testing budget.

What should the project manager do?

A.

Update the basis of estimates and the cost management plan to track the additional funding required for testing.

B.

Ask the project sponsor to allocate funds from the contingency reserve to fund the additional testing.

C.

Submit a change request to the cost baseline through the governance process to fund the additional testing.

D.

Conduct a cost-benefit analysis to determine if the funds can be reallocated from the development team.

Full Access
Question # 576

A project team has been working together for about 2 years. One of the team members has consistently shown high performance and stood out among their peers during the execution of the project.

How should the project manager recognize high performance?

A.

Thank the team member privately to avoid conflict among the team members.

B.

Acknowledge the high-performing team member in the next team meeting.

C.

Choose a reward for the team member that aligns with their personal goals.

D.

Ask the sponsor to approve a bonus for the high-performing team member.

Full Access
Question # 577

A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members

available who are qualified to complete the work.

What should the project manager do?

A.

Assess the team member's development requirements and arrange for the team member to receive training.

B.

Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.

C.

Work with the functional manager to determine an incentive for the team member to complete the project.

D.

Request a substitute for the team member with a new resource who is more skilled in system development work.

Full Access
Question # 578

The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.

What should the project manager do?

A.

Help engineer A to become familiar with this new role and ensure engineer B stays motivated.

B.

Promote engineer B instead since the project manager has the authority to make this decision.

C.

Request management approval that engineer B will be promoted if engineer A fails in this role.

D.

Coach engineer B to be prepared to perform this role if and when engineer A fails.

Full Access
Question # 579

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.

B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.

C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.

D.

Discuss the recommendations with the test manager and request better quality control.

Full Access
Question # 580

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

A.

Log the technical design delay as a risk in the project risk log.

B.

Set up a steering committee session to review the project delay.

C.

Continue with the approved design so that the project is not delayed.

D.

Ask the steering committee to approve a new technical design.

Full Access
Question # 581

An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.

What should the project manager do to help the project team?

A.

Reschedule the project until the local travel restrictions are lifted.

B.

Schedule virtual sessions with the specialist to guide the team in completing the activity.

C.

Seek additional budget to train the project team on the required skill set.

D.

Refer to the organization's lessons learned repository and find an alternative solution.

Full Access
Question # 582

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.

What should the project manager do next?

A.

Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.

B.

Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.

C.

Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.

D.

Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.

Full Access
Question # 583

In a product development project, the project manager is constantly receiving complaints from stakeholders about functionalities being delivered, but not required by the business departments. The project sponsor wants to know if the project resources are being used effectively.

What should the project manager have done to avoid delivering work that is not adding value to the business?

A.

Document the stakeholders' needs, review them during the retrospective, and create improvement plans.

B.

Encourage the product owner to meet with the stakeholders and create a product backlog based on their needs.

C.

Ask the stakeholders to document their complaints in change requests.

D.

Define a product scope and ask the stakeholders to not deviate from it.

Full Access
Question # 584

The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.

What should the project manager do first?

A.

Lead a root cause analysis workshop with the design team to identify the failures that led to the decision to add a component that was not compatible with the production line.

B.

Meet with the operations manager to explain the background for the change and understand the operation manager's concerns about the change.

C.

Escalate the issue to the project sponsor, as the decision to add the component brings many benefits even though it will be disruptive to the production line.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the project may deliver late and over budget due to manufacturing difficulties.

Full Access
Question # 585

A project manager was suddenly asked to take over an ongoing project without any handover. During the first meeting, the project sponsor raised concerns about whether the project was on track to deliver the intended benefits.

What should the new project manager do first?

A.

Review the business case to gather information about the project.

B.

Initiate a rebaselining of the project based on the project sponsor's concerns.

C.

Discuss the items in the requirements register with the project team.

D.

Meet with the project stakeholders to understand the project sponsor's concerns.

Full Access
Question # 586

Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time.

What should the project manager do?

A.

Reschedule on-site training to online sessions.

B.

Create a risk and assign remediation actions.

C.

Cancel all of the on-site training sessions.

D.

Document the project issue and provide options.

Full Access
Question # 587

A project manager is managing a project that requires specialized architecture services. This project was identified as a high risk for the

organization. The project manager works with an external architect who is highly specialized. However, the architect will soon resign because they

accepted an offer from another firm.

What should the project manager do next?

A.

Discuss this with the project team, assess the impact, and decide on the appropriate actions to follow.

B.

Ask the architect for the contact details for their new employer and call their account manager.

C.

Call the account manager and ask them to retain the expert by offering them an incentive.

D.

Escalate the issue to the procurement department and ask them to discuss this with the vendor firm.

Full Access
Question # 588

A multinational company is rolling out a new software platform within its subsidiaries. However, the distributed project team struggles to meet regularly. As a result, the project milestones are not being achieved.

What should the project manager do first?

A.

Inform the project sponsor and request additional team members to crash the project schedule to meet the target

B.

Introduce an award system to promote member participation and establish some competition between the subteams

C.

Evaluate the effectiveness of the virtual teams and support them with the necessary technology and equipment

D.

Propose to roll out the new software in one subsidiary and then use the lessons learned to improve the project

Full Access
Question # 589

An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel

confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product

increment with the product owner now.

What should the project manager do to mitigate this risk?

A.

Extend the sprint end date in anticipation of feedback from the product owner that will require extra work.

B.

Schedule an additional interim demo with the product owner.

C.

Address the issue as part of the retrospective.

D.

Ask the team to work overtime toward the end of the sprint to meet the original sprint end date.

Full Access
Question # 590

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

A.

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.

B.

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.

C.

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.

D.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.

Full Access
Question # 591

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

A.

Explain to the team that open discussions are needed but remind the team to follow the ground rules.

B.

Ask this member to only discuss the current topic to achieve team efficiency.

C.

Ask the team to accept the input from this particular member as their input may be useful.

D.

Allow the self-organized team to discuss the situation among themselves and come to a resolution.

Full Access
Question # 592

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in

a couple of months. The licensing cost is significant.

What should the project manager do next?

A.

Evaluate the impact of nonrenewal of the license.

B.

Escalate the licensing issue to the product owner.

C.

Add a spike to the backlog for an alternative design.

D.

Raise a change request to secure the renewal.

Full Access
Question # 593

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns

that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project.

Which action should the project manager take to procure the vehicles?

A.

Ask the technical team to revise the requirements, even if it requires extra budget.

B.

Arrange a meeting with the client to request additional time to find a new supplier.

C.

Review the existing service contracts to find an option to help procure the vehicles.

D.

Procure the vehicles from another supplier and report the change to the change control board (CCB) later.

Full Access
Question # 594

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers

arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.

Inform the relevant stakeholders.

B.

Inform the project team only.

C.

Inform the product owner.

D.

Inform the project sponsor.

Full Access
Question # 595

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

A.

Ensure the client representative is involved in the estimation.

B.

Review the completion costs of similar projects.

C.

Ensure that a 20% contingency is included in the estimation.

D.

Review the lessons learned from similar projects.

Full Access
Question # 596

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?

A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.

B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.

C.

Invite the PMO manager to the daily standup with the project team and product owner.

D.

Send weekly reports to all stakeholders, including the project team and the product owner.

Full Access
Question # 597

Drag the communication event on the left to the main subject discussed during the event on the right.

PMP question answer

Full Access
Question # 598

Knowledge sharing has been a key priority for a complex technological project with a large number of team members. During the project

execution phase, the project manager receives numerous complaints from all team members that they are overloaded with knowledge-sharing

emails, which contain useful information but are unmanageable due to the high volume.

What should the project manager do to solve this problem?

A.

Establish an unofficial communications method for the team to share knowledge and lessons learned.

B.

Establish a pull communications method to access knowledge repositories and lessons learned.

C.

Establish an interactive communications method between stakeholders to share knowledge and lessons learned.

D.

Establish a push communications method for the team to share knowledge and lessons learned.

Full Access
Question # 599

An agile team has released the second version of its product, but the feedback is that the software has many bugs that compromise the user experience. What should the

project manager do?

A.

Facilitate the next retrospective meeting, focusing the team on analyzing root causes and proposing solutions.

B.

Closely evaluate the skill set of the team, looking for technical gaps that need to be filed in order to improve quality.

C.

Hire an external consultancy firm to focus on testing and quality control to avoid the issue in the future.

D.

Propose an internal program that offers incentives for the team members who find and fix bugs.

Full Access
Question # 600

A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the

appropriate stakeholder participation and involvement level required for successful project delivery.

What should the project manager do?

A.

Communicate with the stakeholders to find a solution.

B.

Review the issue log with the project stakeholders.

C.

Evaluate the stakeholder engagement assessment matrix.

D.

Perform a stakeholder assumption and constraint analysis.

Full Access
Question # 601

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

A.

Add time reserve in the project schedule to allow extra time for the stakeholders to make decisions.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all unavailable stakeholders informed.

D.

Schedule meetings with all of the stakeholders to make business decisions when needed.

Full Access
Question # 602

A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market.

What should the project manager do to move forward with the project?

A.

Continue building the center as the farmers' group does not need to be consulted.

B.

Document a risk related to the impact that the farmers' group could bring to the project.

C.

Request that the project sponsor discuss compensation with the farmers' group for the lost business.

D.

Discuss the project objectives with all stakeholders, including the farmers' group, and review their requirements.

Full Access
Question # 603

An organization embarking on a significant transformation initiated a project to improve and document business processes. One of the objectives of the project is to implement agile project delivery.

What is the main reason for adopting agile?

A.

Projects will be completed faster, saving time and money.

B.

Projects will deliver early and use value based on priority.

C.

Projects will be delivered with very low risk to the organization.

D.

Projects will be delivered with significant cost savings.

Full Access
Question # 604

A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change

in project scope.

How should the project manager respond to this requirement?

A.

Proceed with the existing company governance policy.

B.

Perform an analysis to assess the impact on the project.

C.

Directly comply with the financial regulations.

D.

Escalate the issue to upper management and let them decide.

Full Access
Question # 605

A project for a financial organization is in the proposal phase for the selection of a software tool. There have been conflicting opinions on the software that was ranked in the selection. After analyzing the issue, the project manager realizes that two out of the eight teams have concerns about the tool's scalability to support their business needs.

How should the project manager resolve this conflict and reach a consensus?

A.

Escalate this to senior management and ensure that the team's acceptance is achieved.

B.

Communicate to the two teams that the tool has won per the selection process and they need to accept the outcome.

C.

Ignore the conflict as the tool is selected per the proposal guidelines and the project is complete.

D.

Discuss the outcome of the proposal process and the ranking, then influence the team for acceptance.

Full Access
Question # 606

A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts

with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high

performer, the project goals may be negatively impacted if they leave the team.

What should the project manager do in this situation?

A.

Meet with the developer and ask them to be respectful with the other team members and work together as a team.

B.

Meet with the team members and developer individually to understand the situation and build an action plan accordingly.

C.

Collect the team's feedback and send it to human resources (HR) to resolve the conflict.

D.

Arrange a team-building training session and require all of the team members to attend.

Full Access
Question # 607

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office

(PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?

A.

Engage key stakeholders to complete and deliver lessons learned.

B.

Select the same stakeholders for the next project to avoid doing knowledge transfer.

C.

Present the project achievements and delegate knowledge transfer to the steering committee.

D.

Request the PMO to manage the lessons learned repository.

Full Access
Question # 608

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

Full Access
Question # 609

A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.

Which delivery approach should the project manager recommend?

A.

An adaptive approach with clearly defined user stories.

B.

A predictive approach with an experienced project team.

C.

A predictive approach with clear acceptance criteria.

D.

An adaptive approach with loosely defined large epics.

Full Access
Question # 610

The scope of a project is to replace the street signs within a 10-km radius. The client does not want to sign the project closure report if the radius

is not extended by 1 km, to be aligned with the council's development plan.

What should the project manager do?

A.

Delay the approval and ask the project sponsor for additional funding.

B.

Contact the council and ask for their approval to extend the scope of the project.

C.

Initiate a new project and discuss the request because it came in too late.

D.

Obtain formal acceptance for the completed work and submit a change request.

Full Access
Question # 611

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Full Access
Question # 612

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Full Access