Weekend Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

PMP PDF

$119.7

$399

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PMP PDF + Testing Engine

$179.7

$599

3 Months Free Update

  • Exam Name: Project Management Professional (2025 Version)
  • Last Update: Jul 18, 2025
  • Questions and Answers: 1704
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PMP Engine

$134.7

$449

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

PMP Practice Exam Questions with Answers Project Management Professional (2025 Version) Certification

Question # 6

A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available

time to support the project, but was not planned to be involved in the current agile iteration.

What should the project manager do?

A.

Bring the SME on board immediately and discuss the implications later.

B.

Ask the existing team members to collaborate with the SME and complete the activity.

C.

Ask the SME to complete all of the necessary changes, which will save time.

D.

Direct the team member to ignore the SME's changes as they were not planned.

Full Access
Question # 7

In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.

What should the project manager do?

  • Update the issue log and refer to the resource management plan to address the situation.
  • Ask the team for extra work to fulfill the project commitment.
  • Reduce the scope of the project and inform stakeholders.
A.

Ask the sponsor for an experienced team member in the company to help the project team.

Full Access
Question # 8

A compliance strategy was created during the planning phase of a project During execution, the project manager left the organization and another project manager was assigned to the team

What should the project manager do first to ensure the project is compliant?

A.

Meet with the team to discuss compliance concerns

B.

Review the organizational process assets (OPAs) for compliance topics

C.

Review the compliance strategy and version history

D.

Meet with the project sponsor to discuss their compliance concerns

Full Access
Question # 9

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog

B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints

C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration

D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks

Full Access
Question # 10

A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the

project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years’

experience as an agile practitioner working as a scrum master.

What should the project manager do at the start of the project?

A.

Collaborate with the development team to help the project sponsor acquire the relevant skills.

B.

Assume the product owner role until the project sponsor is ready to take over the product owner role.

C.

Delay the build of the system until the project sponsor is ready to take over the product owner role.

D.

Work with and assist the project sponsor in building and prioritizing the product backlog.

Full Access
Question # 11

A project manager is working on a large IT project. During a review for one of the deliverables, a stakeholder raised a concern about the final product.

What should the project manager do first?

A.

Set up a meeting with the product owner to discuss the stakeholder's concern.

B.

Discuss this with the team and review the project requirements documentation.

C.

Set up a meeting with the sponsor to discuss the details of the deliverable.

D.

Discuss this with the team and put the stakeholder's concern in the issue log.

Full Access
Question # 12

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

A.

Issue a change request to remove items from the scope of work and keep the project on schedule.

B.

Issue a change request to include the additional scope, and track the completion of the work items.

C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.

D.

Arrange to pass the cost to the operational area since the customer will benefit.

Full Access
Question # 13

A project learn member identified a defect in the initial solution design for a project The stakeholders are not sure whether to deploy the system or not. What should the project manager do?

A.

Propose a solution redesign for the project

B.

Perform risk analysis against the issue.

C.

Revise the project's quality control measurements

D.

Develop a mitigation based on the solution design

Full Access
Question # 14

A specialized team member has just received news that they must leave the office for several weeks They have approximately two workdays until they will leave and then they will become unavailable through any communication channels. There is a key deadline approaching

What should the agile project manager do?

A.

Ask the team member to complete as much as they can now.

B.

Ask the team member to work with their peers to knowledge share

C.

Ask the team member to identify their specialist tasks

D.

Ask the team member to host a special team meeting.

Full Access
Question # 15

A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.

B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.

C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.

D.

Invite the customer to join the regular sprint planning sessions to better understand the project's progress.

Full Access
Question # 16

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

A.

Have a discussion with the sales team to find a solution to the issue

B.

Validate the reason and add it as an issue in the issue log

C.

Direct the sales team to speak with accounting to resolve the issue

D.

Escalate the issue to the functional manager

Full Access
Question # 17

The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.

What should the project leader do?

A.

Report the impediment to the functional manager.

B.

Identify the impediment and associated risks at the daily standup.

C.

Escalate the impediment and associated risks to the business sponsor.

D.

Identify the impediment during the retrospective

Full Access
Question # 18

An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the

project manager do to help improve the team's collaboration approach?

A.

Meet with the human resources (HR) department to ask for team support.

B.

Follow the process of the most successful team in the organization.

C.

Compare the team's velocity with other teams in the organization.

D.

Focus on the team's engagement during the next retrospective meeting.

Full Access
Question # 19

A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.

Match the roles for the team on the left to their corresponding responsibilities on the right.

PMP question answer

Full Access
Question # 20

In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress

What should the project manager do first?

A.

Revise the project schedule

B.

Present the project to the stakeholder

C.

Inform the client about the change

D.

Update the risk register with a new risk

Full Access
Question # 21

A project manager is leading an automation project. The project team is colocated

and includes people from both the technical and business units. The project manager

discovers that personal differences and work styles are affecting the project negatively.

How should the project manager address this?

A.

Develop a schedule that ensures people with personal differences work separately.

B.

Use an approach to the project that does not involve colocation.

C.

Meet with the team and agree on expectations from team members.

D.

Invite the functional managers of the different units to address their personal differences.

Full Access
Question # 22

A project manager for a technology project is informed by the cybersecurity team that

there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.

What should the project manager direct the team to do?

A.

Update the scope management plan to track the new government requirements.

B.

Accept the cybersecurity team’s request as the security of the company is at risk of

being noncompliant.

C.

Ask the project sponsor to increase funds in the contingency reserve as a risk mitigation.

D.

Request a change through the change control process to manage the new cybersecurity

requirements.

Full Access
Question # 23

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

A.

Autocratic decision making

B.

Expert judgment

C.

Context diagram

D.

Change control tools

Full Access
Question # 24

On a transformational project, the project manager is confronted with resistance

from the stakeholders. To overcome this and gain acceptance of the change, what should

the project manager do first?

A.

Escalate the issue to the project sponsor.

B.

Review the stakeholder engagement plan.

C.

Update the issue log.

D.

Neutralize the negative stakeholders.

Full Access
Question # 25

During a project planning meeting, the customer is not sure how to build a brand new product and is worried about extra costs and work.

The customer is asking the project manager for guidance.

What should the project manager do?

A.

Wait to start the project execution phase until all requirements and acceptance criteria are clear.

B.

Ask the customer to include all of the requirements in the project charter to officially start the project planning phase.

C.

Schedule a brainstorming session and select the top ten most important requirements.

D.

In the planning meeting, focus on releasing a minimum viable product (MVP) quickly and getting feedback from the end users.

Full Access
Question # 26

An organization initiated a project in a complex program. The project lead notices that the team is demotivated because the current project framework implemented by the project management office (PMO) is not compatible with agile delivery

What should the project lead do?

A.

Escalate the problem to the product owner.

B.

Ask the PMO to review the framework

C.

Request the PMO to define a new framework.

D.

Plan a brainstorming session with the project team

Full Access
Question # 27

A project manager receives a request for proposal (RFP) from a client. The client

is very clear about the requirements. A requirements analysis must be done in the first

month of the project, and the client wants to see a demo of the work completed every two

weeks.

What project approach should the project manager use?

A.

Iterative for the requirements analysis and delivery phases of the project

B.

Agile for all of the phases of the project, including the requirements analysis and delivery

C.

Predictive for the requirements analysis and agile for delivery of the project

D.

Predictive for the requirements analysis and delivery phases of the project

Full Access
Question # 28

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

A.

Ensured reports with significant information were not included in the communications management plan

B.

Defined the appropriate recipients for the report in the communications management plan

C.

Included noncompliance punishment measures in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Full Access
Question # 29

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

Full Access
Question # 30

A project team has transitioned to full-time remote working. The project manager

started noticing that some team members have not been completing their assigned tasks by

the planned dates despite reminders during weekly team meetings. This has the potential for

delaying the project delivery.

How should the project manager resolve this situation?

A.

Communicate the delivery dates twice a week to the team members to ensure timely

delivery.

B.

Set up review sessions with each of the team members to identify the root cause of

delays.

C.

Mentor the team members to work in a remote work environment to ensure

productivity.

D.

Talk to the resource managers regarding the delay and request additional resources

Full Access
Question # 31

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

A.

Forming

B.

Mourning

C.

Storming

D.

Norming

Full Access
Question # 32

The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.

What should the project manager do?

A.

Support the product owner's decision and seek better alignment with this stakeholder in order to avoid this type of issue in the future

B.

Coach the team on the decision-making process, assuming a risk-averse strategy towards product releasing

C.

Assume the responsibility for product releases making the final call on when something is ready for customer launch

D.

Escalate the issue to the sponsor questioning the authority of the key stakeholder regarding the product launch decision

Full Access
Question # 33

An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?

A.

Plan an outdoor activity tor the team to get to know each other

B.

Ask the team to review agile protect management approaches.

C.

Ask the human resources department for an experienced agile team

D.

Conduct a meeting to help the team define the team charter

Full Access
Question # 34

A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of

the team. What should the project manager do?

A.

Move the task to the next sprint.

B.

Ask the team member to bring up the concern in the next daily meeting.

C.

Send an email explaining the issue to all team members.

D.

Reassign the task to another team member.

Full Access
Question # 35

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?

A.

Planned all required training for the team during the onboarding process

B.

Identified all required skills after the kick-off of the project

C.

Identified all required skills during the planning of the project

D.

Asked the sponsor to identify all required skills during the planning of the project

Full Access
Question # 36

Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.

What tool should the project manager use to conduct meetings with the project team and clients?

A.

Use a third-party instant messaging tool.

B.

Use a password-enabled audio/video product,

C.

Use a popular social media platform.

D.

Use a collaborative electronic whiteboard,

Full Access
Question # 37

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME) The SME refuses to accept this rejection and does not want to continue the project without the change

What should the project manager have done to avoid this situation?

A.

Requested that the sponsor approved the change request first.

B.

Assessed the change's overall impact to the project before submission

C.

Ensured that the change request was aligned with the project scope

D.

Submitted the change request directly to the CCB

Full Access
Question # 38

A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.

How should the project manager proceed in order to complete the risk register?

A.

Cancel the meeting and create the risk register using the project documents.

B.

Continue the meeting and send the updated risk register to all stakeholders.

C.

Run the meeting and follow up with each one of the absent stakeholders to get their input.

D.

Escalate the issue of stakeholders not attending the meeting to the project sponsor.

Full Access
Question # 39

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half-yearly review of the project, the project manager raises serious concerns with

the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.

What should the project manager do?

A.

Propose to close the project because it no longer fits the business values of the organization.

B.

Calculate earned value (EV) because the project manager is forecasting a loss for this project in the yearly review.

C.

Calculate float on the project because it has severely affected the project's major critical path.

D.

Request additional resources from the business unit manager due to the project's complexity.

Full Access
Question # 40

A company is planning a digitization project. Which action should the project

manager take first when defining the project scope?

A.

Assess the current state process to define the scope of the digitization.

B.

Digitize the current state process exactly as defined.

C.

Redefine the current state process to scope the supporting software.

D.

Develop the software that will support the current state process.

Full Access
Question # 41

During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.

What should the project manager do first?

A.

Communicate the problem to the sponsor to force the key member to be maintained on the project.

B.

Initiate a change request and replace the key member as soon as possible.

C.

Explain to the company the importance of maintaining the key member on the project according to the vision of the project.

D.

Evaluate the impact of the key team member's removal from the project, look for alternatives, and submit a change request if required.

Full Access
Question # 42

A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.

What should the project manager do?

A.

Remind the team that their primary responsibility is software development.

B.

Add a user story to the product backlog to test the software product.

C.

Discuss the Option in the next daily standup meeting to finalize the decision.

D.

Recommend the option to the product owner for consideration.

Full Access
Question # 43

A project has come to the closing stage. The work is generally finished, and the project manager wants to commence the closure process for the project. What should the project manager ensure is in place prior to the closing process?

A.

The organizational process assets (OPAs) have been updated.

B.

The contractual deliverables of the project have been accepted.

C.

It The handover and deliverable acceptance have been completed.

D.

The lessons learned sessions have been conducted.

Full Access
Question # 44

An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story

What should the agile leader do1?

A.

Emphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint

B.

Ask the team to address this at the next sprint planning instead of at the retrospective

C.

Suggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance

D.

Work with the product owner to remove the story from the sprint because the points cannot be splits

Full Access
Question # 45

A company is transitioning their projects to utilize hybrid project management approaches While putting together their project team, the project manager discovers the requirements from the customer are unclear and also realizes that the team members are lacking critical technical stalls needed for project success. However the customer will not accept any changes to the requirements

What should the project manager do to resolve this issue?

A.

Submit a change request to adapt the objectives of the project to the current situation

B.

Ask the scrum master to refine the user stones to improve the team members' understanding

C.

Find and provide training to the project team members who do not have the required skills

D.

Extend the duration of standup meetings to include skill transference from trained to untrained members

Full Access
Question # 46

A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.

What should the project manager do?

A.

Assume the role of the product owner while the product owner gets familiar with the product.

B.

Schedule time to share insights with the new product owner about the product and project information.

C.

Work with the project management office (PMO) manager to generate an onboarding plan for the new product owner.

D.

Organize a team-building activity and ask the team to respect the opinions of the new product owner.

Full Access
Question # 47

A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.

What should the project manager do?

A.

Reject the risk because the team is not in agreement on escalating it

B.

Include the risk in the risk assessment and evaluate it with the team

C.

Accept the risk and immediately enter the risk into the risk register

D.

Discuss with the consultant to understand why the risk was escalated

Full Access
Question # 48

An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings

How should the project manager handle this'?

A.

Discuss the meeting delays with the director of operations and ask for support with the concerns.

B.

Review the operations manager's concerns and ensure these concerns are addressed

C.

Escalate the concerns to the project sponsor and discuss options to address them

D.

Include the operations manager's concerns in the risk register and assign actions to mitigate the risks.

Full Access
Question # 49

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

A.

Start with the end user documentation review with the customer and gather feedback

B.

Start with design of the prototype review with the customer and gather feedback

C.

Start with the product prototype development, review with the customer, and gather feedback

D.

Start with the product architecture review with the customer and gather feedback

Full Access
Question # 50

A project manager is leading a project that involves on-site and remote team members One task that was assigned to a team member in another country appears to be behind schedule When the project manager inquires about this, the team member claims that the task was completed and that this was reported to the team lead via a telephone conversation

What should the project manager do?

A.

Communicate the ground rules, principles and reporting methods to the project stakeholders

B.

Penalize the project team lead for not updating the project documentation properly.

C.

Review this issue with the team lead for possible ways to resolve this situation

D.

Issue guidance to the team member about reporting directly to the project manager

Full Access
Question # 51

As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the

project. How should the project manager resolve this?

A.

Escalate a schedule risk to the sponsor.

B.

Conduct team-building exercises.

C.

Stop the project and perform a team skill assessment.

D.

Make sure that the team has a full understanding of the scope.

Full Access
Question # 52

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

A.

Assign the tasks individually based on the role of the team member to ensure expertise on the subject.

B.

Encourage and assign the team to perform demos of their products or software with the customers

C.

Give the team autonomy to make their own decisions on how to perform the tasks.

D.

Encourage the team to keep the product owner involved when choosing ways to resolve the given task

Full Access
Question # 53

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

A.

Review and update the project schedule according to performance

B.

Review the schedule baseline and consider adopting a schedule performance indicator

C.

Develop a lime. cost, and scope tracking method exclusively for this project.

D.

Adopt a formal change management process for the project

Full Access
Question # 54

A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)

needs visibility of the regulatory constraints while maintaining a degree of flexibility.

Which tool can the project manager use?

A.

Use a burndown chart to provide transparency.

B.

Use a kanban board to increase accountability.

C.

Use a product backlog to manage changes.

D.

Use a burnup chart to provide transparency.

Full Access
Question # 55

A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable

What should the project manager do to resolve this?

A.

Meet with the stakeholder to discuss the impact of the deliverable

B.

Consider the stakeholder as a risk and evaluate possible solutions with the project team

C.

Improve communication with the stakeholder to obtain their assistance in the future

D.

Escalate to the project sponsor due to the political nature of the issue

Full Access
Question # 56

An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.

What should the project manager, who is responsible for this project, do to mitigate this risk?

A.

Ensure that the executive leadership team approves all scope that is being proposed by the multiple agile teams to avoid misalignment.

B.

Propose a governance model that empowers the teams while providing the necessary oversight to the executive leadership team.

C.

Propose a multilayered gate system based on risks and financial expenditures, involving the executive leadership team as needed.

D.

Assure the executive leadership team that the current governance model will not be affected by the agile approach.

Full Access
Question # 57

A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

PMP question answer

Full Access
Question # 58

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

A.

File a change request to make the customer billable for all extra costs incurred for the project.

B.

Ask the accounting department to forward all project expenses to the project manager's email.

C.

Monitor the budget for the project continually and anticipate any issues if possible.

D.

Ask the project resources to finish their assignments in less time than originally planned.

Full Access
Question # 59

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.

B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.

C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.

D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.

Full Access
Question # 60

Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.

What should the project manager do next to address this issue?

A.

Halt all processes until procurement and implementation of solutions are completed.

B.

Place a hold on activities until the team can resume the work on-site.

C.

Ask the team members to proceed independently while examining needs and alternatives.

D.

Obtain and implement the sponsor's recommendations for a solution.

Full Access
Question # 61

A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution

team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.

What should the project manager do next to deliver a reliable solution?

A.

Meet with the resources and agree that the more experienced resource's approach has proven to be effective in the past.

B.

Meet with each resource's functional manager and arrive at a common approach that is appropriate for the project's constraints.

C.

Meet with the entire project team and decide on a further course of action based on team consensus.

D.

Meet with the resources together and find common ground on viewpoints to compromise on an approach.

Full Access
Question # 62

A project manager is working with team members and customers who are operating in multiple countries. The team is working on implementing a new technology that includes ambiguities, uncertainties, and unknowns, both in terms of technology and of the end-user expectations for this solution.

What should the project manager do to keep the stakeholders engaged?

A.

Use email as a communication channel.

B.

Use feedback and decision-making tools.

C.

Use meetings as a communication channel.

D.

Use a shared collaboration platform.

Full Access
Question # 63

A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.

What should the project manager do?

A.

Discuss this with the project team and select the appropriate tools.

B.

Inform the project team to continue using the current tools.

C.

Implement the communication tools used by other project teams.

D.

Escalate the issue to the sponsor and ask them to decide.

Full Access
Question # 64

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?

A.

Ensure that the schedule is aligned with the vision and objectives.

B.

Escalate the compliance issue to the project management office (PMO).

C.

Congratulate the team and move on to the execution phase.

D.

Develop a new detailed schedule with the team and project sponsor.

Full Access
Question # 65

A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly

to ensure that the stakeholder is up to date on the project. However. the project manager has recently resigned and will not be meeting with the new project manager prior to

departure.

How should the project manager ensure that the new project manager continues to update this particular stakeholder?

A.

Update the communications management plan with specific information on stakeholder engagement.

B.

Update the stakeholder engagement plan with the specific communication needs for the stakeholder.

C.

Ensure that the project team has been provided guidance on the specific needs of this stakeholder.

D.

Ensure that the project documents contain specific instructions regarding the stakeholder.

Full Access
Question # 66

Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.

What should the project manager do next?

A.

Schedule a meeting between the team members to find a solution.

B.

Refer the team members to the project charter to resolve the conflict.

C.

Issue a new change request to evaluate this situation and communicate the result.

D.

Document the facts explained by the team members in the issue log.

Full Access
Question # 67

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project

execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.

What should the project manager have done to prevent this from happening?

A.

Ensured the stakeholder anticipated obstacles to achieving financial closure on the remaining funds.

B.

Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.

C.

Ensured the stakeholder who was providing additional funds remained interested in the project.

D.

Ensured the project team monitored and reviewed the project risk register periodically.

Full Access
Question # 68

During the execution phase, the project manager discovered that the deliverables

are not meeting the quality specifications requested by the main stakeholder. This has

caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost

performance index (CPI) from 1.5 to 1.1.

What action should the project manager take to mitigate the issue of the deliverables being

rejected during the next iteration?

A.

Submit a change request to prioritize resolutions for the quality issue to minimize the impact on the rest of the deliverables.

B.

Reinforce the definition of done (DoD) during sprint planning so that the team has a common understanding of expectations.

C.

Assure that the product backlog is properly prioritized to avoid dependencies that cause rejection.

D.

Create a dedicated sprint to complete all of the pending specifications from previous sprints.

Full Access
Question # 69

A junior team member escalates an issue to the project manager about another

member's interpersonal skills causing the team to be less effective.

What should the project manager do first?

A.

Have the team members resolve the issue on their own.

B.

Highlight the impact of their behavior and motivate the team member to make improvements.

C.

Gather information and find the root cause of the problem.

D.

Document the escalated issue and address it at the end of the project.

Full Access
Question # 70

A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay

Which three actions should the project manager take to encourage engagement? (Choose three)

A.

Require a written status report from all team members on a weekly basis

B.

Form a core group of team leads representing members from each country and encourage them to collaborate

C.

Ask team members to agree on a meeting time prior to setting up virtual meetings ' Set up a discussion board that allows team members to collaborate online at any time of the day

D.

Establish virtual one-on-one's with team members to address any issues and/or concerns privately

Full Access
Question # 71

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.

B.

Review the historical information and make the decision based on the return on

investment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with these

processes.

D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.

Full Access
Question # 72

A project is nearing completion The contingency time has been consumed To ensure that the final deliverables are achieved fhin budget, the project manager has asked the team to follow a rigorous process This Is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

A.

Crash the project schedule and ask project team members to work overtime to meet the new timeline

B.

Motivate project team members by offering incentives to complete the project on time

C.

Describe to the team members how specific tools and techniques can be used to finish on time

D.

Convince team members to use a specific methodology to complete the project on time

Full Access
Question # 73

Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.

What should the project manager do?

A.

Ask the contractor to solve this problem because this is a contractual obligation.

B.

Terminate the contract and initiate a new one with a local contractor.

C.

Implement key performance indicators (KPIs) and convince the contractor to engage the team.

D.

Reassess continually to remove blockers for the team.

Full Access
Question # 74

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?

A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.

B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.

C.

Perform an independent analysis to determine the stakeholders from the client's organization.

D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.

Full Access
Question # 75

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization

How should the project manager handle the different stakeholders?

A.

All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders

B.

Because there are different perspectives perform a stakeholder analysis and act based on the outcome.

C.

The project manager is working on the client's premises, so follow the directions of all the key stakeholders

D.

This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization

Full Access
Question # 76

One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?

A.

Expedite the next phase to reduce slippage

B.

Add more float to the overall project schedule

C.

Request additional contingency from the sponsor.

D.

Organize a root cause analysis (RCA) workshop.

Full Access
Question # 77

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''

A.

Include the local union representative in the high-power, high-impact stakeholder group

B.

Focus on the sideward stakeholders only and let the organization manage the community.

C.

Build channels to extend communication efforts to the local community

D.

Use the city administration to address communication with the community

Full Access
Question # 78

During the execution phase of a project, all project team members were forced to work from their homes rather than in person During this time, the project manager discovered that 0.-10 team member has made disrespectful remarks about another team member to other team members.

How should the project manager handle this situation''

A.

Instruct the team members involved to resolve the issue among themselves

B.

Discuss the issue with the steering committee to determine the proper course of action.

C.

Coordinate a video conference with the offending team member to resolve the issue

D.

Reassign the offending team member to a different project

Full Access
Question # 79

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?

A.

Establish the project scope and set clear team objectives

B.

Set performance standards and direction

C.

Hold early kick-off meetings and regular weekly meetings

D.

Select members for their skill or potential

Full Access
Question # 80

One of the risks identified during project planning activities is related to a component from a preferred vendor. The component utilizes new technology, and there is a possibility of incompatibility with other parts of the system that are being developed.

What should the project manager do?

A.

Create a risk probability matrix to address the incompatibility.

B.

identify an alternative component in case of incompatibility.

C.

Use the contingency fund to redesign the interface if it is incompatible,

D.

Require the vendor to redesign the incompatible component to fit the system.

Full Access
Question # 81

A project team member is struggling to understand a specific requirement. How should a servant leader address this issue?

A.

Assess and evaluate the team member's skills to ensure alignment to the particular requirement and solution

B.

Reassign the requirement to another team member who may have ideas on how to meet the requirement

C.

Assist by connecting the product owner with the team member to discuss what problem is to be solved

D.

Deprioritize the requirement and assign a task tor it to be restated to provide the necessary clarity

Full Access
Question # 82

A construction services company has influence within the local community with the potential to derail a project site establishment. Their build was unsuccessful but they continue to communicate with the hope that their influence will persuade the project manager to reconsider their offer.

What is the appropriate course of action for the project manager to pursue?

A.

Do not communicate with the unsuccessful bidder as they do not have any further influence on the project

B.

Meet with the unsuccessful bidder to review their submission and the areas that led to the bid being unsuccessful

C.

Reassess the bid to establish areas for improvement with the intention to assign work to this contractor

D.

Report the unsuccessful bidder to the local community leadership who have been supportive of the project

Full Access
Question # 83

At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.

What should the project manager do to start building the product faster?

A.

Allow the sponsor to determine how long the planning phase should last.

B.

Allow the client ta determine how long the planning phase should last.

C.

Ask the functional manager to work with the team to finalize planning and begin building the product.

D.

Explain that more features can be planned in upcoming Iterations and begin building the product.

Full Access
Question # 84

During protect execution the project manager observes lower velocity and a high volume of tasks m the testing queue. The project is using a hybrid approach and there are only a few sprints remaining

What should the project manager do?

A.

Work with the team to understand and solve the issues

B.

Provide testing training to all the project team members

C.

Increase the sprint duration so the testing can be completed

D.

Add a new resource with testing skills to the team

Full Access
Question # 85

A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items

What should the project manager do as a servant leader?

A.

Ask the sponsor to submit a change request to the change control board (CCB)

B.

Support the product owners decision to change the priority of the product backlog items

C.

Accept the request and include the product backlog items in the next sprint

D.

Review the impact of the change on the schedule management plan baseline

Full Access
Question # 86

Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.

What is the protect manager's first step in addressing the problem?

A.

Communicate the issue to the change control board (CCB) and relevant stakeholders identified in the stakeholder engagement plan

B.

Create a problem-solving team from quality assurance subject matter experts (SMEs) experienced in this type of analysis

C.

Form a brainstorming team from project team members selected for their relevant technical analytical and management knowledge

D.

Form a brainstorming team with stakeholders from all of the functional departments involved in the project

Full Access
Question # 87

A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.

What advice should the senior project manager provide?

A.

Provide a project management template for the project manager to follow as a guide.

B.

Suggest using an agile approach since customer and team collaboration is critical for project success.

C.

Work with the project manager to develop a new approach that will bring benefits to the project.

D.

Establish a project management methodology that requires the customer to provide daily updates to the team.

Full Access
Question # 88

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

A.

Manage the risks associated with the proposed approach.

B.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.

C.

Coordinate with the business unit to get detailed requirements.

D.

Work closely with the marketing team on market research and product segments

Full Access
Question # 89

During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.

What should the project manager have done to avoid this situation?

A.

Determined the appropriate type of incentive for key team members

B.

Conducted frequent monitoring on key team members’ performance during project execution

C.

Distributed the monetary incentive according to the team members’ individual performance

D.

identified the underperforming team members and asked the human resources (HR) department to replace them

Full Access
Question # 90

Development team members are located in three different time zones It is difficult to find a suitable time to hold the daily standup for all team members

What should the project manager do?

A.

Encourage frequent small team meetings with two or three team members.

B.

Give up the daily standup and replace it with a daily report

C.

Let the team members decide themselves if they want to join the meeting.

D.

Require all team members to join the daily standup regardless of the meeting time

Full Access
Question # 91

A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is

frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.

What should the project manager do?

A.

Request that the team identifies, documents, and registers the issues to locate the source of the problems.

B.

Evaluate the cost and schedule variance in order to determine how much the project is off track.

C.

Ask the team to commit to a new date to fix all the problems and proceed with a change request to adjust the baseline.

D.

Request that a senior subject matter expert (SME) be hired to analyze and solve the problems.

Full Access
Question # 92

A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.

Which aspect should the project manager highlight in the closure report to address the stakeholder's concern?

A.

How the quality was managed

B.

How the acceptance criteria were met

C.

How the scope was managed

D.

How the stakeholders were managed

Full Access
Question # 93

A project team's performance has declined for the last three iterations Some of the team members are disappointed, and raise their concerns during the retrospective meeting What should the project manager do?

A.

Focus on remediation not merely on correcting symptoms

B.

Compare the team's performance against other project teams

C.

Identify potential failure points based on the iteration workload

D.

Motivate the team to perform better

Full Access
Question # 94

Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not

delivered, the company could receive a fine from the government. What should the project manager do?

A.

Discuss the issue with the project sponsor.

B.

Review the resources required for the tasks on the critical path.

C.

Review and update the risk management plan.

D.

Allocate resources to develop the competencies of the other team members

Full Access
Question # 95

A project manager is in the middle of an agile project comprised of 100 user stories broken down into five iterations Each user story is worth USS50 The actual expenditure is US$2,000 and 50 user stories have been delivered.

Which statement is true''

A.

The project is on budget and on schedule.

B.

The project is over budget and behind schedule

C.

The project is under budget and behind schedule.

D.

The project is under budget and on schedule.

Full Access
Question # 96

An organization in a regulated industry has decided to switch from a predictive to

an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,

and the project manager is still accountable for the project outcomes. During the fourth sprint

demo, the customer notices that a feature is not compliant with the regulations.

What should the project manager do?

A.

Have the team consult with the compliance officer to update the definition of done

(DoD) for the user stories in the past sprint.

B.

Have the product owner consult with the change control board (CCB) to have the

necessary compliance requirements implemented.

C.

Have the scrum master organize a weekly meeting with the compliance officer, the

product owner, and the project team.

D.

Have the product owner review the user stories in the product backlog with the

compliance officer on a regular basis to identify any gaps.

Full Access
Question # 97

A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.

What should the project manager have done to prevent this conflict?

A.

Provided copies of the stakeholder engagement plan to all team members.

B.

Defined the roles and responsibilities of the team members.

C.

Updated the communications management plan.

D.

Established ground rules for the team

Full Access
Question # 98

The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.

What should the project manager do to resolve and prevent additional arguments?

A.

Monitor the interactions between the vendor and infrastructure manager going forward.

B.

Host a meeting with the vendor and infrastructure manager to help resolve their disagreement.

C.

Escalate the issue to the sponsor so appropriate action can be taken.

D.

Instruct the vendor to correct the problem without additional arguments.

Full Access
Question # 99

A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?

A.

Express trust in the team's ability to fulfill the necessary deliverables.

B.

Assert judgment over the team.

C.

Use a plan-driven approach in order to demonstrate control over the project.

D.

Increase the amount of subject matter experts (SMEs) to get better results.

Full Access
Question # 100

A project team is conducting a retrospective. The team wants to identify what had

a positive impact on the velocity and keep doing it.

Click on the area that the team should focus on to identify good practices.

PMP question answer

Full Access
Question # 101

As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved

How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

PMP question answer

Full Access
Question # 102

A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a

requirement for a user experience design approach.

Which project management approach should the project manager use?

A.

The software development has a high uncertainty level, so an agile approach is recommended for the project.

B.

The scope is well defined; therefore, a predictive approach is straightforward and the hardware and software can by synchronized on the gates.

C.

The deliverables are significantly different, so the project should be split into two projects that are driven by a program.

D.

A hybrid approach will work, using agile for software development and a predictive approach for the hardware deliveries.

Full Access
Question # 103

A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,

yet some stakeholders lack an understanding of how it will provide value to the organization.

What should the project manager do next?

A.

Ask the sponsor to identify requirements for a new project to monitor and report achievement of the benefits.

B.

Direct the team to implement the benefits management plan and track achievements before the end of the project.

C.

Coordinate with the stakeholders to ensure the benefits management plan is in alignment with the goals.

D.

Update the work breakdown structure (WBS) and project schedule with tasks and resources to track benefits realization.

Full Access
Question # 104

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

A.

Evaluate the impact of skipping the quality check for the deliverable.

B.

Seek approval from the sponsor on an extension of the project schedule,

C.

Seek approval from the quality board to skip the quality check.

D.

Ask the team member to work overtime to complete the quality check.

Full Access
Question # 105

A company wants to launch a new product for customers. The project for this new product is in the development phase. Due to an uncertain environment, the project manager has

doubts about the feasibility of the project.

What should the project manager do in this situation?

A.

Validate assumptions using appropriate tools to assess the risks.

B.

Refer to the lessons learned to determine the impact on the external environment.

C.

Recommend postponing the project until the uncertainty is resolved,

D.

Highlight the concern to the project sponsor in the next project review meeting,

Full Access
Question # 106

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.

What should the new project manager do?

A.

Meet with the team to review the backlog and create small iterations that can deliver incremental value to the client,

B.

Continue working with the predictive approach to deliver the value at the end of the project.

C.

Use a hybrid approach in which agile practices are used but the value is provided to the client at the end of the project.

D.

Submit a change request to the project board to adjust the delivery date to 2 months earlier than planned.

Full Access
Question # 107

During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?

A.

Ask the team to solve the issue internally and review the underperforming resource's situation

B.

Meet with the team member privately to discuss the problem and work together to find a solution

C.

Contact the functional manager and request to replace the team member with a better resource

D.

Discuss various options to improve the team member's performance with their functional managers

Full Access
Question # 108

A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor

What should the project manager have created to prevent this situation1?

A.

Resource breakdown structure

B.

Work breakdown structure (WBS)

C.

Team charter

D.

Project charter

Full Access
Question # 109

A project manager is assigned to a new project and is allocated with virtual team

members. Later, two more members from a recently acquired company join as additional

resources to the project team.

In order to ensure that there are no potential misunderstandings, what should the project

manager do?

A.

Send an email update to existing team members about the addition of the new team

members.

B.

Set up a weekly meeting with the new team members for a couple of months.

C.

Request the transfer of the new members to another project, citing a risk of confusion.

D.

Update and share the guideline document dealing with team communication.

Full Access
Question # 110

An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.

What should the project manager do?

A.

Provide feedback to the team and conduct a meeting to review the team rules.

B.

Provide feedback to the team and conduct a retrospective meeting to find a root cause.

C.

Provide feedback to the team and request agile training for the new member.

D.

Provide feedback to the team and coach the new team member in agile methodology.

Full Access
Question # 111

A project manager is working on a large project with a very difficult client. During

the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.

How should the project manager approach this?

A.

Concentrate on the current project milestones.

B.

Update the project management plan for this new work.

C.

Develop a business case and submit it to the client.

D.

Make all the changes and then show the client the results.

Full Access
Question # 112

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

A.

Replace the team member immediately to maintain a good relationship with the

functional manager.

B.

Discuss the issue with the functional manager to understand the reason for the

complaint.

C.

Support the team member and provide documentation to the functional manager

proving their performance.

D.

Protect the team member and ask the project sponsor to minimize any external

interruptions.

Full Access
Question # 113

A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?

A.

Provide opportunity for team members to learn and adjust to the technology.

B.

Move team members who are not performing from the team.

C.

Add new members to the team and increase the velocity

D.

Re-assign the project to a team that has worked with this technology

Full Access
Question # 114

In a hybrid project, the customer has issued a contract that specifies the deliverables for each quarter The customer wants to show their stakeholders a tangible outcome in the first quarter and wants to move the second milestone to the first quarter The project manager explains to the customer that it is not feasible unless the requirements for the second milestone are changed

Which two actions should the project manager take? (Choose two)

A.

Convince the customer to leave the second milestone in place and not change it.

B.

Escalate the issue to upper management to resolve the problem and suggest a plan.

C.

Go back to the development team and discuss which second milestone requirements can be performed in the first quarter.

D.

Ask the customer for their priorities regarding the requirements for the second milestone

E.

Tell the customer that moving the milestone has a very high impact on the cost of the project

Full Access
Question # 115

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?

A.

Ask the new team member to follow the team ground rules.

B.

Ask an experienced team member to identify a replacement

C.

Ask the new team member to reassess their own capabilities

D.

Ask an experienced team member to coach the new team member

Full Access
Question # 116

A retail company identifies that it is losing sales because customers are not promptly

informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.

Considering the objective to deploy customer value, which project life cycle approach should be chosen?

PMP question answer

Full Access
Question # 117

According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.

What should the project manager do?

A.

Record it in the risk register

B.

Ask the client to help solve the problem

C.

Start procuring this material from another supplier.

D.

Engage the project team to look for alternatives to find a solution

Full Access
Question # 118

In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.

What should the project manager do to manage this conflict?

A.

Schedule a meeting with the team member and their manager to discuss the issue.

B.

Talk to the project sponsor about the team member's attitude.

C.

Schedule a one-on-one meeting with the team member to talk about it and get their

cooperation.

D.

Find another person to replace this team member.

Full Access
Question # 119

While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:

  • Approved Work Package Cost Estimates: US$9,500
  • Contingency reserves: $500 %
  • Management reserves: 10% of contingency reserves
  • Percent complete of the project: 50%
  • Planned percent of the project: 40%
  • Actual costs of the project: US$4,500

What is accurate about the project status?

A.

The actual work is 25% more than the planned work.

B.

The project cost is 10% lower than planned.

C.

The actual work is 25% less than the planned work.

D.

The project cost is 10% higher than planned.

Full Access
Question # 120

A project to implement a new process is still in development. When implemented,

the company will benefit by a reduction in utility costs. The project financial evaluation

indicates a payback of 3 years.

What should the project manager do to expedite the project delivery?

A.

Increase resources on the technical design to enable a decision to proceed as this is a

quick return project.

B.

Increase the time spent on project development to improve the level of confidence to

validate the financial evaluation.

C.

Conduct a stakeholder survey with the plant operators to establish the probability of

this project reducing the cost of utilities.

D.

Stop any further project development and commence with the implementation as there

is no need to seek further approval.

Full Access
Question # 121

There is a problem with a project because some features are not in compliance with

regulations. Some stakeholders do not believe compliance is a priority, while others disagree.

What should the project manager do?

A.

Review the stakeholder engagement assessment matrix to determine next steps.

B.

Set up some time with the stakeholders to explain the importance of compliance.

C.

Meet with the sponsor to discuss how to handle the stakeholders' differing opinions.

D.

Send out documentation to align stakeholder expectations and project objectives.

Full Access
Question # 122

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?

A.

Request the project team include the stakeholder's details and make sure the project

status reports are shared with the stakeholder.

B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.

C.

Review the stakeholder management plan and update the stakeholder register for

incorporation in the project management plan.

D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.

Full Access
Question # 123

A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.

Which approach should the project manager choose for this project?

A.

Agile

B.

Waterfall

C.

Hybrid

D.

Predictive

Full Access
Question # 124

A project manager is working with an agile team to enhance a product. Due to a

tight deadline, the team is trying to crash the schedule by engaging multiple resources to work

on the project simultaneously. However, the technical environment is configured to allow only

one resource to work on a feature at a time. The team plans to upgrade the technical

environment but is unable to agree on a way forward.

What should the project manager do first?

A.

Conduct a consensus-building session to decide how to approach the next set of work.

B.

Escalate the issue to the product owner for resolution.

C.

Add this conflict to the agenda for discussion at the next daily standup meeting.

D.

Conduct a planning session to decide how to approach the next set of work.

Full Access
Question # 125

A project management team received news that a competitor has released the

latest version of a program. What should the team do next?

A.

Review the project plan to evaluate if any updates should be made.

B.

Crash the existing schedule with additional resources to deliver more features.

C.

Stop the project immediately as the market opportunity has already been missed.

D.

Continue with the project plan and target delivery date as expected.

Full Access
Question # 126

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

A.

Arrange separated group meetings to allow everyone to express their opinions.

B.

Review the communications management plan with the team and enforce its implementation.

C.

Prepare an agenda for all future team meetings and facilitate the discussion.

D.

Speak with the experienced team member to discuss the issues in a supportive way.

Full Access
Question # 127

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

A.

Increase the capacity of the team to deliver the completed backlog on time.

B.

Ask the customer to reduce the backlog to meet the launch date.

C.

Assist the team in defining a minimum viable product (MVP) by the launch date.

D.

Schedule a meeting with the stakeholders to review the contingency plan.

Full Access
Question # 128

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday

morning. Due to an unexpected issue, 50% of the team has to work from home. The bank's management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team

What should the project manager do?

A.

Postpone the daily standups and ask the team members to update the project manager daily via messaging.

B.

Hold virtual daily standups each workday morning and use collaboration tools to manage project updates.

C.

Delegate authority to the team members and ask them to submit weekly status reports instead.

D.

Ask senior management for permission to hold in-person team meetings once each week.

Full Access
Question # 129

A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.

What should the project manager do to address this issue?

A.

Request that the project team change their task deliverables to reflect the project sponsor's requirements.

B.

Set up a daily standup and request that the project sponsor attend to understand the project's tasks and deliverables.

C.

Ask the project team to compile a project scope document and obtain approval from the project sponsor.

D.

Facilitate a stakeholder alignment session so that the team and project sponsor are in agreement with the deliverables.

Full Access
Question # 130

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version

How can the project manager prevent this outcome in the new project?

A.

Hire a team of external users to perform acceptance testing on the product.

B.

Define a user focus group as external stakeholders with a high influence on outcomes

C.

Hire a consultant to perform a benefit analysis as an input to the project charter.

D.

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS

Full Access
Question # 131

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.

This request does not match the project manager's expectation, since a program manager is overseeing the remaining work

How should the project manager approach the situation?

A.

Attend only the program meetings where the market launch is being monitored

B.

Provide an answer via email recommending a division of tasks between both roles.

C.

Politely inform the program manager that attending these meetings is no longer required.

D.

Schedule a meeting to discuss the different perspectives and agree on a decision.

Full Access
Question # 132

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of

risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk

mitigation plan.

What should the project manager do?

A.

Submit the new response plan to the stakeholders for their review.

B.

Obtain management approval prior to implementing the new risk response.

C.

Use the management reserve to mitigate the risk.

D.

Implement the new response to address the risk.

Full Access
Question # 133

A project manager is assigned to a project with a long timeline and complex scope. The client requires a high-level, long-term plan as well as

something that will work immediately, adding features to the product as the project progresses.

How should the project manager plan and deliver this project?

A.

Plan the project with a predictive approach with a work breakdown structure (WBS) and then execute it using an agile approach to deliver

value incrementally.

B.

Plan the project with a predictive approach and a work breakdown structure (WBS) following the plan and deliver value at the end of the

project.

C.

Agree on a minimum viable product (MVP) first to be delivered immediately with the client and then release the rest of the scope at the end

of the project.

D.

Select an agile approach and manage the project according to best practices to ensure value is delivered to the client.

Full Access
Question # 134

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.

B.

Create a salience model to determine if the employee will have influence on the project.

C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.

D.

Assess the influence and power of the employee to see if the employee will add value.

Full Access
Question # 135

A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce

the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December

might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.

What should the project manager do about this risk?

A.

Update the risk register and take advantage of the opportunity.

B.

Review the supplier's contract to understand the terms of sale.

C.

Accept the risk and update the risk register.

D.

Insist that the supplier deliver the goods on the agreed date.

Full Access
Question # 136

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

A.

Dedicate the next sprint to completing the missing details.

B.

Apply fast-track techniques to work on the missing details in parallel,

C.

Continue iterating and monitoring quality aspects sprint by sprint.

D.

Create a new risk entry for the delay in the risk management plan.

Full Access
Question # 137

In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale.

What should the project manager do to handle this situation?

A.

Give team members more authority to make decisions.

B.

Perform team-building activities and enhance collaboration.

C.

Identify the team members who are impacting low morale.

D.

Coach the team members on agile processes and knowledge.

Full Access
Question # 138

An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.

What should the project manager have done to avoid this situation?

A.

Ensured the project repository is up to date.

B.

Updated the job descriptions for all team roles.

C.

Provided specialist training for all team members.

D.

Made an effort to reemploy the senior project team member.

Full Access
Question # 139

In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement

How should the project manager respond to the suggestion?

A.

The change should be considered and immediately added to the product backlog.

B.

The change should be considered and presented to the project sponsor for approval

C.

The change should be considered because it will help the team work more efficiently

D.

The change should not be considered because it adds no value to the end customer

Full Access
Question # 140

A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule

Which two actions should the project manager take to manage Impediments and improve the team's velocity? (Choose two)

A.

Look for processes that cause bottlenecks and slow down the team's agility

B.

Assign the items with high complexity lo senior developers

C.

Empower the learn to make decisions to remove impediments

D.

Work with the team to remove impediments as quickly as possible

E.

Move the items with high complexity to the last iterations

Full Access
Question # 141

A project is successfully delivering its product outcomes, and the customer satisfaction rating is high. However, during an internal audit, it is discovered that certain essential process documents and approvals are missing, and the project is evaluated as being noncompliant.

What should the project manager do next?

A.

Review the latest project management standards with the project management office (PMO) and make changes to the quality management plan.

B.

Perform quality assurance to review the processes against the quality management plan and identify gaps.

C.

Review and update the project document repository with the missing documents and approvals.

D.

Change the quality management processes to align with the project objective.

Full Access
Question # 142

A company has agreed to run a transformation project using agile approaches.

During the implementation, there is pushback from the functional groups that the project is moving too fast.

What should the project manager have done at the beginning of the project to prevent this from happening?

A.

Circulated the project charter

B.

Assessed the organizational culture

C.

Determined the level of maturity of the employees

D.

Communicated the project schedule

Full Access
Question # 143

A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.

What immediate action should the project manager take to improve the situation?

A.

Communicate this issue to the human resources department.

B.

Provide additional training to the new hire.

C.

Increase team cohesiveness by sharing information and experiences openly.

D.

Update the issue log and define the mitigation strategy.

Full Access
Question # 144

A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.

What else does the project manager need to do before determining the budget baseline?

A.

Look at a previous project to ensure the budget totals match.

B.

Require all stakeholders to review and approve the estimates.

C.

Revise the project timeline and scope based on the WBS.

D.

Add contingency into the budget for inflation and other changes.

Full Access
Question # 145

A project manager prepared the base budget model to deliver a highly

customizable software solution. The solution will be delivered in multiple countries with

significantly different cultures and will be staged over phases.

What should the project manager do next?

A.

Review the base model with the team leaders in each country to establish an

independent budget for each phase.

B.

Overestimate costs and underestimate revenues to include the impacts of different

cultural elements.

C.

Apply the company's operational budgeting model.

D.

Ask the project management office (PMO) to review the draft budget.

Full Access
Question # 146

At the end of a project, the project manager is asked to submit project documentation for an internal audit in response to regulatory requirements. What should the project manager have done at the beginning of the project to ensure that project documentation would

fulfill these requirements?

A.

Conducted a document review

B.

Confirmed documentation requirements with stakeholders

C.

Updated the project templates

D.

Implemented a new change control policy

Full Access
Question # 147

The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.

How should the project manager approach this situation?

A.

Meet with the stakeholders to understand their concerns and define an action plan to resolve issues.

B.

Continue to work on the project until the stakeholders and management come to a decision.

C.

Socialize with the stakeholders to better understand their needs and reset expectations.

D.

Escalate the stakeholder issue to the management team and ask for help with resolving the conflict.

Full Access
Question # 148

A project started 12 months ago and is currently on iteration 12 of 14. The team

has performed well and completed all deliverables on time. However, some team members

are starting to complain about the length of the project, creating a risk for lack of

performance at this critical stage.

What should the project manager do as a servant leader to mitigate this risk?

A.

Meet with the team to reinforce their responsibilities and the consequences if the

project deliverables are not completed on time.

B.

Apply additional controls to the project deliverables to ensure that all milestones

are achieved on time.

C.

Contact the functional manager to ensure that team motivation remains high until

the end of the project.

D.

Schedule a team event with the project sponsor to highlight the importance of the

project and recognize the work of the team.

Full Access
Question # 149

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

A.

Modify the project management plan and get approval from relevant stakeholders

B.

Add more resources to recover the schedule without making changes to the baseline.

C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.

D.

Negotiate with the project sponsor immediately and establish a new project charter.

Full Access
Question # 150

A project manager is working with a customer's team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start

activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the

project manager has decided to use a hybrid approach.

Why did the project manager choose a hybrid approach?

A.

A hybrid approach will ensure the delivery date is accomplished and will eliminate product uncertainties.

B.

A hybrid approach will enable project activities to start immediately and allow for a plan for the requirements definitions.

C.

A hybrid approach will allow the project manager to revise the product specifications.

D.

A hybrid approach will allow for management of the requirement uncertainties as well as the date restriction.

Full Access
Question # 151

A project team needs to follow regulatory compliance guidelines that are mandatory for the project. What should the project manager do to ensure compliance adherence?

A.

Assess compliance when there is time in the project.

B.

Assign a project team member to ensure compliance.

C.

Review compliance adherence at the end of the project.

D.

Include compliance within the development tools.

Full Access
Question # 152

A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.

What should the project manager do first?

A.

Send an email to the client team member explaining that they have the information already.

B.

Review the stakeholder register to gain insight into the expectations of that team member.

C.

Inform the client project manager that they are sending too many trivial requests.

D.

Update the project risk register to include potential delays in answering these requests.

Full Access
Question # 153

A project manager is working on a major construction project. Part of the

agreed-upon plan was to use a cloud-based system with a server that runs on high-speed

internet service since most of the team members work virtually. The company needs to

reduce operating costs as much as possible and management insists that the project will

now use a system running on a conventional dial-up service.

What should the project manager do next?

A.

Evaluate the impact of this decision and communicate with management.

B.

Agree with management and continue working the project management plan.

C.

Meet with management about their decision and ask them to get another project manager.

D.

Replace some of the team members that work virtually to help the company save money.

Full Access
Question # 154

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

PMP question answer

A.

Continue with the sprint as the progress shows buffers for potential interruptions.

B.

Ask the product owner if some low-priority stories could be cut from the sprint.

C.

Continue with the sprint work as planned and keep monitoring.

D.

Ask the project team to select any additional stories as they have additional capacity than planned.

Full Access
Question # 155

A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?

A.

The team with the higher velocity is performing better and should be rewarded.

B.

The issue should be addressed as part of a retrospective in the next iteration.

C.

The velocity should not be compared as teams can size items differently.

D.

The velocity of both teams should be compared at the end of every iteration.

Full Access
Question # 156

A stakeholder is requesting that the project manager share project status updates

on a regular basis. This stakeholder is not included in the regular distribution list.

What should the project manager do?

A.

Start sending status updates to this stakeholder based on the request.

B.

Ask the stakeholder's manager if the stakeholder can be added to the list.

C.

Review the stakeholder engagement and communications management plans.

D.

Escalate the stakeholder’s request to the project sponsor.

Full Access
Question # 157

A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?

A.

Check if the budget can cover the enhancement

B.

Accept the request because it came from the project sponsor

C.

Refuse the project sponsor's request because it is out of scope

D.

Validate the proposed change's impact on the project.

Full Access
Question # 158

An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.

What should the project manager do to avoid this situation in the future?

A.

Ensure that customer requirements do not change from the start of the project.

B.

Ensure that the definition of done (DoD) is well defined and complete for future iterations.

C.

Ensure that the development and quality assurance team members implement the feature correctly.

D.

Ensure that the team facilitator allocates tasks correctly to team members.

Full Access
Question # 159

At the end of the last iteration, the customer rejects the deliverables since they did

not meet the customer's expectations. What should the project manager have been done

to prevent this situation?

A.

Involved the customer more in the planning process for the project, and ensured

agreement on the proceedings.

B.

Included all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.

C.

Provided the customer with the backlog and the specified user stories at the beginning of the iteration.

D.

Developed the DoD in close cooperation with all stakeholders to ensure their expectations were included.

Full Access
Question # 160

A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.

What should the project manager tell the team members to focus on?

A.

Reducing cost for the customer

B.

Delivering value to the customer

C.

Working together as a team

D.

Finishing the project on schedule

Full Access
Question # 161

A project manager is assigned to a new project. The project management office

(PMO) and the project manager agree that this is the right opportunity to include daily

standup meetings. The project team has never used such tools, and a few members are

challenging the decision.

What should the project manager do in this situation?

A.

Engage an external vendor to perform the design phase under an iterative approach.

B.

Request that new team members familiar with iterative approaches be assigned to this project.

C.

Update the project schedule to consider a daily standup as part of the project design phase.

D.

Define the ground rules, responsibilities, and conflict management strategies.

Full Access
Question # 162

The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.

What should the project manager do to ensure timely delivery?

A.

Ask the team leader to assign other resources.

B.

Update the issue log.

C.

Include this in the risk register.

D.

Escalate the issue to the functional manager.

Full Access
Question # 163

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.

What strategy should the project manager use in order to keep delivering value in a restricted environment?

A.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance.

C.

Restrict the project scope only to basic critical features, and run the project with the current staffing level until all of the budget is consumed.

D.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction

Full Access
Question # 164

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?

A.

Escalate the issue to the team's manager.

B.

Remove some of the team members.

C.

Review the roles and responsibilities document.

D.

Develop working agreements with the team.

Full Access
Question # 165

A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.

What should the project manager do?

A.

Implement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.

B.

Ask the product owner to act as a risk manager to assist with the remediation of risks.

C.

Implement the role of an agile risk manager to take care of the risk management process.

D.

Follow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.

Full Access
Question # 166

During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.

What should the project manager do?

A.

Schedule a meeting with the new sponsor in order to explain the agile approach and how teams are supposed to be self-organized.

B.

Schedule an emergency meeting with the project team so they fulfill every request that comes from the sponsor.

C.

Review the sponsor's request with the project team during the next daily review meeting in order to provide the requested control.

D.

Review the sponsor's request with the project team during the next iteration review meeting in order to obtain a team decision.

Full Access
Question # 167

In a multinational project, stakeholders are in different time zones. The project

manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the

project sponsor that they know very little about the project.

What should the project manager do?

A.

Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.

B.

Ensure that the stakeholders who are complaining are present for the next project update meetings.

C.

Record the regular project update meeting and share it with all stakeholders after the meeting is completed.

D.

Change the meeting time to the working time zones of the stakeholders who are complaining.

Full Access
Question # 168

During a regular review, the project manager of an agile project realizes that a key stakeholder is missing critical information about some features being developed. In order to improve communications and reduce the risk of deploying the wrong features, what should the project manager do?

A.

Assess the stakeholder's needs and communication style and propose a tailored approach with regular status reports and progress meetings.

B.

Invite the stakeholder to the regular "show and tell" sessions so the stakeholder is aware of project progress and feedback can be gathered.

C.

Conduct stakeholder remapping, evaluate stakeholders by their level of influence and interest on the project, and communicate accordingly.

D.

Include the stakeholder on regular project communications so that decisions can be followed up closely.

Full Access
Question # 169

An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern's mentor Two months later, the project goes into critical status, delaying the release milestone by a month.

What should the project manager have done to avoid this scenario?

A.

Convinced the critical resource to remain on the project.

B.

Requested an experienced resource as a replacement

C.

Allocated additional time for mentoring

D.

Negotiated additional time to complete the project

Full Access
Question # 170

When reviewing the project team's performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?

A.

Increase the sprint duration to allow the team more time

B.

Prioritize the contents of the backlog and remove some stories

C.

Create a change request to modify the gate review goals

D.

Use the standup meeting to assess impediments and problems

Full Access
Question # 171

A project manager is using a hybrid approach for project delivery. The

development team was sized, but is not yet fully resourced. The project manager is working

on defining the project schedule.

What should the project manager do to address the issue of developer availability?

A.

Organize a planning session with the development team and use their estimations to complete the schedule.

B.

Ask the resource manager when the new contractor is available to start and change the delivery date for the project schedule.

C.

Ask the sponsor to provide the desired completion date for project activities and complete the schedule.

D.

Use expert judgment to estimate all of the tasks and complete the schedule in the allocated time.

Full Access
Question # 172

A project needs to purchase a specific piece of equipment, as stated in the

project documents and approved by the project sponsor. The procurement division is

questioning the need to buy the specific brand of equipment and has suggested buying a cheaper alternative instead.

What should the project manager have done earlier in the project to ensure the purchase of the specific equipment?

A.

Communicated the project charter to the procurement division

B.

Included a procurement division member on the project team

C.

Reminded the project sponsor about the procurement division's reputation

D.

Communicated the project management plan to the procurement division

Full Access
Question # 173

A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?

A.

Develop new procedures that are easy for the team to follow.

B.

Escalate the issue to the CEO and the board members.

C.

Instruct the team that the procedures should always be followed.

D.

Initiate a review of the procedures with the CTO and the team.

Full Access
Question # 174

While developing a new product, a key stakeholder expresses concern about

insufficient information on product feature requirements. The product team disagrees and

mentions that detailed requirements have been provided.

What should the project manager do to handle this situation?

A.

Organize a discussion with the product team to clarify the missing information.

B.

Redirect the stakeholder to discuss this request with the functional manager.

C.

Record the new requirements and ask the product team to develop them.

D.

Conduct new risk and scope analyses, identifying the missing information.

Full Access
Question # 175

A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?

A.

Be clear with directions and assignments so people stay focused and engaged with their work.

B.

Promote an environment where everybody knows what their contribution means to the project as a whole.

C.

Design a reward system to get people motivated by recognizing significant individual contributions from the last sprint

D.

Encourage continuous rotation of roles among team members to keep people motivated throughout project delivery.

Full Access
Question # 176

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area

What should the project manager do first?

A.

Identify an alternative site.

B.

Update the issue log

C.

Issue a change request

D.

Update the risk register.

Full Access
Question # 177

A project manager and a stakeholder have different opinions on the budget estimates for a project that is being initiated based on a new consumer privacy law. What would be a reason for this difference in opinion?

A.

The communications management plan was not used by all stakeholders.

B.

Organizational assets were not available to back the rationale.

C.

Relative estimation by the team resulted in two estimates.

D.

The use of the Monte Carlo method can result in different estimations.

Full Access
Question # 178

An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.

What should the project manager of the ongoing project do?

A.

Submit new user stories to the product owner in order to put documentation in the product backlog.

B.

Introduce a document management tool to support the agile teams in preparing the documentation.

C.

Check with the agile teams to see if the project manager's understanding of the Agile Manifesto is correct.

D.

Add an additional team member to take up the role of scribe for the required documentation.

Full Access
Question # 179

Due to organizational changes: several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised What should the project manager do to ensure success of the project?

A.

Review and prioritize new requirements with stakeholders to determine which change requests are needed.

B.

Escalate the issue to the project sponsor and seek support to keep the original requirements.

C.

Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements

D.

Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project

Full Access
Question # 180

A company is transitioning from a predictive to agile delivery of projects. Based on

the requirements, the project team estimates the budget and decides to use a fixed-price

contract with its vendor. However, during the execution of the project, the requirements

evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.

What should the project manager do next?

A.

Send a detailed status report highlighting the issue with funding to all of the stakeholders.

B.

Submit a change request to the financial manager to increase the funding and continue as is.

C.

Meet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.

D.

Wait until the next gate review meeting to highlight the risk of low funds to the stakeholders.

Full Access
Question # 181

A team Is experiencing difficulties and has decided to use a spike. Please click on the portion of the burndown chart that corresponds to the spike.

PMP question answer

Full Access
Question # 182

An issue reoccurs six months after a project's go-live date despite being resolved

during the project life cycle. What should the project manager have done in the previous

phase to avoid this issue?

A.

Ensured the project team documented lessons learned about the issue

B.

Ensured the project team applied a long-term solution for the issue

C.

Asked the project team to conduct more testing with users

D.

Discussed the issue with the stakeholders

Full Access
Question # 183

A project manager is leading a project at a contracting company, and the project

team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.

What should the project manager do to avoid this situation in the future?

A.

Manage the scope baseline to influence the factors that drive change.

B.

Follow the proper change control process and evaluate the change for further impact.

C.

Work with the customer to ensure the feature adds value.

D.

Perform frequent reviews with the customer to ensure that the product is working as

expected.

Full Access
Question # 184

A project manager is assigned to deliver an innovative solution that is part of a

brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.

How should the project manager bridge the gap and ensure the project delivers the expected

business value?

A.

Determine the critical requirements.

B.

Document the risks and mitigations.

C.

Define the project schedule.

D.

Create a project scope statement.

Full Access
Question # 185

A project manager has recently joined a small company. The company's chief

operating officer (COO) asked the team to skip some steps in the process in order to work

more quickly. The project manager wants to ensure that these steps are not skipped in the

future.

What should the project manager do?

A.

Notify all team members that all steps in the process must be completed.

B.

Escalate the issue to the other executive leadership members.

C.

Schedule a review of the process steps with the team and the COO.

D.

Redesign the process so the team can move more quickly.

Full Access
Question # 186

During the executing phase, a project manager is reviewing the issue log and finds

there are outstanding high-priority issues that are still open. Most of the open issues require

effort from external domain experts who are not on the project team.

What should the project manager do?

A.

Ask the issue reporter to close the issues, because there are no project team members

who have the required domain knowledge.

B.

Review the open issues with the issue reporter and issue a change request to hire an

external domain expert.

C.

Request that the project team members learn the required domain knowledge and

resolve the open issues in a short time.

D.

Reduce the project scope to ensure that the project team has the knowledge to deliver

the system on schedule.

Full Access
Question # 187

A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days

What should the project manager do first to maintain the project team's performance level?

A.

Initiate a performance-based bonus for the team members to provide them with a monetary incentive

B.

Remind the team frequently that the project must be delivered on time and within budget

C.

Invite the team to a team-building event to alleviate their stress while strengthening teamwork

D.

Provide routine mentoring and coaching to the team members to identify any demotivating issues

Full Access
Question # 188

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.

B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline

C.

Seek approval with the sponsor to triple the project budget, hiring more people to

compensate for the compressed schedule

D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline

Full Access
Question # 189

A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.

What should the project manager do?

A.

Proceed with the project without allowing scope creep to occur

B.

Use the contingency funds to provide support for the requested projects

C.

Cancel the project since the stakeholder's request is out of scope

D.

Inform the sponsor and document the request in the stakeholder engagement plan

Full Access
Question # 190

A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams

What should the project manager do?

A.

Emphasize to the teams the importance of meeting the agreed deadlines

B.

Provide appropriate training to compensate for the mismatch.

C.

Update the project schedule to reflect the delay

D.

Accept the risk of the project missing deadlines due to the mismatch.

Full Access
Question # 191

An agile project team is looking to develop quality standards for a project How should the project manager coach the team?

A.

Determine the tools and techniques suitable for the project and ensure that testing is done early and continuously.

B.

Inform the team that user acceptance testing is required to ensure that the product owner accepts the solution

C.

Insist that test-driven development is implemented along with the automated testing

D.

Ensure that the definition of done (DoD) is provided when the product owner agrees that all acceptance criteria have been met for the user story

Full Access
Question # 192

A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

A.

Ask stakeholders to communicate with the project manager and not directly with the team

B.

Empower the team members to remove obstacles and blockers

C.

Address and remove obstacles and blockers for the team

D.

Add blockers to the issue log and risk management plan

Full Access
Question # 193

For an ongoing project, match the key performance indicators (KPIs) on the left to the correct categories on the right.

PMP question answer

Full Access
Question # 194

A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?

A.

Log a risk in the risk register and work with the new team member to mitigate it

B.

Motivate the new team member to perform.

C.

Share project documents with the new team member.

D.

Offer cross-training and mentoring to the new team member

Full Access
Question # 195

As part of a temporary assignment, a project manager is leading a business project During a daily status meeting, it is discovered that the project manager's former department has not completed a task This is delaying the current iteration.

What should the project manager do?

A.

Create an entry in the impediment board and assign it.

B.

Invite the project team to a swarming session to define a solution

C.

Leverage the network of the former department and ask for help

D.

Escalate the issue to the product owner to define the next steps

Full Access
Question # 196

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?

A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team

B.

Update the communications management plan based on the product owner’s

preferences and distribute to the team

C.

Suggest to the team to start using the communication tool suggested by the product owner

D.

Request the product owner to use email because using another tool will increase the workload

Full Access
Question # 197

local company is developing a new product and. for the first time, using a remote

team for the programming tasks of features. The design for the product comes from the local team. During the third sprint review, the product owner has concerns about the project's

outcomes. The remote development team is complaining that they do not clearly understand the requirements conveyed in the daily standup meetings.

How should the project manager address this situation?

A.

Evaluate and reassign the developing tasks to a local vendor who has worked on previous projects.

B.

Document the risk in the risk management plan and use contingency reserves to hire a local vendor.

C.

Review lessons learned from previous projects and organizational process assets (OPAs).

D.

Determine the communication needs, environment, and tools to get the message across.

Full Access
Question # 198

During the initiation stage of a multimedia exhibition-design project the project manager is developing the project management plan What should the project manager do to complete this task?

A.

Benchmark other similar exhibitions' deliverable lists and final outcomes

B.

Initiate a survey to solicit end-customer opinions and prioritize exhibition contents

C.

Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.

D.

Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract

Full Access
Question # 199

One of the service providers on a complex project has been facing resource

availability problems over the last six months. However, the service provider has assured the

project manager that the deliverables will be on time.

How should the project manager address this situation?

A.

Update the issue log.

B.

Perform a qualitative risk analysis.

C.

Perform a root cause analysis.

D.

Implement a risk response plan.

Full Access
Question # 200

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?

A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team

B.

Escalate the issue to the functional manager

C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training

D.

Perform the quantitative risk analysis for the team member.

Full Access
Question # 201

A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?

A.

Include key risks in the cost baseline.

B.

Perform an analogous estimate.

C.

Perform a bottom-up estimate.

D.

Include projected inflation rates.

Full Access
Question # 202

A contractor delivering construction services to a company is using agile principles

to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design

changes or performing rework.

What should the project manager do to minimize the cost?

A.

Put the project on hold until all definitions are ready in order to avoid rework.

B.

Review the backlog with the product owner and prioritize the tasks that are least likely to be affected by a change in legislation.

C.

Capture the engineers' feedback at the daily meeting and communicate it to the product owner.

D.

Cancel the project release resources, then start again when all the definitions are ready.

Full Access
Question # 203

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

% What should the project manager do next?

A.

Update the assumptions log and change log, and implement the change control process.

B.

Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests.

C.

Inform the client that the project cannot meet the project timeline and additional costs will be incurred.

D.

Deliver what was planned in the project management document according to the specifications.

Full Access
Question # 204

A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.

The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.

Match the stakeholders on the left with the appropriate frequency for updates.

PMP question answer

Full Access
Question # 205

A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.

What should the project manager do?

A.

Assign a development team member to have the responsibility of managing dependencies.

B.

Suggest that each project develops a high-level plan to monitor the dependencies

C.

Recommend switching to a predictive approach to have detailed plans to manage the dependencies

D.

Continue the project with 2-week iterations as dependencies will be managed individually

Full Access
Question # 206

A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.

What should the project manager do to gain an understanding of the cause for the resource's refusal?

A.

Speak directly with the resource.

B.

Communicate with their supervisor.

C.

Organize a team meeting.

D.

Speak with their colleague.

Full Access
Question # 207

A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.

Which action should the project manager take next?

A.

Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.

B.

Ask the team to wait until they are able to update the requirements specifications.

C.

Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.

D.

Meet with the development team to review and assess the requirements specifications.

Full Access
Question # 208

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

A.

Inform the functional manager that self-organization includes task allocation.

B.

Confirm with the team members that the functional manager is responsible for the delivery.

C.

Ask the product owner to clarify the roles and responsibilities of the project team.

D.

Inform the functional manager that task allocation is the responsibility of the product owner.

Full Access
Question # 209

An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a

critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining

that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.

What should the project manager have done differently?

A.

Communicated a new delivery date to the customer along with the news about the delay

B.

Disclosed to senior management in confidence, then communicated the delay to the customer

C.

Assessed the situation with the project stakeholders first and communicated the impact to the customer

D.

Spoken to the customer on the phone and explained the reason for the delay instead of writing an email

Full Access
Question # 210

A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?

A.

Draft a project decision request to include in the scope for the current iteration and ask the sponsor to approve.

B.

Explain that the team is fully dedicated to the current sprint activities and negotiate a mutually agreeable time.

C.

Add this to the project backlog and have the product owner determine where it fits in terms of priority.

D.

Indicate that this was a not a requirement identified during project planning and it is outside of the scope.

Full Access
Question # 211

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

A.

Update the project management plan and adjust the project budget with this change request.

B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Full Access
Question # 212

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

A.

Add the new requirements to the project scope immediately since they are mandatory changes.

B.

Review the new requirements with the compliance department to determine if a change request is needed.

C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.

D.

Proceed with the defined project requirements and delay implementing the new requirements.

Full Access
Question # 213

A new marketing vice president just joined a software startup and is concerned that the agile model does not provide the needed accountability for their role. What should the responsible project manager do to ensure the vice president is comfortable with the project meeting its agreements?

A.

Require proper approval of all requirements from the marketing vice president and formally document the agreements.

B.

Foster an environment of open communication where all parties can discuss issues and agree on objectives.

C.

Establish an executive review board where all stakeholders discuss and approve features and requirements.

D.

Leverage the use of the review/demo sessions with the vice president to acknowledge that the agreements were met.

Full Access
Question # 214

A customer discovered quality issues with the latest deliverables. However, the project team immediately resolved the issues.

Now that the project is back on track, what should the project manager do next?

A.

Reassess the risk log to ensure it is up to date.

B.

Monitor quality metrics to ensure the project continues as planned.

C.

Perform lessons learned to ensure the issue does not happen again.

D.

Schedule a team meeting to review the issue,

Full Access
Question # 215

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

A.

Review the requirements of the report with the team member to redefine its purpose.

B.

Escalate to the team member's functional manager that the report was not submitted as requested.

C.

Instruct the team member to provide the report and document this in the performance review.

D.

Reassign the report to another team member to prepare and submit it as requested.

Full Access
Question # 216

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could

resolve the bottleneck, and the project manager has been informed.

What should the project manager do next?

A.

Add developers to remove the backlog.

B.

Escalate the issue with the product owner.

C.

Reduce the testing scope of the backlog.

D.

Enroll team members in training on the tool.

Full Access
Question # 217

An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.

What should the project manager do to avoid this situation in the future?

A.

Create a team incentive program with prizes, allowing the team members to work overtime to find defects.

B.

Reduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.

C.

Hire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.

D.

Use the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.

Full Access
Question # 218

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

A.

Share a template with the stakeholder to receive feedback on deliverables.

B.

Ask the project sponsor to arrange a meeting with the stakeholder.

C.

Use networking skills to approach the stakeholder.

D.

Update the stakeholder engagement plan for the stakeholder.

Full Access
Question # 219

After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

A.

On schedule

B.

Ahead of schedule

C.

Stopped

D.

Behind schedule

Full Access
Question # 220

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product. What should the project manager do

next?

A.

Request approval from the company director to conduct training for the team.

B.

Ask the senior developer to rewrite all the stories.

C.

Engage with the customer and rewrite all the stories.

D.

Rewrite the stories to include the technical vision of the product.

Full Access
Question # 221

A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.

PMP question answer

Full Access
Question # 222

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned

cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.

What should the project manager have done to avoid this situation?

A.

Captured and reviewed all of the project work and related costs regularly

B.

Notified all vendors about the invoicing and nonpayment deadlines

C.

Reviewed the total committed cost against the cost invoiced at project closing

D.

Involved the finance team and discussed the issue with the vendor

Full Access
Question # 223

One of the team members is always late to the daily standup meeting. What should the project manager do?

A.

Schedule the meeting at the end of the day to accommodate everyone.

B.

Ignore the situation since the team member is accomplishing their deliverables.

C.

Reinforce the ground rules for standup meetings with the entire team.

D.

Speak with the team member directly to reinforce the ground rules.

Full Access
Question # 224

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.

B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.

C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.

D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.

Full Access
Question # 225

A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.

What should the project manager do?

A.

Use the existing budget for executing the fallback plan and update the baseline.

B.

Add additional resources to the project to fast track certain activities and reduce delays.

C.

Evaluate the fallback plan proposed by the team and submit a change request, if required.

D.

Communicate the delay to stakeholders and maintain the existing budget baseline.

Full Access
Question # 226

A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.

What should the project manager do to address this problem?

A.

Increase the contingency reserves to cover unknown-unknowns.

B.

Implement short cycles for inspection and provide feedback.

C.

Increase the management reserves to convert the known-unknowns.

D.

Create a new risk entry to identify the stakeholder as a detractor.

Full Access
Question # 227

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

A.

Update the project charter with the new requirement.

B.

Add a risk to the risk register.

C.

Add it to the issue log as an ongoing issue.

D.

Review and validate the scope management plan.

Full Access
Question # 228

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.

B.

Request help from the project sponsor to get support from the sales agents.

C.

Escalate the issue to senior management to gain team buy-in

D.

Explain the change benefits to the sales agents' manager to get their support.

Full Access
Question # 229

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

A.

Adopt the same timeframe as the closed project for the current project.

B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.

C.

Create a draft schedule based on the activity list and the historical data from the closed project.

D.

Evaluate each activity duration and build a new project schedule.

Full Access
Question # 230

A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment

What should the project manager do?

A.

invite the investor to a sprint retrospective meeting to discuss the improvements of the concept and expected performance of the equipment with the team

B.

invite the protect sponsor to the sprint review meeting and nave a QSA session about the concept and expected performance of the equipment

C.

invite the product owner and the team to a discussion about the concept and expected performance of the equipment

D.

invite the investor to the design review meeting to present the concept and expected performance of the equipment and include a QSA session m the meeting

Full Access
Question # 231

A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?

A.

Set up a meeting with the team to discuss and determine the project's challenges.

B.

Propose a revised project schedule to the sponsor as the delays have affected the time lines.

C.

Schedule a meeting with the sponsor to express the team's frustrations about the data.

D.

Meet with the data suppliers to explain the critical timing requirements of the project.

Full Access
Question # 232

A technology project is delivering new functionality on a new platform. Several team resources are starting to train their teams, but they are asking questions about the training that the project will provide.

What should the project manager's first action be?

A.

Indicate that on the new technology is the functional manager's responsibility.

B.

Review the project charter to determine if the training is in scope and, if not, put in a change request.

C.

Consult with the organizational change management specialist as to what the training plan includes.

D.

Document the skill requirements for the product to determine what training is needed.

Full Access
Question # 233

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

A.

Be more involved in the team member recruitment process to ensure qualified team members are chosen.

B.

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.

C.

Avoid micromanaging the team, enforce stricter rules, and monitor employees.

D.

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.

Full Access
Question # 234

An agile project to provide a material information system has started. During the kick-off meeting, the team realizes that the stakeholders require a solution in 2 months, but it will take at least 4 months to deliver the entire project.

Who should the project manager contact to help the team accelerate the delivery?

A.

The human resources (HR) department—to ask for more resources to add to the project team.

B.

The product owner and the stakeholders—to prioritize the requirements in the product backlog.

C.

The team—to have them increase their velocity to accomplish the stakeholders requirements.

D.

The stakeholders—to have them prioritize the requirements in the product backlog.

Full Access
Question # 235

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist

from the team was average.

What should the project manager do to help the new compliance specialist improve?

A.

Escalate this situation to the manager of the area for a possible solution.

B.

Provide time for the specialist to adjust to the pace of the project.

C.

Coordinate a one-to-one meeting with the specialist to assess the situation.

D.

Contact the human resources (HR) manager about the team's feedback.

Full Access
Question # 236

During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?

A.

Review the project time line and find opportunities to reduce the project schedule.

B.

Review the budget with the project sponsor and ask for an increase to the budget

C.

Review the backlog and find opportunities to reprioritize the work and reduce the project scope

D.

Review the resource management plan and find opportunities to reduce project costs.

Full Access
Question # 237

A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.

Which stakeholders should the project manager consult with first to manage interdependencies?

A.

Project sponsors

B.

Other project managers

C.

Business unit managers

D.

Program managers

Full Access
Question # 238

A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.

What should the project manager propose?

A.

Keep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.

B.

Propose an approach based on value measurement, such as the use of objectives and key results.

C.

Maintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.

D.

Maintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.

Full Access
Question # 239

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

A.

Plan the project to deliver value incrementally with regular releases.

B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime

C.

Identify tasks that can run in parallel to deliver the project faster.

D.

Ask the project sponsor to provide additional resources to fast track the project.

Full Access
Question # 240

A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager

discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The

remote team member feels they are not being adequately rewarded and recognized for their job.

What should the project manager do?

A.

Inform the human resource (HR) manager of this situation and ensure this news does not spread.

B.

Make arrangements with the resource's functional manager to relocate the team member to another existing project.

C.

Send a copy of the engagement contract to the remote team member and indicate that the team member is entitled to what is included in the

contract.

D.

Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.

Full Access
Question # 241

A project manager was recently assigned to a project that is in the execution phase and is experiencing roadblocks. During a review of the

processes and procedures, the project manager notices similarities to a previous project that experienced similar roadblocks. The project manager

reviews the task schedule and finds that certain tasks are well behind expectations. In speaking with the project team, the project manager

confirms that the team is following the processes exactly.

What should the project manager do?

A.

Update the schedule to account for the unexpected delays in the project tasks.

B.

Review the resources allocated to the project and change accordingly.

C.

Review and amend the processes to ensure only value-adding activities are present.

D.

Update the variation register to account for the extended project time.

Full Access
Question # 242

The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.

What should the project manager do to ensure a smooth start and completion of the project?

A.

Conduct an on-site survey, start the project to avoid any undue delays, and ensure costs are under control

B.

Invite all the stakeholders to a change control board (CCB) meeting, share feedback and facts, and come to a consensus.

C.

Advise the firm to cancel the project due to misunderstandings among the stakeholders and the associated risks.

D.

Determine the root cause of the misunderstandings, get all parties to reach a consensus, and help to implement the outcome.

Full Access
Question # 243

A project manager is managing an internal project with a tight budget and schedule. While executing the project, the project manager realizes that

some stakeholders are working against the success targets of the project.

What should the project manager do to ensure successful project delivery? (Choose two)

A.

Update the project stakeholder analysis and methods to satisfy the stakeholders’ requirements.

B.

Escalate the issue to the functional manager and ask for support.

C.

Involve all stakeholders in the project by distributing status reports.

D.

Focus on the supportive stakeholders and minimize involvement of unsupportive stakeholders.

E.

Engage all stakeholders in the project including the unsupportive stakeholders.

Full Access
Question # 244

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.

B.

Include project stakeholder expectations and needs while creating project acceptance criteria.

C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.

D.

Discuss project acceptance criteria with the project sponsor before the execution phase.

Full Access
Question # 245

The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete

the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility

activities that must commence immediately.

How should the project manager get these funds approved?

A.

Wait until the next investment committee meeting to submit the request and include the delay in the schedule due to work that could not start.

B.

Continue with the preliminary activities and inform the investment committee at the next monthly meeting.

C.

Exclude the preliminary scope from the full project scope and continue it as a new project that does not require investment committee approval.

D.

Submit the request to the project director for interim approval and include this approval for discussion at the next investment committee meeting.

Full Access
Question # 246

A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.

What immediate corrective action should the project manager take?

A.

Discuss the issue with the virtual team members and revise the communications management plan.

B.

Escalate this issue to the virtual team members' supervisors.

C.

Add this issue to the risk management plan and take action if it persists.

D.

Discuss the issue with the project sponsors and add this as an issue in the issue log.

Full Access
Question # 247

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

A.

Forward the client's request to management as a change request to get formal approval.

B.

Document the information in the meeting minutes and share it with the project stakeholders.

C.

Draft a contract change with the desired scope changes and send it to the client for approval.

D.

Finish the current monthly release as it was planned and replan for the future months.

Full Access
Question # 248

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

PMP question answer

Full Access
Question # 249

A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk

materialized and the project time line had to be extended by 2 months.

Which two actions should the project manager take? (Choose two)

A.

Ask the team member to work overtime to make up the time lost so that the project schedule is not impacted.

B.

Analyze the impact of the issue and submit a change request to update the project schedule.

C.

Inform the project sponsor that the risk has materialized and request that the project budget be increased.

D.

Extend the project deadline and update the project schedule to reflect the delay.

E.

Log it in the risk register and work with the relevant owner to implement the mitigation action plan.

Full Access
Question # 250

An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?

A.

Meet with the project team to develop a proper resolution to the issue.

B.

Update the project artifacts to reflect the new deadlines reported.

C.

Request approval from the project sponsor to add more resources,

D.

Prepare documentation to explain the issue and communicate accordingly.

Full Access
Question # 251

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

A.

Increase the frequency of updates given to this stakeholder.

B.

Inform the team member to stop sending any further updates to the stakeholder.

C.

Raise this issue to the project sponsor in the next project status review meeting.

D.

Review this stakeholder's communication requirements.

Full Access
Question # 252

A project team member was unhappy with a new change in project governance and complained to one of the project sponsors. The project sponsor challenged the project manager.

How should the project manager resolve this conflict?

A.

Arrange a meeting with the project team member and project sponsor to discuss the change and obtain consensus.

B.

Discuss how to manage this conflict with the project management office (PMO) and let them decide how to resolve the issue.

C.

Explain to the sponsor why the change is required and get their support in forcing the project team member to accept the new change.

D.

Schedule a meeting with the project team member's functional manager and request the functional manager's support.

Full Access
Question # 253

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

A.

Map the lessons learned against work breakdown structure (WBS) components.

B.

Archive the survey responses with project artifacts for future projects.

C.

Use the information to restart the project.

D.

Evaluate the information collected on areas of improvement.

Full Access
Question # 254

A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the

project manager ensure that the needs of stakeholders are consistently met?

A.

Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.

B.

Add more iterative techniques to improve stakeholder learning.

C.

Identify all the critical stakeholders during the project initiation.

D.

Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.

Full Access
Question # 255

A startup company has just appointed a CEO that has no prior project experience. The CEO wants to execute projects with their own resources

and has appointed a project manager.

What should the project manager recommend that the CEO do first?

A.

Create a framework to justify project execution.

B.

Utilize an agile approach for all upcoming projects.

C.

Create a framework to support project success.

D.

Utilize a predictive approach for all upcoming projects.

Full Access
Question # 256

In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.

What should the project manager do?

A.

Coach the team member on how to keep work and personal issues scjparate.

B.

Ask the human resources (HR) manager to speak with this team member.

C.

Reallocate this team member's tasks to others for the immediate future.

D.

Understand the team member's personal issue and offer them support.

Full Access
Question # 257

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?

A.

Work with the procurement team to find alternative options.

B.

Contact the vendor that supplied similar equipment for a previous project.

C.

Use the existing equipment and replace it later with the new equipment

D.

Ask the project sponsor to expedite the vendor selection process.

Full Access
Question # 258

A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it.

What should the project manager have done to prevent this?

A.

Deployed to production after the first iteration

B.

Reviewed the compliance requirements with stakeholders

C.

Planned smaller iterations to review the results more often

D.

Implemented the authorization in the first iteration

Full Access
Question # 259

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

A.

Add 4 additional weeks to the schedule and request additional resources.

B.

Ask the sponsor to obtain a special work permit to continue work.

C.

Review the project management plan to see the impact of the possible delay.

D.

Crash the resource management plan to keep the schedule on track.

Full Access
Question # 260

A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the

scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,

among other critical blockers.

What should the project manager do?

A.

Request an additional resource to assist in solving all of the impediments listed by the team.

B.

Determine and agree when a situation becomes an impediment to be solved by the scrum master.

C.

Request the team review and prioritize the open impediments to resolve all of them as soon as possible.

D.

Push back, explaining that a self-organized team should address all of the problems to get the work done.

Full Access
Question # 261

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

A.

Reviewed the acceptance criteria and obtained client approval.

B.

Allocated a risk budget for any post-release improvements.

C.

Conducted a pilot to understand the client's performance parameters.

D.

Established meetings with the client throughout the project phases.

Full Access
Question # 262

While a project manager is trying to build the first baseline for a project, a change request is being sent from one of the functional managers. What should the project manager do?

A.

Discuss this with the functional manager and related parties.

B.

Reject the functional manager's change request immediately.

C.

Analyze the impact of the change request on the project.

D.

Apply for a formal change control board (CCB) approval.

Full Access
Question # 263

Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the

project manager support this team to succeed?

A.

Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.

B.

Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.

C.

Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.

D.

Work with the team members to define the overall objective and support them to engage around the goal.

Full Access
Question # 264

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

A.

Raise a change request.

B.

Purchase the application.

C.

Create a decision tree.

D.

Analyze assumptions and constraints.

Full Access
Question # 265

A project charter has been approved and the project manager has been assigned to the project. The project manager is currently working with the project team to subdivide the project work packages.

What is the project manager doing?

A.

Network diagram

B.

Decomposition

C.

Work breakdown structure (WBS)

D.

Resource leveling

Full Access
Question # 266

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team's engagement?

A.

Collect feedback from the team to discuss alternatives to enhance the communication.

B.

Conduct individual meetings to create a trusting environment with team members.

C.

Establish periodic face-to-face meetings and address the communication topic.

D.

Hold meetings in accordance with the team members’ preferences and availability.

Full Access
Question # 267

A team has just adopted an agile approach. During daily standup meetings, the team expressed concerns about task delays. The project leader worked with the product

owner to get clarity on the features. The project leader asked the team to fast-track all product features to ensure delivery. Sprints are being completed but with either fewer

features or low quality.

What should the project leader have done to ensure success?

A.

Directed teams to possible solutions that help in removing the impediments and contribute to a timely delivery

B.

Suggested to the team to add impediments as work items in the product backlog to be fixed in the next sprints

C.

Asked the team to create an impediment log and keep it updated for use in the next sprint planning

D.

Empowered the team to improve their processes, tools, and interactions to be more effective in delivery and removing impediments

Full Access
Question # 268

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

A.

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.

B.

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.

C.

Meet with the project sponsor and key stakeholders to assess each deliverable's value to the organization and set execution priorities.

D.

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.

Full Access
Question # 269

A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.

What should the project manager do first to address the SPI trend?

A.

Notify the project stakeholders that the scope needs to be reduced in order to hold the costs within budget.

B.

Engage with the project team to create a plan that will deliver benefits on a defined and incremental basis.

C.

Contact the project sponsor to let them know you require more resources to meet the schedule.

D.

Meet with the project scheduler to rebaseline the project using a more realistic schedule.

Full Access
Question # 270

A project manager analyzes the cumulative flow chart and identifies a bottleneck in the testing activities from a self-organizing team. After discussing it with the team, a gap related to testing skills is identified.

What should the project manager do to address the issue?

A.

Onboard a new project team member who has testing skills.

B.

Provide training to the entire team so they all will be able to perform tests.

C.

Support the team to identify an approach to resolve the problem.

D.

Ask the development team to slow down so the testers can catch up.

Full Access
Question # 271

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

A.

Project requirements, target benefits, issue log, metrics

B.

Target benefits, strategic alignment, time frame for realizing benefits

C.

Strategic alignment, benefits owner, risk register

D.

Target benefits, benefits owner, lessons learned

Full Access
Question # 272

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.

What should the project manager do?

A.

Assess the schedule impact and evaluate the most feasible solution to keep the project on track.

B.

Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.

C.

Initiate regular conference calls with the vendor for status updates to keep this item in focus.

D.

Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.

Full Access
Question # 273

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

A.

Reject the changes as the lead time is too short.

B.

Determine whether the project team is capable of making the changes.

C.

Review the additional changes and perform integrated change control.

D.

Check if the changes are covered in the statement of work (SOW).

Full Access
Question # 274

A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed

a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other

contracting jobs because they are not part of the project team.

What should the project manager do first in this situation?

A.

Report the issue to higher management and seek their direct involvement to complete the job from the contract department.

B.

Arrange a meeting with the contract department to build trust and commitment by recognizing their critical support to the project.

C.

Arrange several meetings with the contract department and ask them to contract the project as it is critical for project success.

D.

Communicate with the contract manager to commit a budget for the resources required for project execution.

Full Access
Question # 275

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.

What should the project manager do next?

A.

Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.

B.

Instruct the team to make only a graphical representation of all the data for the report.

C.

Instruct the team to conduct a meeting with the stakeholders before finalizing the report.

D.

Instruct the team to analyze and interpret the data before including it in the report.

Full Access
Question # 276

A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?

A.

Register a risk and escalate it to the project sponsor.

B.

Include the responsibility for acquisition with the core team.

C.

Detail the reason for the deliverable delay in the status report.

D.

Invite the stakeholders to discuss prioritization of a new deliverable.

Full Access
Question # 277

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

A.

Request a budget extension to get local resources experienced in agile.

B.

Plan to have the agile resources temporarily relocate to the project manager's location.

C.

Engage the agile resources through video conferencing on a daily basis.

D.

Advise the sponsor that the project will be delayed as agile training will be required.

Full Access
Question # 278

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

A.

Consult the risk response plan.

B.

Assign the tasks to another team member.

C.

Update the resource calendar.

D.

Issue a request to the change control board (CCB).

Full Access
Question # 279

A project to construct an electricity generation plant is on site near a nature reserve. An environmental activist group is questioning the need for

the project. The customer has informed the project manager to disregard the group as they are not in support of the project.

What should the project manager do next?

A.

Ask the customer to contact the activist group and let them know the project status and completion date.

B.

Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery.

C.

Obey the directive from the customer since they are funding the project and are the most important stakeholder.

D.

Request the project team disregard all communication from the activist group and continue with their project work.

Full Access
Question # 280

Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.

What should the project manager do?

A.

Assess and prioritize the impact of the new law on the project plan.

B.

Update the project plan because the law is an obligation for the project.

C.

Minimize the scope to catch the cost and schedule baseline.

D.

Meet the sponsor to ask for additional time and budget increase.

Full Access
Question # 281

After the merger of two large companies, a project manager is assigned to a project. The company hires a consultant to ensure best practices are

being used in information security. During an iteration, the consultant requests changes to a software component, claiming that it is not meeting

market requirements.

What should the project manager do?

A.

Continue the iteration and add the requested changes.

B.

Continue the iteration and review the change with the customer.

C.

Cancel the iteration and meet with the product owner.

D.

Cancel the iteration and add the requested changes.

Full Access
Question # 282

In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in

a couple of months. The licensing cost is significant.

What should the project manager do next?

A.

Evaluate the impact of nonrenewal of the license.

B.

Escalate the licensing issue to the product owner.

C.

Add a spike to the backlog for an alternative design.

D.

Raise a change request to secure the renewal.

Full Access
Question # 283

A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them. There are a few complex backlog items, and a new junior tester has identified a few compliance defects. The product owner and a couple of developers will be leaving the project team, and the contract with the test and production support partner will not be renewed.

Which issue should the project lead focus on first?

A.

Developing a new contract for production support.

B.

Finding a new product owner to prioritize the product backlog.

C.

Regulatory compliance issues discussed in the meeting.

D.

Recruiting, onboarding, and training new developers.

Full Access
Question # 284

A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.

What should the project manager have done to avoid this issue?

A.

The customer's requirements should have been captured in order to meet the customer's standards.

B.

The iteration review planning meeting should have been planned accordingly.

C.

The sprint retrospective meeting should have included necessary stakeholders.

D.

The customer's requirements should have been captured and modified to meet the supplier’s standards.

Full Access
Question # 285

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

A.

Create a risk register to track the risks and request additional budget.

B.

Analyze the impact against the release plan if the blocker is not addressed.

C.

Work with the project owner to prioritize the product backlog.

D.

Escalate the situation to the project sponsor for a possible resolution.

Full Access
Question # 286

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?

A.

Mitigate the risks that are applicable to the current and following iterations.

B.

Focus on the project deliverables rather than the documented risks.

C.

Agree that any issue can be handled when it becomes a problem.

D.

Acknowledge that the risks will be handled in the corresponding iteration.

Full Access
Question # 287

A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.

What should the project manager have done to prevent this?

A.

Incorporated sufficient schedule reserves based on similar delays in past projects.

B.

Appointed a senior environmental compliance officer to report directly to the project manager.

C.

Mapped environmental compliance requirements, identified risks to achieving them, and prepared mitigations.

D.

Approached the regulator for a partial waiver in light of the environmental importance of the project.

Full Access
Question # 288

An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.

What should the project manager do?

A.

Replace the members with new members who understand the system.

B.

Encourage the team members to make changes directly in the system.

C.

Ask the team to read through all of the available system documents.

D.

Encourage the team to hold a knowledge-sharing session in each iteration.

Full Access
Question # 289

A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The

resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.

What should the project manager do?

A.

Use the remaining time and resources to add additional scope to the project without spending the project budget.

B.

Ensure product quality by spending the remaining resources and time on additional quality checks for the product.

C.

Acknowledge the project closure criteria has been met and release the remaining budget and resources.

D.

Obtain approval from the sponsor to add additional functionality to the project deliverables with the leftover budget.

Full Access
Question # 290

A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.

Which estimation technique should the project manager implement in this context?

A.

Budget estimate

B.

Definitive estimate

C.

Story points

D.

Order of magnitude

Full Access
Question # 291

A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.

What should the project manager do?

A.

Discuss with the team how the project objectives can be met.

B.

Request that the sponsor increase the bonus for high performers.

C.

Schedule a team-building activity to boost the team's morale.

D.

Organize a team meeting to remind the team of the ground rules.

Full Access
Question # 292

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The

project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

A.

Requirements traceability matrix

B.

Stakeholder register

C.

Stakeholder engagement assessment matrix

D.

Issue log

Full Access
Question # 293

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

A.

Counsel both team members and caution them with a final warning.

B.

Escalate the issue to the human resources (HR) manager before a larger problem develops.

C.

Help cultivate self-awareness between the two team members through emotional intelligence (El).

D.

Relocate the two project team members into different project teams.

Full Access
Question # 294

A company recently adopted agile to develop innovation projects. The project manager is experiencing problems with some team members who consider some agile ceremonies to be unnecessary.

What should the project manager have done before the beginning of the project?

A.

Conducted a survey to determine if the team was willing to adopt agile ceremonies on the current project.

B.

Prepared an inception deck and clearly explained the purpose of agile ceremonies and their benefits to the project.

C.

Discussed with the product owner and requested assistance by requiring the adoption of agile ceremonies.

D.

Discussed with the project sponsor about convincing the team to adopt the agile ceremonies as part of their routine.

Full Access
Question # 295

A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be

engaged in how the project will be executed.

How should the project manager proceed?

A.

Create an environment where the agreement is reached by a majority vote.

B.

Create an environment where the agreement is reached through discussion.

C.

Establish recurring brainstorming sessions to discuss project issues.

D.

Allow team members to contribute ideas in a stream-of-consciousness mode.

Full Access
Question # 296

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government

official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include

aspects that the previous project sponsor did not support.

What should the project manager do next?

A.

Meet with the new project sponsor to review the current project scope and the requested changes.

B.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.

C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.

D.

Inform the new project sponsor that the new aspects will not be included in this project.

Full Access
Question # 297

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to

analyze team performance? (Choose two)

A.

0Project schedule

B.

Product backlog bumup chart

C.

Work breakdown structure (WBS)

D.

Cumulative flow diagram of completed features

E.

Burndown chart

Full Access
Question # 298

An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?

A.

Discuss this with the team and reprioritize the backlog to deliver maximum value by including a portion of the complex work.

B.

Reprioritize the product backlog by lowering the priority of the complex activity, so it will be worked on later in the project.

C.

Allow the team to focus and complete the complex work because it will reduce the risk of finding issues later in the project.

D.

Inform the customer that there will not be any deliverable due to the complexity involved in the requirement.

Full Access
Question # 299

A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial

department that is being delayed for a later iteration.

What should the project manager do to clarify the situation?

A.

Create an executive board to review the product backlog and replan the next iterations.

B.

Clarify with the CFO that the prioritization process is based on business value.

C.

Request support from the CEO on how to deal with the situation.

D.

Increase the size of the team in order to match any prior expectations of the CFO.

Full Access
Question # 300

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

A.

Organize an online distribution channel from another country.

B.

Ask the sponsor to authorize the launch and then wait for approval.

C.

Ask the board to use their influence and speed up the approval.

D.

Work with the team to find ways to bypass the regulations.

Full Access
Question # 301

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.

Which estimation technique should the project manager recommend?

A.

Planning poker

B.

Parametric estimating

C.

Three-point estimating

D.

Analogous estimating

Full Access
Question # 302

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

A.

Prioritize the projects, giving higher priority to projects that will increase profit.

B.

Make sure the project is fast tracked so that slipped time lines are recovered.

C.

Request that upper management hire additional staff to support the projects.

D.

Ensure that all of the projects are of high quality and are delivered on time.

Full Access
Question # 303

Midway through the execution of an agile project, there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?

A.

Prepare a user story to handle the change and assign it to the next iteration.

B.

Escalate to the product owner and cancel the upcoming iterations.

C.

Update the risk-prioritized backlog with the strategic change.

D.

Schedule a meeting with the team to assess the impact of the change.

Full Access
Question # 304

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?

A.

By scheduling iterative meetings with the product owner to improve project tracking

B.

By focusing on the delivery of incremental working products lo the customer

C.

By reviewing burnup charts to determine the effort required against estimated earned value

D.

By conducting daily standups to more accurately track project deliverables

Full Access
Question # 305

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

A.

Log the technical design delay as a risk in the project risk log.

B.

Set up a steering committee session to review the project delay.

C.

Continue with the approved design so that the project is not delayed.

D.

Ask the steering committee to approve a new technical design.

Full Access
Question # 306

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor

management team will not derive any benefits from the project. However, the project requires support from the vendor management head.

What should the project manager do next?

A.

Get support from the sponsor to hire a subject matter expert (SME) from the vendor management team to work on the project.

B.

Review the terms of reference of the steering committee to include the vendor management head.

C.

Work with the sponsor on a communications management plan to obtain support from the vendor management head.

D.

Obtain help from the sponsor to highlight any nonfinancial benefits for the vendor management team.

Full Access
Question # 307

A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization

and asks the project manager to pay attention to changes that can affect the project.

Which action should the project manager take to identify changes that may affect the product?

A.

Implement face-to-face communication between the team and product owner to change the iteration objectives as needed.

B.

Stop the iteration as soon as possible in case an external change that makes the product invaluable is identified.

C.

Take action to reprioritize the backlog after every iteration to evaluate if user stories are still valuable to the business.

D.

Apply a pair programming technique to react to changes immediately, even in the middle of the interaction.

Full Access
Question # 308

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not fo release the requested staff.

What should the project manager do first?

A.

Ask the leadership team for help obtaining the needed staff.

B.

Check with human resources (HR) regarding the availability of staff.

C.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

D.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

Full Access
Question # 309

A project manager is leading a project to develop accounting software for a trading firm. As the outcomes are being delivered, a new risk is

identified regarding an indirect tax regulation that is being changed by the government in the next 6 months. This risk will have a significant impact

on the project outcomes.

What should the project manager do next?

A.

Determine the impact of the risk and prioritize outcomes that do not affect the tax module.

B.

Delay developing the indirect tax module until the tax regulation comes into effect.

C.

Assess the impact of the risk with an expert and prioritize further outcomes with the client.

D.

Analyze the impact of the risk and discuss with the team to determine how to separate the tax module.

Full Access
Question # 310

An agile project manager notices that one of the team members is developing extensive knowledge in a specific matter. Other team members are

likely to require this knowledge in the future.

What should the agile project manager do?

A.

Ask the team member to develop more expertise and become a subject matter expert (SME).

B.

Ask the team member to provide a training session for the rest of the team.

C.

Ask the team member to produce a lessons learned document and share it with the team.

D.

Ask the team member to record highlights the team may want to know.

Full Access
Question # 311

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?

A.

Register a new risk in the risk management plan.

B.

Ask for additional resources and review the project estimate.

C.

Review organizational process assets (OPAs) and perform analogous estimating.

D.

Complete a bottom-up estimation for the project activities.

Full Access
Question # 312

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

A.

Ask the sponsor to increase the budget and schedule of the project to accommodate the additional scope.

B.

Encourage the sponsor to start another project for the additional location so that the current project is not impacted.

C.

Assess the impact to the scope and submit a change request for approval of the two locations before including them in the scope of the project.

D.

Discuss with the sponsor that the project scope is approved and it is not possible to include two locations as it will affect the budget.

Full Access
Question # 313

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,

but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities

planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

A.

Report that the project has not fulfilled all the expected functionalities.

B.

Complete the outstanding functionalities before informing the sponsor of the project progress.

C.

Communicate the benefit expectations and the action plan for the pending functionalities.

D.

Send an email with the monthly project progress to all relevant stakeholders.

Full Access
Question # 314

A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.

However, that tool is not available in one team member's country.

How should the project manager deal with this situation?

A.

Contact the project sponsor to have the team member removed from the project.

B.

Ask the team member to move to another location where the tool is available.

C.

Start the project and use email to communicate with the team member until the tool is available.

D.

Investigate alternative tools for virtual meetings that are available to all team members.

Full Access
Question # 315

A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the

equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.

What should the project manager have done to prevent this situation from happening?

A.

Defined the skill requirements more clearly in the scope statement.

B.

Asked the manager to follow the agreed-upon resource management plan.

C.

Conducted periodic reviews with the manager on resource availability.

D.

Consulted with the installation team on a regular basis to check for conflicts.

Full Access
Question # 316

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable.

What should the project manager do?

A.

Perform an impact analysis, readjust the schedule as needed, and communicate the changes to the customer.

B.

Ask the product owner to stretch the delivery team further to complete the final product in the original timeline.

C.

Inform the customer of the impact immediately and prepare for escalation.

D.

Request additional funding from the sponsor to obtain a new resource to fill in the gap.

Full Access
Question # 317

A project manager is working as a servant leader for a pilot project to adopt agile practices. After three sprints, the team demos the product to the

main stakeholders, but receives negative feedback about the product's features. The team feels that all the features met the acceptance criteria

defined by the product owner and does not understand what went wrong.

How should the project manager mitigate the product rejection?

A.

Share the product backlog for the main stakeholders to review in advance.

B.

Engage the main stakeholders in the upcoming sprint review sessions.

C.

Create dedicated sprints to implement feature fixes for the rejected ones.

D.

Ask the project sponsor to evaluate the assignment of a new product owner.

Full Access
Question # 318

During iteration planning, team A identifies that an important deliverable is dependent upon a deliverable from team B. What should the project manager do?

A.

Inform team B of the dependency and ensure that the deliverable is planned.

B.

Make team Aa part of team B and ensure that the deliverable is ready.

C.

Request team B to immediately start this activity and deliver to team A.

D.

Ask team B to focus on their backlog and deliver based on their priority,

Full Access
Question # 319

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

A.

Prioritize the item flagged as high business value and low complexity for this sprint.

B.

Support the team to move both items to the next sprint when the team will know more.

C.

Facilitate the discussion until the team reaches an agreement about the two items.

D.

Prioritize the item flagged as a dependency with low business value and high complexity.

Full Access
Question # 320

During sprint planning, the product owner wants to prioritize items with high business value. However, the project team is concerned about technical debt and infrastructure dependencies to deliver the expected value.

How should the project manager handle this issue?

A.

Support the project sponsor so the decision is made top-down and the team follows the provided direction.

B.

Support a voting exercise so all team members can express their opinion and the reason behind their vote.

C.

Support the product owner so only items with high business value are included in the next sprint.

D.

Support the project team so technical debt and infrastructure dependencies are included in the next sprint.

Full Access
Question # 321

The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.

What should the project manager do?

A.

Help engineer A to become familiar with this new role and ensure engineer B stays motivated.

B.

Promote engineer B instead since the project manager has the authority to make this decision.

C.

Request management approval that engineer B will be promoted if engineer A fails in this role.

D.

Coach engineer B to be prepared to perform this role if and when engineer A fails.

Full Access
Question # 322

A project manager is leading a large public project that will have a high impact on the town's citizens. How should the project manager define the different requirements?

A.

Include only the common requirements of each stakeholder group in the project goals.

B.

Include only the key requirements and keep the stakeholders informed about scope decisions.

C.

Analyze the interests and influence of stakeholders and evaluate their requirements.

D.

Add only the opinions of the team, because they know the objectives of the project.

Full Access
Question # 323

A project manager decided to use a highly adaptive approach to manage a large-scale project. In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members.

What should the project manager do next?

A.

Assign critical tasks to the most experienced team members.

B.

Review the budget with the team for the needed resources.

C.

Review lessons learned from similar projects with the team.

D.

Explain the higher-level objectives to be assigned to the team.

Full Access
Question # 324

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?

A.

Apply appropriate conflict resolution techniques to solve the issue.

B.

Call a team meeting to have a formal discussion of the issue.

C.

Allow the team to work through it on their own unless help is needed.

D.

Engage in individual conversation with each team member.

Full Access
Question # 325

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version

is not clear to the stakeholders.

What should the project manager do to increase value delivery?

A.

Use spikes to dig deeper into the technical challenges of the new product, thus reducing the technical risk.

B.

Create a visual task board with all of the relevant stakeholders to support backlog prioritization.

C.

Work with the team on the definition of a minimum viable product (MVP) and present it to the stakeholders.

D.

Gather the team to create a comprehensive product roadmap but only commit to requirements for the next quarter.

Full Access
Question # 326

A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers

arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.

Inform the relevant stakeholders.

B.

Inform the project team only.

C.

Inform the product owner.

D.

Inform the project sponsor.

Full Access
Question # 327

During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?

A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome

B.

Update the communications management plan and implement the change

C.

Meet with the project sponsor to discuss how to address the situation.

D.

Meet with the stakeholder prior to the meeting to obtain their opinion

Full Access
Question # 328

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)

A.

A lot of discussions that yield no results or possibly too many results

B.

A lack of direction and motivation for the team in the workshop

C.

Lessons learned from other teams to not be considered

D.

Time management plan for the retrospective workshop to not be updated

E.

A focus on the negative and a disinterest in further improvements

Full Access
Question # 329

A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.

What training should the project manager choose for their team to help with this situation?

A.

Communication training

B.

Negotiation training

C.

Emotional intelligence training

D.

Agile training.

Full Access
Question # 330

A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change

What should the scrum master do?

A.

Create a stakeholder engagement plan

B.

Design a communications management plan

C.

Update the team charter accordingly.

D.

Set up a meeting to discuss accommodations the team will have to make

Full Access
Question # 331

During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?

A.

Communicate the concerns to the project management office (PMO) during the weekly project reports

B.

Call for a team meeting to decide if the changes should be included

C.

Initiate the change request to modify the scope and adjust the timelines

D.

Conduct an impact analysis and present the results to the steering committee for approval

Full Access
Question # 332

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings

How should the project manager handle this moving forward?

A.

Ask that only key decision makers attend the project meetings.

B.

Update the project schedule to cater to this particular stakeholder

C.

Allocate time to gain buy-in from the stakeholder prior to key decision meetings.

D.

Update the risk register to consider the possible project impacts

Full Access
Question # 333

Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement

What should the project manager do next?

A.

Escalate the issue to the project sponsor and add it to the risk register

B.

Refuse to work on the project because management is not following standard project management practices

C.

Meet with management to explain the potential problems with running a project without a project scope statement

D.

Start the project with inputs from the project charter to save time

Full Access
Question # 334

Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them

What strategy should the project manager use to resolve this conflict in the meeting?

A.

Explain to the managers that the contradicting requirements are being considered for implementation in the project

B.

Explain to the managers that only one of the two requirements can be implemented, and submit a change request,

C.

Ensure that both managers understand the requirements and search for a solution that best satisfies this deliverable

D.

Request that the managers explain why each requirement must be implemented and decide by considering the cost and benefits

Full Access
Question # 335

The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project

How should the project manager alert the new project sponsor about these concerns?

A.

Send an email invitation to the project sponsor to attend all of the project team's weekly meetings, and hope the sponsor will find time to attend

B.

Send an email to the project sponsor summarizing the project status and key concerns, and request an immediate face-to-face meeting to discuss them

C.

Continue emailing updated project status reports highlighting the key risks and

issues, and wait for the project sponsor to request a meeting

D.

Complete a risk analysis outlining the delays and impacts, and email a copy of the risk register, urging the project sponsor to respond

Full Access
Question # 336

The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?

A.

A release burndown chart

B.

Analysis of the business requirements document

C.

Story points for the remaining user stories

D.

Surrogate measurements

Full Access
Question # 337

An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

PMP question answer

Full Access
Question # 338

During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?

A.

Retrospect frequently and suggest improvements.

B.

Incorporate a predictive approach for this element.

C.

Implement mitigation strategies for this element

D.

Request additional team members to help with improvements

Full Access
Question # 339

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

A.

Conduct a proof of concept to make sure there are no problems in the revised design

B.

Amend the design specifications and pass them to the development team for reprogramming

C.

Make a change request and get format approval from the project owner

D.

Inform the client of the problem and follow the change request process

Full Access
Question # 340

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively

What key activity is needed to ensure the project's success?

A.

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.

B.

Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution

C.

Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue

D.

Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities

Full Access
Question # 341

Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.

What should the project manager do when made aware of these issues?

A.

Ask for advice on how to be a better mentor to these team members.

B.

Set up a team building event to bring synergy back to the project team.

C.

Adjust the project manager's management style to better fit senior team members.

D.

Meet daily with each senior team member to monitor project status

Full Access
Question # 342

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

A.

Ensuring that the team is also focused on the overall change management plan

B.

Determining and aligning performance indicators that will help in assessing successful delivery

C.

Planning for regular project updates to cover the status of critical deliverables

D.

Ensuring that the scope management plan is in place to cover all related objectives

Full Access
Question # 343

During the last sprint review the product owner stated that the product does not deliver any value The project manager believes that the product meets all the provided specifications

The team is confused by the product owner's statement

What should the project manager do when using a hybrid approach?

A.

Escalate the matter to the executive board so they can decide on next steps

B.

Prioritize the project backlog and ask the development team to fix the issues

C.

Review the project's benefits management plan with the product owner.

D.

Ask the product owner to terminate the project as it is no longer aligned to the expected benefits

Full Access
Question # 344

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?

A.

Implement crashing to compress the schedule and improve the schedule performance index (SRI).

B.

Implement fast-tracking to compress the schedule and improve the SPI

C.

Perform conflict management using the project's resource management plan.

D.

Review the risk management plan to evaluate the probability and impact of these delays

Full Access
Question # 345

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team's efforts What should the project manager do in this situation?

A.

Work to understand the key stakeholder's concerns and provide feedback in regular project status reports

B.

Arrange an ad hoc meeting to address the key stakeholder's concerns with team members

C.

Reinforce with the key stakeholder that the project is performing on schedule\

D.

Escalate the situation to the project sponsor because the key stakeholder's behavior is impacting progress

Full Access
Question # 346

A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships

Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)

A.

Use the project's contingency budget

B.

Create a change request with the scope of the new internal projects.

C.

Influence the client to initiate a new project.

D.

Create a work breakdown structure (WBS) of the new scope with the internal projects

E.

Manage the quality of the delivery

Full Access
Question # 347

A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.

What should the project manager do to support the business analyst?

A.

Assign resources to coach the business analyst

B.

Ask the business analyst to focus on their work allocation for the needs of the project

C.

Create reports to inform the business analyst about the schedule and project cost

D.

Provide the business analyst with access to the financial and scheduling information

Full Access
Question # 348

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

A.

Exclude the activities from the roadmap

B.

Encourage working in pairs and knowledge sharing

C.

Teach the entire team the new skill.

D.

Facilitate a training event with an external trainer

E.

Increase the time estimates on the activities that require such abilities

Full Access
Question # 349

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Perform a risk assessment and define a risk response action plan.

B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Propose a pause in this phase to save labor costs and asset depreciation.

D.

Establish new partnerships with other suppliers in anticipation of any delays.

Full Access
Question # 350

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately

What should the project manager do to help ensure more collaboration between the teams?

A.

Organize regular meetings with all of the deployment teams to share issues and solutions

B.

Propose that some of the teams delay deployments in their countries

C.

Ask the project sponsor to appoint new managers for the deployment teams

D.

Ask each deployment team to provide a very detailed schedule and action plan

Full Access
Question # 351

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint

B.

Refer the product owner to the change management plan, then escalate to the steering committee

C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes

D.

Tell the product owner the issues will be addressed in the second version of the software

Full Access
Question # 352

In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?

A.

Ask the team member to enter this potential schedule delay in the risk register.

B.

Explain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges

C.

Actively listen to the team member and identify ways to support their needs in completing the tasks.

D.

Set up team-building activities with the project team members to reduce tension

Full Access
Question # 353

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?

A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.

B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain

C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.

D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue

Full Access
Question # 354

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?

A.

Ensure that the impediments are captured and prioritized based upon the highest valued features

B.

Estimate the financial impact of the impediments and request additional funding

C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment

D.

Capture the impediments and inform management that their assistance is needed

in resolving the impediments

Full Access
Question # 355

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals

What two options will help the team initially address this obstacle? (Choose two)

A.

Escalate the issue to the project sponsor.

B.

Review and update dependencies

C.

Schedule a retrospective.

D.

Conduct a root cause analysis.

E.

Create a risk management plan.

Full Access
Question # 356

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

PMP question answer

What should be the priority order in the product backlog?

A.

Risk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2

B.

Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2

C.

Requirements, Requirement 1, Requirement2

D.

Requirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2

Full Access
Question # 357

A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end

What action should the project manager take to motivate the project team’s performance?

A.

Send a formal notice to team members instructing them to maintain performance

B.

Hire a few temporary team members to help with the additional work

C.

Award certificates of appreciation to encourage the team

D.

Inform the team about the delivery pressure from the project sponsor

Full Access
Question # 358

A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?

A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project

B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register

C.

Refer to the stakeholder register from the previous project as it was similar to the current project

D.

Document in the risk register that the current project may have different

stakeholders than the previous project

Full Access
Question # 359

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register

What should the project manager do?

A.

Assign the documenting task to a project team member

B.

Ask the SME to document and capture the occurrence.

C.

Request the SME to wait until the project closure phase.

D.

Take ownership of documenting this information

Full Access
Question # 360

During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy What should the project manager share with the key resource?

A.

The updated benefits management plan

B.

The updated scope management plan

C.

The updated project management plan

D.

The updated communications management plan

Full Access
Question # 361

A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.

Using a hybrid approach, what techniques can be used to achieve this goal?

A.

Daily Scrum and product owner quality assessments.

B.

Scrum master reviews and the quality Kanban method

C.

Paired work and the customer role method.

D.

Time-boxed iterations and standup review meetings

Full Access
Question # 362

As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change

What should the project manager do?

A.

Conduct meetings with resistant members to facilitate smooth project implementation

B.

Meet with the team on a regular basis to ensure they are aware of changes.

C.

Influence the team to communicate any changes

D.

Check with the

Full Access
Question # 363

An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project

Drag the mitigation strategy on the left to the project manager's actions on the right

PMP question answer

Full Access
Question # 364

A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter

What should the project manager do?

A.

Modify the baseline of the project for minor impact changes to the project scope

B.

Use a focus group and brainstorming sessions to gather more details about the project scope

C.

Register the changes in the configuration management plan and send it to the change control board (CCB).

D.

Explain to the sponsor that these requests could endanger the schedule and cost of the project

Full Access
Question # 365

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?

A.

Ask the human resources director to appoint a senior team leader

B.

Inform the project sponsor about the possible delay

C.

Directly manage the project team to avoid project delays

D.

Provide mentoring to the newly appointed team leader

Full Access
Question # 366

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?

A.

Tell the junior team member that the information is available in lessons learned

B.

Offer guidance and follow up with some developmental activity for the junior team member

C.

Inform the junior team member that risk mitigation is not part of their work

D.

Refer the junior team member to the senior team member who develops the risk mitigation strategy

Full Access
Question # 367

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?

A.

Reviewed the communications management plan before inviting an external client representative to the meeting

B.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting

C.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register

D.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting

Full Access
Question # 368

Drag the to the correct scenario on the right

PMP question answer

Full Access
Question # 369

After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

A.

Share the customer feedback with the project team

B.

Follow the meeting agenda and make a list of the next deliverables

C.

Document this feedback in the meeting minutes.

D.

Start planning how to improve the dates of next deliverables

Full Access
Question # 370

A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client’s decision to keep the project active? (Choose two)

A.

Alternatives analysis

B.

Voting

C.

Cost-benefit analysis

D.

Multi-criteria decision making

E.

Autocratic decision making

Full Access
Question # 371

The following table shows the business value created and the development effort required to implement various features in a product

PMP question answer

Which feature should the team prioritize first? Enter the feature name in the box below

PMP question answer

Full Access
Question # 372

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics

1,600 rpm (rate-per-minute) -> stops working and crashes the system

1.500 rpm (rate-per-minute) -> warns of max rate allowed

1.400pm (rate-per-minute) -> reduces the power and brakes the engine

Which of the following statements is correct?

A.

0 1,600 rpm is a project risk,

1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project issue.

B.

1,600 rpm is a project issue,

1,500 rpm is an event that triggers a response strategy and 1,400 rpm is a project risk

C.

1600 rpm is a project issue; 1,500 rpm is a project risk; and

1,400 rpm is an event that triggers a response strategy

D.

1.600 rpm is an event that triggers a response strategy.

1,500 rpm is a project issue and 1,400 rpm is a project risk.

Full Access
Question # 373

A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year

Which project approach suits the scenario?

A.

Execute it as a Scrum project

B.

Execute it as a predictive project

C.

Execute it using the same approach as the reference project

D.

Execute it as a project with stage gates

Full Access
Question # 374

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?

A.

Hold a stakeholder meeting to align timelines and scope expectations.

B.

Crash the schedule to shorten the timeline while keeping the scope unchanged

C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.

D.

Reduce the scope of the project by removing activities and shortening the timeline

Full Access
Question # 375

In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?

A.

Assign the tasks to another resource, and ask the resource to work double shifts

B.

Update the schedule to reflect the project's changes in duration

C.

Ask human resources (HR) for a replacement, and update the nsk register

D.

Update the resource management plan and resource allocation chart accordingly

Full Access
Question # 376

The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?

A.

Ask the team to work overtime to complete the deliverable on time

B.

Evaluate the situation and identify ways to compress the schedule without impacting baselines

C.

Check the scope to verify if there is scope creep and get the project on schedule

D.

Submit a change request to the project sponsor to change the schedule

Full Access
Question # 377

The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.

What two actions can the project manager take to be more cost effective? (Choose two)

A.

Conduct a stakeholder analysis.

B.

Reinforce team communication.

C.

Update the project management plan with the new timeline

D.

Adopt an incremental approach

E.

Leverage work between team members

Full Access
Question # 378

After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.

Which technique will help the project manager to accelerate the deliverable?

A.

Impact mapping

B.

Rolling wave planning

C.

Collective code ownership

D.

Scrum of Scrums

Full Access
Question # 379

The project manager has learned that the project sponsor is unhappy with the development of the project requirements In order to realign the project with the sponsor's expectations, what should the project manager do?

A.

Review the project goal diagram with the team.

B.

Perform a stakeholder evaluation

C.

Confirm which templates the team should be using

D.

Review the risk management plan

Full Access
Question # 380

During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work.

What should the project manager do next in this situation?

A.

Review the project scope and negotiate with the contractor

B.

Refuse the offer as it is included in the initial project scope

C.

Review the project costs and communicate this to the project sponsor

D.

Submit a change request to approve the offer

Full Access
Question # 381

The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay’

A.

Update the stakeholder engagement plan

B.

Review the latest project status report and update the stakeholders

C.

Escalate the case to the customer's management team

D.

Issue the project payment invoice to the customer in advance

Full Access
Question # 382

One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager Because of the missed deliverable, the critical path of the project is extended

What should the project manager do next?

A.

Start an audit of the vendor's processes and procedures

B.

Review lessons learned from previous projects with this vendor

C.

Make a detailed analysis on vendor issues during the project

D.

Execute a contingency plan to address the issue with the vendor

Full Access
Question # 383

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control

How should the project manager report the project status to key stakeholders?

A.

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results

B.

Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget.

C.

Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control.

D.

Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away

Full Access
Question # 384

A project manager is appointed for the deployment of a new solution The solution will be integrated into the environment by a third-party vendor This vendor just announced a delay in delivering a key component, which will impact the project schedule.

What should the project manager do?

A.

Ask for expedited delivery of the component to mitigate the risk of schedule delays

B.

Ensure that relevant stakeholders and expectations are identified and assess the component delay

C.

Perform a detailed analysis of the release content for each component of the solution.

D.

Propose a new design of the solution to replace the external component with an internal one

Full Access
Question # 385

A project manager is managing a project which has a very complex and long execution period Although the project is mostly predictive, the team was able to break the design and execution into smaller packages using a hybrid framework The business wants to keep track of the value delivered by this framework application but there is no defined set of measurable items for the framework.

What should the project manager do first?

A.

Work with the stakeholders to determine which measurable benefits can be tracked and assign an accountable person to monitor and report them

B.

Create a report based on the work breakdown structure (WBS) and update it on a regular basis.

C.

Use the same benefits tracking process from the last predictive project and add this to the monthly status report

D.

Research which templates of reports were used the most for this framework and incorporate them into the project

Full Access
Question # 386

During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?

A.

Conduct an expert judgment evaluation.

B.

Review the quality management plan

C.

Update the lessons learned register

D.

Review the risk management plan

Full Access
Question # 387

Drag the organizational characteristics on the left to the correct scenario on the right

PMP question answer

Full Access
Question # 388

A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?

A.

Seek extra funding approval with the sponsor to replace junior team members for more experienced ones

B.

Create a reward system granting incentives to the team members who are able to catch more defects

C.

Hire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.

D.

Use the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems

Full Access
Question # 389

for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier To stay on schedule, the vendor proposed replacing the sub- supplier's component with a similar part that is different from the one that is stipulated in the project specifications.

What should the project manager do next?

A.

Accept the proposed replacement in order to keep procurement activities on track

B.

Insist on using the component per the project specifications and air freight the equipment to mitigate the delay

C.

Instruct the vendor to use the part that is compliant with the project specifications and update the schedule

D.

Consult with a subject matter expert (SME) to see if the proposed change is

acceptable

Full Access
Question # 390

A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.

What should the project manager do?

A.

Speak with peers about the need for a project charter

B.

Develop the project charter and send it for approval

C.

Explain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities

D.

Agree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan

Full Access
Question # 391

During the course of a project, the project manager wants to ensure that the work carried out and the product being created do not deviate from the prescribed business value.

What should the project manager pay special attention to in order to achieve this goal?

A.

Reviewing and updating the requirements management plan

B.

Carrying out quality audits and failure analyses

C.

Monitoring the work breakdown structure (WBS)

D.

Monitoring and updating the benefits realization plan

Full Access
Question # 392

A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?

A.

Mark the product backlog completion status and update the communications management plan.

B.

Ensure that knowledge transfer activities are executed as planned

C.

Release the resources and plan for a project completion celebration.

D.

Hold a steering committee meeting to inform them of the project completion

Full Access
Question # 393

A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog

What should the project manager do?

A.

Push the team to deliver more so that the modules are developed and rolled out according to management's request

B.

Speak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined

C.

Have the team work toward the tighter deadline so that integration will be easier.

D.

Speak to the team and slow the current pace to ensure the team is in alignment with the release date

Full Access
Question # 394

During a project’s third iteration, two of the existing team members were replaced As the project entered the next iteration, the team velocity dropped and the performance started to slip.

What should the project manager do?

A.

Guide the team to revert back to the forming and storming stages

B.

Escalate the issue to the project sponsor.

C.

Convene a team building event to address key performance indicators (KPIs).

D.

Discuss the decrease in productivity with human resources

Full Access
Question # 395

Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated'?

A.

The project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate

B.

Budget estimates are provided based on the experience of the sponsor, product owner and team facilitator

C.

The team facilitator uses historical data and arrives at an estimate based on the nature of the project.

D.

The product owner obtains all project details and based on the team's experience and velocity provides a budget estimate

Full Access
Question # 396

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?

A.

Switch to a Kanban approach, implementing features on a first-come, first-serve basis, fostering a sustainable pace

B.

Review the velocity of the team over the last several sprnts and adjust the plan accordingly

C.

Ask the project sponsor to approve overtime to compensate for the lack of performance while adjusting the plan

D.

Replace junior team members with more experienced ones and negotiate the project scope to compensate for the budget gap

Full Access
Question # 397

A project manager is involved with a project to remodel a long-used product. There are no proper records for the original design and execution of the original product. The stakeholders doubt that the remodel can be accomplished without this information and are hesitant to provide support for the project.

What should the project manager do?

A.

Acknowledge the stakeholders’ concerns with open dialogues and realign the project with stakeholder requirements and past lessons learned.

B.

Solicit a larger reserve for cost and time and manage the stakeholders’ expectations.

C.

Create a plan to inform stakeholders on the progress so they are able to see that the project can succeed,

D.

Share the threats of not updating old solutions and ask stakeholders to be patient with any inconveniences.

Full Access
Question # 398

A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.

How should the project manager plan and manage the project?

A.

Refuse to manage the project as there is too much risk in developing this kind of project without a product owner.

B.

Define the project's requirements, prepare a long-term detailed plan, and manage the project according to it.

C.

Convince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,

D.

Agree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.

Full Access
Question # 399

A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.

What should the project manager do?

A.

Assign an experienced resource to support the team member

B.

Escalate the team member's performance to the project sponsor

C.

Ask the team member to learn the new system as on-the-job training

D.

Issue a change request to extend the project schedule

Full Access
Question # 400

The project team is planning a schedule with limited information. The team |s having

issues identifying the detailed tasks and estimating task durations.

Which three techniques should the project manager use? (Choose three)

A.

Rolling wave planning and an adaptive approach

B.

Relative estimation to determine the task or deliverable sizes

C.

Iterations and reviews to continuously keep adapting the plan

D.

Bottom-up estimating based on a work breakdown structure (WBS)

E.

Gantt chart that includes milestones and deadlines https://www.projectmanager.com/blog/project-management/planning-techniques-for-projects

Full Access
Question # 401

A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project

What should the project manager do?

A.

Start planning the project and then request that a PMO be implemented in the organization

B.

Request that the implementation of a PMO be executed in parallel with the project

C.

Provide project management training to only the internal team involved m the project

D.

Provide project management training to the stakeholders and explain their responsibilities

Full Access
Question # 402

A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.

What should the project manager do?

A.

Recommend to the PMO that it is not the right time to start implementing new tools for projects.

B.

Include the use of tools and monitoring of their benefits in regular status reports and the communications management plan.

C.

Prepare a change request and seek approval from the steering committee regarding the new project framework.

D.

Bring in a third-party company to develop and implement a hybrid framework for this specific project.

Full Access
Question # 403

A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

A.

Meet with each team member separately and apply an appropriate approach with each one.

B.

Approach the project sponsor and request help in discussing the project deliverables with team members.

C.

Explain to the team that the project manager is ultimately responsible for the delivery.

D.

Assign multiple managers to the various teams and delegate all of the tasks to them.

Full Access
Question # 404

A predictive project team come across a scenario where they need to use some agile tools and methods. However, they did not feel this was appropriate since their organizational project management processes did not mention this.

What should the project manager do in this scenario?

A.

Ensure the project team follows the organizational project management processes.

B.

Create a change request to include the agile methods and proceed to implementation,

C.

Work with the team to determine appropriate project methods and practices and implement them.

D.

Prepare a summary and escalate this issue to the project's change control board (CCB),

Full Access
Question # 405

A project manager needs the team to define the steps and identify the risks of migrating data to a new system.

What type of leadership should the project manager use to accomplish this?

A.

Laissez-faire

B.

Transformational

C.

Dynamic

D.

Servant

Full Access
Question # 406

A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented

What should the project manager do?

A.

Ask the team member to learn the new system as on-the-job training

B.

Issue a change request to extend the project schedule

C.

Escalate the team members performance to the project sponsor

D.

Assign an experienced resource to support the team member

Full Access
Question # 407

During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred

What should the project manager do to address this issue?

A.

Book one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates

B.

Check the ground rules of the meeting to review the initial agreement with the team members

C.

Identify one team representative to speak up during the daily meeting and share the team updates

D.

Use round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak

Full Access
Question # 408

A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager

believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the

technology.

What should the project manager do?

A.

Engage stakeholders to modify policies outlined by the PMO.

B.

Move forward with the project governance and inform the PMO.

C.

Discuss the proposed changes with the PMO.

D.

Disregard the initial procedures and follow the policies outlined by the PMO,

Full Access
Question # 409

In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?

A.

Facilitate a meeting with the stakeholders and product owner to clarify the new need,

B.

Update the acceptance criteria documentation to clearly reflect what was approved.

C.

Review the new requirement and update all the stakeholders accordingly.

D.

Ask the two key stakeholders to agree on the requirement based on a Pareto analysis.

Full Access
Question # 410

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?

A.

Ask the accounting manager to delegate a team member who can support the project.

B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,

C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,

D.

Begin discussions with other functional managers and meet with the accounting manager later.

Full Access
Question # 411

An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but

the agile coach and technical writer feel that is an inconvenient time for them.

How does the project lead ensure adherence to agile practices?

A.

Escalate to management that the agile process is not going to work and ask them to speak to the agile coach,

B.

Have two separate daily standups, one for the agile coach and technical writer and one for the agile development team.

C.

Have a discussion with the team on the approach and come to a decision on when the daily standups should be.

D.

Inform the agile coach that the daily standup will be at 10:00 am local time and ensure all parties can attend.

Full Access
Question # 412

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

A.

Ask the leadership team for help obtaining the needed staff.

B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.

C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.

D.

Check with human resources (HR) regarding the availability of staff.

Full Access
Question # 413

A project manager is a part of the project management office (PMO) and Is tasked with finding a reputable vendor to provide on-site support for their project. The project sponsor stresses the urgency of the need and suggests using a vendor they know to provide the support.

What should the project manager do given the urgency?

A.

Consult preferred vendors from the company.

B.

Perform research on experienced vendors in the market.

C.

Source vendors with extensive experience.

D.

Follow the company's standard vendor selection criteria process,

Full Access
Question # 414

One deliverable for a project is to translate and print materials for students every 2 weeks Printing services are available but without guaranteed time lines because other projects make a significantly higher profit and have a higher priority

What should the project manager do to mitigate the risk of not having the materials printed on time?

A.

Meet with the manager to set a high priority for printing the materials

B.

Create a change request to modify the print requirements

C.

Include a risk response in the resource management plan

D.

Purchase a high-volume printer specifically for this project.

Full Access
Question # 415

A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?

A.

Risk register

B.

Project schedule

C.

Change request

D.

Issue log

Full Access
Question # 416

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

A.

Assign the marketing executive's tasks to another project team member

B.

Review the executive's declining performance with human resources (HR)

C.

Show empathy and praise the marketing executive's strengths

D.

Make the marketing executive accountable for their work and output

Full Access
Question # 417

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

PMP question answer

Full Access
Question # 418

An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?

A.

Ask the product owner to stop accommodating further changes to the scope

B.

Leverage the product owner to monitor the external environment

C.

Accommodate the critical and urgent changes in the current iteration

D.

Suggest to the product owner to execute the changes in a separate project

Full Access
Question # 419

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget

B.

Engaged with the project sponsor to ensure support for the project manager's decision

C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped

D.

Convinced the functional manager to stop the activities that will run beyond the budget

Full Access
Question # 420

A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.

What should the project manager do?

A.

Create an opportunity (or the project team to recognize this developer

B.

Send a recognition email to the team and copy management

C.

Reward the developer according to their motivations and interests

D.

Print a recognition certificate and present it to the developer during a meeting

Full Access
Question # 421

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.

What should the agile leader do?

A.

Move the solution designer to another team.

B.

Review the process that resulted in this situation.

C.

Stop work until the design document is completed.

D.

Ask the team to document the design.

Full Access
Question # 422

A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members

Which three actions should the project manager take? (Choose three)

A.

Allow team members to resolve personal issues without involving the project manager

B.

Arrange and conduct team-building sessions to improve team effectiveness

C.

Obtain feedback from the isolated team member to understand the situation

D.

Get feedback from other team members to understand what led to this situation

E.

Identify the isolated team member as a risk and document the situation in the risk register.

Full Access
Question # 423

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.

What should the project manager do?

A.

Ask the team to focus on and deliver only the agreed-upon features.

B.

Request additional budget because additional features are being added.

C.

Encourage the team to continue, as this will eventually help the customer.

D.

Ask the product owner to add the additional features to the requirements.

Full Access
Question # 424

An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?

A.

Review the process and remove the impediment

B.

Escalate this to the project director for a resolution

C.

Remove the certification need from the project scope

D.

Escalate this to the agile lead of the second team

Full Access
Question # 425

A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?

A.

Provide the team with a solution that solves the problem.

B.

Coach the team to solve the problem independently,

C.

Discuss the issue with the management team and provide a solution,

D.

Speak with the team lead about the issue and provide a solution,

Full Access
Question # 426

During a project meeting, the project manager asks risk owners to present issues that may affect the backlog. During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.

What should the project manager do to reduce exposure?

A.

Report the risk owners to the project management office (PMO) with the recommendation to remove them from the team.

B.

Reassign the outstanding risk tasks to other team members who have implemented their risk responses.

C.

Ask the risk owners to implement the risk responses before the next meeting and present the results in the meeting.

D.

Meet privately with the risk owners and work with them to address any impediments to the risk responses.

Full Access
Question # 427

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs

to be delivered to the customer as a ready-to-use product .

Based on this scenario, what should the project manager focus on throughout the project life cycle?

A.

Resource management and lessons learned

B.

Time management and stakeholder engagement

C.

Cost management and risk management

D.

Stakeholder engagement and lessons learned

Full Access
Question # 428

An agile team recently started working on a project for a financial institution. The

project sponsor is concerned that an agile approach will not provide enough support for the

organization's compliance standards.

In order to mitigate this risk and avoid problems, what should the project manager do?

A.

Propose using a compliance review board that will be responsible for approving all

product features prior to their release to the public.

B.

Liaison with the compliance group, making them responsible for understanding the

requirements and keeping them prioritized in the backlog.

C.

Meet with the compliance team and make sure that their requirements are covered in the

definition of done (DoD) for each story.

D.

Ensure that the peer review process also covers compliance requirements, creating a

second layer of security for the project.

Full Access
Question # 429

A project manager works at an organization that intends to use an agile delivery approach, The product owner asks the project manager what the benefit of agile delivery is from a project evaluation perspective?

How should the project manager reply to the product owner?

A.

The functionality is delivered early; therefore, more value is delivered.

B.

The team productivity is higher; therefore, more value is delivered,

C.

The cost is reduced: therefore, the total value delivered is higher.

D.

The risk is significantly reduced; therefore, more value Is delivered.

Full Access
Question # 430

A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment

What should the project manager do?

A.

Escalate the issue with an impediment to the project sponsor

B.

Use the contingency budget to implement schedule compression

C.

Implement the mitigation plans listed in the organizational process assets (OPAs)

D.

Reassess the issue as part of monitoring and controlling

Full Access
Question # 431

A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.

What should the project manager do first?

A.

Accept the feature.

B.

Determine if the feature is within the scope.

C.

Submit a change request! for the feature.

D.

Reject the feature.

Full Access
Question # 432

A project manager was recently assigned to a new project that is about to start. The

organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

A.

Create an issue log template that will be used to identify and track impediments.

B.

Create a contingency plan in case the project deviates from the initial plan.

C.

Create a schedule management plan to ensure the project meets the delivery date.

D.

Create an assumption log and map assumptions to impediments based on the impact to

the project value.

Full Access
Question # 433

A new project team has formed and the project manager notices that some of the team members do not feel comfortable being part of the project team As a result members of the team are working individually and not as a team

What should the project manager do to resolve this?

A.

Facilitate a team-building meeting to help this issue

B.

Allow the team members to remain in their former individual roles

C.

Directly guide the team members on how to perform their tasks

D.

Wait until some iterations are completed to intervene

Full Access
Question # 434

A project manager has considered a detailed and expensive training plan for a new technology for all team members. The training is needed several months into the execution phase of a project Surprisingly. many problems still appear that are related to the team members' lack of competence and the training costs are now negatively impacting the budget baseline

What should the project manager do next?

A.

Select resources who are more experienced with the new technology

B.

Perform a root-cause analysis to measure how the new training will address the issue

C.

Include in the risk register a risk of unskilled resources for the new technology

D.

Elaborate and socialize the team charter as per the resource management plan

Full Access
Question # 435

During project execution for an innovative product, a project team has been working hard to meet the deadlines. However, one of the team members will be leaving in 3 weeks and will be replaced with a new team member.

How should the team share tacit knowledge?

A.

Provide the new member with access to the knowledge database so all of the project documentation Is available.

B.

Have the team meet on a regular basis and share their experiences, challenges, and lessons learned.

C.

Ask the new member to document all of the requirements so a better understanding of the project objective is acquired,

D.

Provide the new member with the project documentation repository to allow the new member to review previous lessons learned, Owner

Full Access
Question # 436

A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new

Hems

Match the risks on the left lo the correct category on the right.

PMP question answer

Full Access
Question # 437

A client comes to the company asking to copy a project that was executed 2 years ago

in the same city, with the expectation that the new project will have the same cost and duration.

While finalizing the project management plan, the project manager realizes that the baseline

costs are much higher than the original project.

What could the project manager have done to avoid this?

A.

Verified applicable budget inputs related to this project

B.

Assigned the same project resources to this project

C.

Estimated a budget for the project's quality management

D.

Determined a budget reserve for this project

Full Access
Question # 438

A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.

How should the project manager resolve this conflict?

A.

Meet with all project stakeholders to identify how to implement the technology.

B.

Identify the disagreement in the risk register and develop a contingency plan.

C.

Update the project charter to align with the desires of the project sponsor.

D.

Negotiate with the project sponsor to develop a mutually beneficial solution.

Full Access
Question # 439

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?

A.

Review the iteration backlog because the product definition has changed and needs to

be reassessed before continuing the project.

B.

Continue work and ask the product owner to assess the changes and add/remove the

stories as needed in the backlog.

C.

Ask a business analyst to assess the changes and then add/remove the stories in the

backlog and prioritize them by business value.

D.

Ask the product owner to add new changes to the bottom of the backlog in order to

handle the modifications as a change request.

Full Access
Question # 440

A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?

A.

Request action from the functional manager regarding the team members poor performance

B.

Avoid selecting the team member to the next project that has an iterative design stage

C.

Provide feedback and coach the team member during the iterative design stage

D.

Escalate the issue to the human resources manager and request that the team member be replaced

Full Access
Question # 441

A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.

What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?

A.

Schedule a training course for the new team member to fill in their gaps in experience.

B.

Log this as an issue in the project issue log and speak with the resource manager.

C.

Provide weekly feedback to all project team members, including the new member.

D.

Ensure that coaching meetings are in place for this team member within the project timeline.

Full Access
Question # 442

A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?

A.

Colocate the team members

B.

Perform team-building activities

C.

Review and reassign tasks

D.

Revisit the communications management plan

Full Access
Question # 443

A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is

on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.

What should the project manager do?

A.

Contact the design team manager and ask to reconsider the priority list based on the latest situation,

B.

Meet with the designer to share the current status and develop a solution to complete the task.

C.

Meet with the design team manager to inform them of the current status and request an additional designer.

D.

Ask the software engineer to move forward without completing the important feature.

Full Access
Question # 444

A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.

What should the project manager do?

A.

Escalate the issue to the procurement team as the final delivery date of the project will be impacted.

B.

Review the project scope with the stakeholders and remove the potentially delayed item from the scope.

C.

Plan the task delivery with the contractor or vendor, highlighting the criticality of the current situation,

D.

Check with procurement to see if there is another previously used contractor who can develop the task.

Full Access
Question # 445

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

A.

Request help from human resources to keep the key team members on the project.

B.

Work with the project sponsor to determine an appropriate response.

C.

Ask to meet privately with the senior-level executive to discuss the matter further.

D.

Discuss the incident with the key project team members.

Full Access
Question # 446

During a kick-off meeting at the start of project execution, the vendor presents a

migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.

What should the project manager do?

A.

Schedule a meeting with the director to provide proof of expertise so the client

stakeholders will trust the project team's decision.

B.

Schedule a meeting with the project sponsor to determine if it is appropriate to accept

the director's request to provide a decision.

C.

Confirm with the director that the client stakeholders will be made accountable for the

decision in the responsibility assignment matrix (RAM).

D.

Ask the client to initiate a change request to make the director accountable for the

decision.

Full Access
Question # 447

A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.

What technique is the project manager applying?

A.

Fast tracking

B.

Resource leveling

C.

Critical chain method

D.

Schedule crashing

Full Access
Question # 448

An agile team was hired to work on a public service project. The team received a

list of vague ideas about the business and now needs to understand, develop, and prioritize a

list of functionalities.

Who will be responsible for this task?

A.

Project owner

B.

Agile leader

C.

Agile team

D.

Product owner

Full Access
Question # 449

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

A.

Mass communication

B.

Push communication

C.

Pull communication

D.

Interactive communication

Full Access
Question # 450

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule

B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report

C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion

D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)

Full Access
Question # 451

A project manager is working on a cost-reimbursable contract from the client's side. During project execution the project manager notices a major deliverable is missing. The project manager raises this with the seller but the seller advises the project manager that the subject deliverable is not part of the contract. The project manager remembers negotiating and agreeing to this deliverable during the tender process but cannot find it in the contract

What should the project manager do?

A.

Request a change in the contract in order to add the deliverable

B.

Add this deliverable to the requirements traceability matrix

C.

Terminate the contract and commence the closeout process

D.

Look to see if the deliverable is described in the statement of work (SOW)

Full Access
Question # 452

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

A.

Change management plan

B.

Schedule management plan

C.

Scope management plan

D.

Cost management plan

Full Access
Question # 453

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

A.

Escalate the situation to the engineer's manager

B.

Request external training for the engineer

C.

Request external training for the engineer and designer

D.

Allow the engineer and designer to cross-train with each other

Full Access
Question # 454

During the project planning phase, a project manager called a meeting to discuss the

product backlog with multiple stakeholders who represent the end users in various capacities.

Only one executive manager attended the meeting.

What should the project manager do?

A.

Meet with each stakeholder individually to gather input to the product backlog and

begin project planning.

B.

Proceed with prioritization of the product backlog based on previous lessons learned

and complete the project planning phase.

C.

Reschedule the meeting to ensure the majority of stakeholders are present for the

product backlog discussions.

D.

Proceed with the meeting in order to keep the project on track and start prioritizing the product backlog.

Full Access
Question # 455

A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.

Which action should the project manager take?

A.

Ask the internal sales team to keep the customer informed of the delivered value

B.

Evaluate various delivery options in order to immediately demonstrate value to the customer

C.

Inform the customer about the progress and update them on the final deliverables

D.

Wait for an important milestone to complete and then inform the customer of the progress

Full Access
Question # 456

A project team consists of members based in country A and subject matter experts

(SMEs) based in country B with a 12-hour time difference. What can the project manager do

to improve interactions between the team members in both countries?

A.

Ensure full participation of both the product owner and business SMEs in scope

planning sessions.

B.

Identify virtual communication methods and arrange for regular team meetings

accordingly.

C.

Explore the opportunity to have both teams colocated.

D.

Plan for frequent face-to-face meetings.

Full Access
Question # 457

In an agile team, some of the team members are coming forward to ask for more

autonomy on the project. What should the project manager do in this situation?

A.

Encourage the team members to make decisions.

B.

Discourage them as conflicts may be created.

C.

Encourage the team lead to make decisions.

D.

Discourage this request, as it is for the management team.

Full Access
Question # 458

In an ongoing project, stakeholders have been approaching team members for status

reports and changes without consulting the project manager. What should the project

manager do to ensure a successful project?

A.

Send the project charter to all stakeholders for information.

B.

Send an email to all stakeholders directing them to approach the project manager

directly.

C.

Review the stakeholder engagement plan and inform the stakeholders.

D.

Review the change management plan and ask the change control board (CCB) to be

involved.

Full Access
Question # 459

A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?

A.

Follow the risk response plan

B.

Use the contingency fund

C.

Prepare a change request

D.

Update the risk register

Full Access
Question # 460

A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office's (PMO's) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO's status reports have sufficient enough information

How should the new project manager proceed*?

A.

Continue using the outgoing project manager's status reports as well as their approach for schedule reporting

B.

Explain to the PMO that the hybrid project team needs to keep an agile approach for reporting and will not be complying with the organizational standard

C.

Change the status reports according to the template supplied by the PMO and proceed with scheduled reporting

D.

Meet with the project stakeholders to explain the need to comply with the PMO standards and update the status report format accordingly

Full Access
Question # 461

A project manager is leading a project that is on time and under budget. In the

weekly meeting with the team, the project manager finds out that one of the tasks due next

week does not have an assigned resource available for it. The resource is currently assigned

to another project.

What should the project manager do to manage the situation?

A.

Ask the procurement department to supply a different resource.

B.

Change the schedule according to the availability of the resource.

C.

Ask the sponsor to obtain the resource as originally planned.

D.

Contact the other project manager to request the resource.

Full Access
Question # 462

A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?

A.

Evaluate the project exit criteria in the project charter.

B.

Reach out to the senior executive sponsor for the project.

C.

Understand the project success criteria and objectives.

D.

Review the project status reporting for the latest information.

Full Access
Question # 463

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

Full Access
Question # 464

us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

PMP question answer

A.

Review project cost because the project is over budget and ahead of schedule

B.

Review project schedule and cost because the project is over budget and behind schedule

C.

Review project schedule because the project is under budget and behind schedule

D.

Review project scope because the project is under budget and ahead of schedule

Full Access
Question # 465

A project manager is leading a hybrid project. The self-organizing teams are

continually late in delivering their demos, resulting in low morale. The steering committee is

familiar with the reporting and planning associated with a predictive approach and is

concerned about the project because it is unclear if the expected value will be delivered.

What should the project manager do?

A.

Emphasize to the teams the importance of reaching the agreed deadlines and value.

B.

Request to coach the team to ensure motivated project team members are on board.

C.

Update the project schedule with a buffer to reflect the expected delays being incurred

by the team.

D.

Suggest to the teams to limit the scope of work per iteration so they will start to deliver

more reliably.

Full Access
Question # 466

A project manager is working with a team that is new to agile. One of the more

influential stakeholders struggles with the nature of agile. The project manager knows that this

stakeholder is needed as an advocate and wants to do everything possible to make the

stakeholder comfortable with the project.

What should the project manager include in the status report to illustrate the project's

performance?

A.

Results of the MoSCoW assessment

B.

Cost-benefit analysis

C.

Return on investment (ROI) analysis

D.

Earned value analysis (EVA)

Full Access
Question # 467

Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.

What should the project manager propose?

A.

Develop requirements and designs to support a faster product release.

B.

Emphasize the adoption of a predictive approach to minimize ambiguity.

C.

Recommend an agile approach so the project can be delivered iteratively.

D.

Outsource development of the product to a third party with more experience.

Full Access
Question # 468

The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?

A.

Ensure there are opportunities for the product owner to present project reviews to the stakeholders.

B.

Suggest that the product owner attend a training session about assertive communication.

C.

Suggest that the product owner shadow colleagues who are good presenters.

D.

Recommend a specialized article about delivering effective presentations to the product owner.

Full Access
Question # 469

The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?

A.

Schedule a time to negotiate a trade-off regarding the quality of the product with the customer

B.

Meet with the risk manager to identify potential threats related to the schedule delay.

C.

Set up a meeting with the project sponsor and submit a change request to the scope of the product

D.

Start the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations

Full Access
Question # 470

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.

B.

Schedule a meeting to discuss recent observations with the team member.

C.

Organize a team-building session with all of the team members.

D.

Consult the resource allocation matrix to see if the team member is still required for the

project.

Full Access
Question # 471

A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided

details to the customer 2 weeks ago and set up a weekly conference call to effectively

communicate with them, but the customer has not been participating in the calls.

How should the project manager handle this situation?

A.

Request a change in the contract to include the shipment in the project management

plan.

B.

Find the root cause of the issue and discuss the customer's current engagement.

C.

Inform the customer that subsequent packages cannot be manufactured.

D.

Request a delivery date extension from the customer

Full Access
Question # 472

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives

B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders

C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project

D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable

Full Access
Question # 473

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

A.

Contract negotiation

B.

Team assessment

C.

Mentoring and coaching

D.

On-the-job training

Full Access
Question # 474

A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project

How should the project manager report this cost?

A.

Estimate user story points and forecast a budget for that deliverable

B.

Determine the control accounts and use a top bottom estimate

C.

Consider the cost performance index (CPl) based on earned value (EV) divided by costs

D.

Calculate the budget at completion (BAC) based on the completed and planned features

Full Access
Question # 475

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

A.

Communicate the task assignments to the team members in a clear manner.

B.

Verify that the product owner has made the task assignments clear.

C.

Confirm that the agile coach has made the task assignments clear.

D.

Verify that the team members have made the task assignments clear.

Full Access
Question # 476

The change control board (CCB) has approved a change request to add a new

component within a product. The operations manager discovers the change after its approval

and complains that the implementation of the change will cause significant disruption to the

production line.

What should the project manager do first?

A.

Escalate the issue to the project sponsor, as the decision to add the component brings

many benefits even though it will be disruptive to the production line.

B.

Lead a root cause analysis workshop with the design team to identify the failures that

led to the decision to add a component that was not compatible with the production

line.

C.

Meet with the operations manager to explain the background for the change and

understand the operation manager's concerns about the change.

D.

Formally acknowledge the operation manager's concerns and raise a new risk that the

project may deliver late and over budget due to manufacturing difficulties.

Full Access
Question # 477

A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.

What should the project manager do?

A.

Include the new requirement in the next iteration of the software without informing the sponsor.

B.

Inform the team that the sponsor decided to reject any changes and release the software as is.

C.

Release the software as is and start a new project to deliver the new requirements.

D.

Collect the requirements of the regulation and follow the change control process.

Full Access
Question # 478

A project team is facing challenges understanding how to deliver a project's scope.

A senior subject matter expert (SME) from the organization's global office is in town for 1 week.

What should the project manager do to benefit from the SME's presence?

A.

Ask the SME to review the scope for alignment with the project charter.

B.

Organize a mentoring session with the team and the SME.

C.

Meet with the SME to discuss the current challenges the team is facing.

D.

Review the project scope statement with the SME.

Full Access
Question # 479

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

A.

Schedule meetings with all of the stakeholders to make business decisions when

needed.

B.

Share the project schedule, milestones, and meeting agendas with the stakeholders

ahead of time.

C.

Work with the available stakeholders to make business decisions and keep all

unavailable stakeholders informed.

D.

Add time reserve in the project schedule to allow extra time for the stakeholders to

make decisions.

Full Access
Question # 480

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

A.

Add the situation to the project risk register to be managed

B.

Identify competitors that are qualified to replace the current supplier

C.

Inform the purchasing department that manages the supplier relationship

D.

Use the issue log to record the situation immediately

Full Access
Question # 481

An organization is adopting an agile mindset. On the first agile project, the project

manager faced an issue because the team was unable to make decisions on time.

What should the project manager do to address the problem?

A.

Define clear guidelines on how decisions should be made under the new

organizational policy and reinforce them with the team on every occasion.

B.

Invite senior leadership to a team-building workshop and restate the importance of

accountability and leadership under the new company direction.

C.

Assess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.

D.

Adopt an autocratic leadership style and dictate all decisions in order to speed up the

team's velocity.

Full Access
Question # 482

The main project stakeholder was fired and replaced by another stakeholder. The

new stakeholder reviewed the project scope and requested numerous changes, arguing that

the stakeholder's team is unhappy with the results to date.

What should the project manager do?

A.

Put the new requirements in the backlog with high priority and implement the

requested changes.

B.

Put the new requirements in the backlog and submit a formal change request for

approval.

C.

Put the new requirements in the backlog and let the product owner check their value

and priority.

D.

Put the new requirements in the backlog with low priority and implement the requested

changes.

Full Access
Question # 483

The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?

A.

Advise the marketing director to receive formal training.

B.

Ask the marketing team members to coach their director.

C.

Train the marketing team and keep their director informed.

D.

Mentor the marketing director on the approaches.

Full Access
Question # 484

During a team meeting the project manager asks the team to complete a personality assessment to help everyone understand themselves and one another better. The project manager analyzes the results and realizes that more than one-half of team members are introverts

What should the project manager do?

A.

Present brainstorming topics a day before the session so the team can reflect and contribute more fully during the session

B.

Adjust the lighting and ambient sounds in the work and common areas to create a relaxing work atmosphere

C.

Ensure the team understands that their input needs to be fully articulated and explained to all team members during daily standups

D.

Require everyone to share personal details at the start of each team meeting to allow learn members to get to know one another

Full Access
Question # 485

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

A.

Ask human resources (HR) to coordinate another activity.

B.

Reassess the team situation and provide a proper solution.

C.

Inform HR about the situation and ask for support.

D.

Meet with the team to explain that conflicts must be addressed and solved.

Full Access
Question # 486

The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.

Which two things should the project manager do? (Choose two)

A.

Inform the customer that moving the milestone has a very high impact on project cost.

B.

Escalate the Issue to senior management so they can impose a solution on the customer.

C.

Convince the customer to keep the requirements as is and not move the milestone.

D.

Review the customer's priorities regarding the desired requirements for the milestones.

E.

Discuss which requirements can be delivered faster with the project team.

Full Access
Question # 487

A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.

How should the project manager handle this situation?

A.

Request to meet with the team member and ask that any issues be escalated separately.

B.

Reprimand the team member and provide immediate coaching on goal alignment.

C.

Proceed with defining the goals with the team members given the majority approval from the team.

D.

Approach the team member with empathy and obtain agreement through collaboration.

Full Access
Question # 488

A junior project manager is excited to start working on their first project with a telecommunications company, A senior project manager has decided to educate the junior project manager on the challenges of project management and how to achieve success.

Which three artifacts should the senior project manager tell the junior project manager to utilize to ensure project success? (Choose three)

A.

Organizational process assets (OPAs)

B.

Lesson learned registers from past projects

C.

Historical issue logs

D.

Project scope statement

E.

Project management plan

Full Access
Question # 489

An organization started the process of a digital transformation and is trying to change

its culture from a predictive to a more agile approach. The project manager leading the

change management process identified some knowledge gaps of key team members, which

could prevent the transformation from happening as planned.

What should the project manager do?

A.

Provide mentoring for the key team members on agile practices and support the team

with training and encouragement.

B.

Create an agile conduct guideline and ensure that all team members follow the rules

stated in the document.

C.

Replace the key team members with new resources who are already aware of the agile

mindset.

D.

Provide directions to the team members on how to accelerate the company's

transformation, bringing the project back on track.

Full Access
Question # 490

A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own

What should the project manager do?

A.

Improve the risk management strategy and risk monitoring

B.

Reach out to the project manager of the previous project for assistance

C.

Allow the team member to work through the issue as a training opportunity

D.

Share the lessons learned from the previous protect with the team member

Full Access
Question # 491

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

A.

Request additional developers to join the project team through the change cannot process

B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment

C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers

D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely

Full Access
Question # 492

During the planning for a long project, the project manager recognized that several

members of the team are new to their roles. How should the project manager incorporate this

into planning?

A.

Increase the overall project duration to account for the inexperienced team members

on the project.

B.

Ensure planning has accounted for replacing team members in new project roles who

do not deliver on project goals.

C.

Assess the training requirements and ensure time for professional development

training by senior members.

D.

Revisit the project resource allocation to remove the inexperienced team members

assigned to the project.

Full Access
Question # 493

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

A.

Motivate the team and deploy the necessary resources.

B.

Find a way to maintain the project schedule.

C.

Impose authority on the project.

D.

Request additional resources from the sponsor and motivate the team.

Full Access
Question # 494

A system migration project is in its closing stage. The project manager is being pressured to close the project The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification

What should the project manager do?

A.

Report the issue during the next status meeting at the end of the week

B.

Escalate the issue to the project sponsor and upper management

C.

Close out the project and tell the manager to open a service desk ticket

D.

Log the issue and assign it to the project team member(s).

Full Access
Question # 495

A project manager is working on a project that has strict deadlines and budget restrictions. The project manager realizes that in order to win the bid the company submitted a significantly tower bid than their local competitors leaving a thin profit margin. The client is constantly submitting change requests and. unfortunately, these change requests are stretching both the schedule and the budget

What should the project manager do?

A.

Instruct the team to accommodate the changes to the project

B.

Review the project charter to identify the agreed scope

C.

Negotiate the impact of these changes with the client

D.

Escalate the issue to senior management

Full Access
Question # 496

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

A.

Held a touchpoint with marketing before the demo to discuss any impediments

B.

Scheduled a demo presentation of the product during the first reason

C.

Asked the marketing team to start working on the product immediately

D.

Confirmed marketing requirements and constraints when adding to the backlog

Full Access
Question # 497

A project team is executing a project to replace an existing system with a new one.

A new project manager has been hired and observes that the team consist of professionals

who have worked with the older system, and others who have little previous experience.

What should the project manager do to ensure project success?

A.

Request a performance assessment for the team from the functional manager.

B.

Evaluate the current effectiveness of the team and define development needs.

C.

Allow each team member to use their individual strengths for project success.

D.

Assign team member roles and responsibilities based on past experience.

Full Access
Question # 498

The sponsor approaches the project manager with new features they want added to

the project. The project is 95% complete, but the sponsor insists that continued support for the

project relies on the addition of the new features.

What should the project manager do?

A.

Assess the impact of the features and refer it to the change control board (CCB).

B.

Implement the new features after assessing the impact.

C.

Reject the new features since it amounts to gold plating.

D.

Add the new features to avoid losing the sponsor's support for the project.

Full Access
Question # 499

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies

When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?

A.

During the risk register update

B.

During the retrospectives

C.

During each steering committee meeting

D.

During each iteration and review

Full Access
Question # 500

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

A.

Stakeholder analysis

B.

Resource needs analysis

C.

Accommodations assessment

D.

Team member assessment

Full Access
Question # 501

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

A.

Requirements analysis

B.

Retrospective

C.

Sprint planning

D.

Standup

E.

Backlog refinement

Full Access
Question # 502

A company made several changes recently, which resulted in a positive change in

the company culture. A project manager was just assigned to report to a new project

supervisor whose leadership style is about getting things done quickly regardless of employee

and operational impacts. Some employees are complaining about this.

What should the project manager do?

A.

Clarify expectations by explaining the company culture with the supervisor.

B.

Ask senior management to move the supervisor to a different project.

C.

Revisit the company's organizational culture.

D.

Instruct the employees to listen to the supervisor.

Full Access
Question # 503

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage

What should the project manager do?

A.

Investigate the impact of this issue with the team and survey the market for alternative wires with similar characteristics

B.

Stop the project and kick off another project to apply alternative wires for the machine

C.

Meet with the sales and marketing representatives and ask them to convince the manufacturer to reconsider

D.

Meet with the wire manufacturer to secure enough of the existing stock for the machine

Full Access
Question # 504

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

A.

Ensure that the whole team is appropriately recognized and organize a project farewell

party to celebrate the project success and closure.

B.

Update and close both the risk register and issue log with the latest updates, and save

them in the organization's project management information system (PMIS).

C.

Archive all the project documents following the organization's accepted practices so

the documents can be used in other future projects.

D.

Meet with the project sponsor and advise that the new project might be difficult to

undertake because the current project is not yet complete.

Full Access
Question # 505

While working on a poorly defined internal project, a project manager receives

multiple change requests from senior management. What should the project manager do first?

A.

Identify how the proposed changes will benefit the project in relation to the business

case.

B.

Ask for a temporary budget increase to avoid cost overruns.

C.

Keep the team motivated and incentivized to avoid exhaustion from working on a

lengthy project.

D.

Assess the schedule delay and begin implementation to avoid additional lags

Full Access
Question # 506

A team is given an agile project to build a conceptual product for a new customer.

While planning, the project manager is trying to determine the best way to show value to the

customer, as the technical requirements are not very detailed.

What should the project manager do to help the client understand the value delivered during

project execution?

A.

Include a planned value (PV) calculation in the sprint report for each build cycle.

B.

Conduct a customer demonstration at the end of each build cycle.

C.

Provide the customer with the refined specification during each build cycle.

D.

Show the customer a sprint burndown chart for each build cycle.

Full Access
Question # 507

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

A.

Negotiate the payments with the supplier and remind them of their long-term association

B.

Penalize the supplier according to the contract's service level agreement (SLA)

C.

Hire another information security supplier and incentivize them for speedy delivery

D.

inform the relevant stakeholders of this challenge and seek their support

Full Access
Question # 508

A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met

How should the project manager approach the stakeholder?

A.

Analyze the stakeholder's expectations and emphasize the topics of interest that may influence the project's success

B.

Post regular updates to the project teams board and email the stakeholder when they are posted so the stakeholder can review at their convenience

C.

Schedule regular review sessions with the stakeholder and the project team so the stakeholder can understand the status and engage with team members

D.

Continue to send status reports by email and schedule one-on-one sessions with the stakeholder so they are regularly debriefed on the project status

Full Access
Question # 509

A subcontractor informs the project manager that they are unable to supply a key

component to the project. What should the project manager do?

A.

Discuss the issue with the project sponsor and request extra time and budget to obtain

the component from a different supplier.

B.

Raise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response

C.

Submit a change request to the change control board (CCB) for changes to the

performance measurement baseline to obtain the component from a different supplier.

D.

Raise a new issue in the issue log and convene subject matter experts (SMEs) and

relevant stakeholders to identify alternatives to address the problem.

Full Access
Question # 510

A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.

What should the project manager do to avoid these challenges?

A.

Increase the project budget by 10% for team-related activities and awards.

B.

Plan to implement team-building strategies throughout the project.

C.

Ask the functional manager to motivate the team outside of the project.

D.

Colocate the team to encourage more motivational team activities.

Full Access