We at Crack4sure are committed to giving students who are preparing for the PMI PMP Exam the most current and reliable questions . To help people study, we've made some of our Project Management Professional (PMBOK 7th Version) exam materials available for free to everyone. You can take the Free PMP Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
During project execution, one of the project tasks is to create an important document for a service vendor. The project manager assigns a senior engineer to clearly detail
the service instructions to avoid any redo loops. Two days after the service information document was sent, the service vendor has doubts and needs more clarity on the task. This redo loop will probably cause a delay of one or more days.
What should the project manager do next?
The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could
resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?
In a project steering committee meeting, a few stakeholders raise concerns that the project manager ' s report shows that the outcome of the project is already in the market
while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.
What should the project manager do to avoid a reoccurrence of this scenario?
A project manager is leading a hybrid project for the development of denial equipment with live team members A dentist, who is also one of the major investors attends a sprint review meeting and raises questions and doubt about the concept and expected performance of the equipment
What should the project manager do?
During a project review meeting, several project team members expressed that they did not have an understanding of the benefits of certain features for the project What should the project manager do next?
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
A project manager just finished a meeting to identify the main stakeholders of the project. What should the project manager do next?
During the execution phase of a project, a project manager notices that the project team is not motivated and performance is decreasing. The decision is made to invest in financial rewards for all of the Key team members. After the rewards are distributed, the team is still underperforming.
What should the project manager have done to avoid this situation?
A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big
of an expenditure for the company to undertake.
What should the project manager do in the future when working on new product projects?
A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?
At a meeting, the project manager for an agile project indicates that the sprint goals were not met. The product owner leaves the meeting early. and the team discusses how the meeting went. Team members are confused as there were no defects for the new user stories and no new requirements were discussed.
What should the project manager do in the future to avoid this situation?
A project manager is working with a customer ' s team on a new project. Some product definitions and requirements are still not clear, but the customer wants to start
activities as soon as possible. The organization is also expecting product delivery for a specific date due to a regulatory requirement. Due to the nature of the project, the
project manager has decided to use a hybrid approach.
Why did the project manager choose a hybrid approach?
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a
result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?
A project is delayed due to multiple problems discovered during the quality review. Every time the team addresses one problem, additional problems are encountered. This is
frustrating for both the project team and the project sponsor, who are driven to meet the dates and results expected by the organization.
What should the project manager do?
A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?
After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What
should the project lead do next?
A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.
What should the project manager have done to avoid this situation?
A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master ' s program will coincide with the last phase of the project.
What should the project manager do?
A stakeholder is requesting that the project manager share project status updates
on a regular basis. This stakeholder is not included in the regular distribution list.
What should the project manager do?
A senior management team member contacts an agile project lead and mentions
that certain features the senior manager thought would be in the current release were not
included. What should the agile project lead do?
In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
A scrum team ' s daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically
last 45 minutes with many misunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?
A company ' s project management office (PMO) has started to implement iterative tools. The project manager is starting a new project and has
identified an opportunity to use the new tools. There is disagreement among stakeholders about the use of the adaptive tool.
What should the project manager do first?
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk
materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two)
A few new team members working on a public housing project are unfamiliar with the system. They do not understand how to evaluate residents applying for a subsidy to build a house, including the rules and criteria for applicant approval.
What should the project manager do?
After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?
A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.
What should the project manager do in this situation?
A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the
obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.
What should the project manager have done to avoid this issue?
A company is transitioning from a predictive approach to an agile approach. A project manager is assigned to the first pilot with an inexperienced team. Due to an unexpected event, the whole team is asked to work remotely. During the second sprint, the project manager starts to notice a lack of commitment from the team members.
What should the project manager do in this situation as a servant leader?
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.
Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two)
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the
company’s competitive advantage. What should the project manager do?
During an agile project a project manager lost one of the resources, and at the same lime, uncovered new requirements, which were added to the backlog What should the project manager do next?
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.
What should the project manager do?
A project manager is reviewing the lessons learned for an historical project. The review identifies that the client ' s engineer was adamant that they review all changes, even those not identified in the contract.
How should the project manager deal with this when planning the project?
Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information
should the project manager provide so that senior management can get a broader view of the project?
A project manager has been assigned to a hybrid project that must receive approval from a government regulator. During the daily standups, one
member reported an impediment that requires collaboration from an expert who is assigned to another project.
What should the project manager do first in this situation?
A complex project has a well-established responsibility assignment matrix (RAM). One of the critical stakeholders flagged a task as an issue because it was not completed and has remained open for some time.
What should the project manager do?
An IT company ' s office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a
critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining
that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.
What should the project manager have done differently?
A project sponsor is concerned that the scope is not being met correctly and has questioned several team members about this individually. When the project sponsor approached the project manager, the project manager realized that the issue was that the project sponsor understood the scope in a different manner than the project team.
What should the project manager do to address this issue?
A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.
What should the project manager do first?
A project manager is leading a hybrid project. The work breakdown structure (WBS) and the schedule were developed, but the project manager is having difficulty assigning specific resources to all of the project tasks.
What should the project manager do?
A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.
What should the project manager do to ensure value is delivered quickly?
During a team meeting, the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues.
A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.
What should the project manager do?
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
Close to the end of a project, a customer claims that some deliverables have not
been met and starts initiating change requests. What should the project manager do next?
A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

An agile team completes a deliverable that is to be certified by another expert team. The second team does not take the deliverable for many months.
What should the servant leader do?
During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that
could become unmanageable with time. What should the project manager do?
A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.
What should the project manager propose?
The investment committee is the authority for the approval of funding required for a business improvement project. The investment committee approved funding to complete
the preliminary feasibility study. The project is on an expedited schedule, and the project manager requires interim funding to continue with the preliminary feasibility
activities that must commence immediately.
How should the project manager get these funds approved?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
A project manager is using a centralized management and leadership style for a project. The project design does not meet the expected outcomes at later stages of the project.
What is the most important action the project manager should have taken to prevent this?
In a highly politicized organizational environment, the stakeholders are driven by their own operational or business goals, which results in
conflicting interests regarding the project. What should the project manager do to steer the stakeholders toward the collective project goal?
A project manager is assigned to a strategic communication project that involves
subject matter experts (SMEs), interns, and new recruits. The project manager discovers
that the project is not gaining much traction due to knowledge gaps from the interns. The
budget for training is exhausted and the project needs to be delivered without delay.
Which two actions should the project manager take? (Choose two)
During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific
component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality
management plan and there is no reference to this component.
What should the project manager do next?
A project manager receives a request for proposal (RFP) from a client. The client
is very clear about the requirements. A requirements analysis must be done in the first
month of the project, and the client wants to see a demo of the work completed every two
weeks.
What project approach should the project manager use?
Five vendors are contributing to a project with an impending deadline. Two vendors are behind on their deliverables and rarely provide status updates. What should the project manager do?
A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?
During the team’s daily meetings, the project manager notices that some team members are consistently experiencing blockers due to communication issues and misunderstanding process directions.
How should the project manager proceed in this situation?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
A project manager is managing a national rollout for an innovative product in a regulated environment that is expected to change. The project management office (PMO)
needs visibility of the regulatory constraints while maintaining a degree of flexibility.
Which tool can the project manager use?
An organization in a regulated industry has decided to switch from a predictive to
an agile delivery approach. It has been decided that the ongoing projects will adopt Scrum,
and the project manager is still accountable for the project outcomes. During the fourth sprint
demo, the customer notices that a feature is not compliant with the regulations.
What should the project manager do?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.
What should the project manager do?
A project sponsor is upset that a vital project might miss an agreed-upon delivery deadline. The sponsor asks the project manager to check whether the project team can do anything to deliver on time. What should the project manager do first?
An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they
are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.
What should the project manager do to get commitment from the sales agents?
During a project ' s initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion
What should the project manager do next?
A project manager is working on a major construction project. Part of the
agreed-upon plan was to use a cloud-based system with a server that runs on high-speed
internet service since most of the team members work virtually. The company needs to
reduce operating costs as much as possible and management insists that the project will
now use a system running on a conventional dial-up service.
What should the project manager do next?
A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of control to sign with the vendor responsible for migrating the systems.
How should the project manager address this situation?
A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?
An agile project is starting and the assigned team is new to agile During the first daily meetings, the project manager observes that the team is having problems meeting goals What should the project manager do?
A project manager is managing two agile teams and reviewing their metrics to find out which team is performing better. Which approach should be taken?
A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change
requests issued due to the nature of the project.
What should the project manager do?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
One of the main deliverables of a project is delayed due to a problem with a key provider.
What should the project manager do?
A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The
procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.
How should the project manager approach this project?
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.
What should the project manager do?
In the planning phase of a software implementation project, two of the team members disagree on how to approach end-user training. The
discussion has intensified and the team members are not able to agree.
What should the project manager do next?
A project using a hybrid approach to migrate from a current system to a new and
enhanced system is underway. The plan is to migrate the system in stages. However, the
operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
In the past, the project manager and the project team performed well using
predictive methodology. However, the organization recently decided to adopt agile
approaches, and the project sponsor wants to use an agile approach in an upcoming project.
Before initiating the project, what should the project manager do?
A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders
What document should the project manager use to communicate these requests?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.
What should the project manager do?
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.
What should have been done to avoid this situation?
A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?
After a project review meeting, a key stakeholder tells another stakeholder that they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation.
What should the project manager do?
A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?
A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with
significantly different cultures and will be staged over phases.
What should the project manager do next?
A project manager is working with an agile team. A key stakeholder who does not
join the sprint planning session is very unhappy, as the delivery date for the final product has
been pushed back three times. What should the project manager do?
The vendor for a new IT data center project failed to follow the required cabling standards as stated in the requirements specification. The infrastructure manager and vendor were involved in an argument about the issue.
What should the project manager do to resolve and prevent additional arguments?
During project execution, a key team member has to be moved to another critical project for the company. Currently, there is no other team member who can fill that role.
What should the project manager do first?
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?
Experienced team members assigned to a critical project are also supporting several other projects and this is delaying the critical project. If this critical project is not
delivered, the company could receive a fine from the government. What should the project manager do?
A project manager is leading a council ' s project that aims to ensure full compliance with health, ecological, and environmental standards.
At the same time, the project ' s goal is to remain fully adherent to the council ' s values, policies, and procedures.
How should the project manager ensure project success?
A project manager is managing a hybrid project A stakeholder has directly contacted a team member and has requested a change Due to the request, the team member was distracted from their work, which caused a loss in productivity.
What should the team member do?
Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)
A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.
What should the project manager have done to prevent this conflict?
A new facility project is being developed using a hybrid approach. After the third iteration, the project manager sees a decline in the team ' s productivity.
What should the project manager do next?
The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors
What should the project manager do?
A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.
How can the project manager convey these benefits to the stakeholders?
At the end of the last iteration, the customer rejects the deliverables since they did
not meet the customer ' s expectations. What should the project manager have been done
to prevent this situation?
A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area
What should the project manager do first?
Due to a recent budget reduction, two team members were released from an agile
team. The customer is still expecting early results for the project.
Which two actions should the project manager take to align customer expectations? (Choose
two)
A company is developing a new product. During project planning, a stakeholder from the legal department does not attend any of the project meetings and is not interested
in the product design.
How should the project manager deal with this situation?
A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards.
Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.
The company asked the project manager to explain the value gained by using an agile process.
How should the project manager respond?
A project manager is preparing a project closure report. The project sponsor is confident about the success of the project, but the client is not sure that the project outputs will achieve their business needs.
Which aspect should the project manager highlight in the closure report to address the stakeholder ' s concern?
A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?
In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.
Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.
What should the project manager do next?
On a project to create the perfect paper airplane, the development of the airplane Is performed In iterations. The artwork to go on the wings and tail is done using a predictive approach. One of the stakeholders provides a requirement that conflicts with the product owner ' s requirements.
Who is responsible for analyzing the new requirement and making the final decision?
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?
On a transformational project, the project manager is confronted with resistance
from the stakeholders. To overcome this and gain acceptance of the change, what should
the project manager do first?
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.
What should the project manager do?
A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor ' s style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
A project manager is leading a virtual team that is geographically dispersed. What
should the project manager do to avoid uncertainty in the project due to different cultures?
A project manager is managing a megaproject. The project stakeholders are from different geographical areas and have diverse cultural and social backgrounds. The project manager wants to improve team productivity to realize more effective and efficient results.
Which action should the project manager take?
A Scrum team working in an aircraft manufacturing company has completed Its first iteration for a critical project. It is very Important for the project sponsor to complete the project on time and under budget A burndown chart indicates that the project is behind schedule
Which two actions should the project manager take to manage Impediments and improve the team ' s velocity? (Choose two)
A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?
In the middle of a project, a business unit manager who regularly interacts with the project manager ' s team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.
After getting more information about the new manager, what is the project manager ' s next step?
A project manager notices that the team lacks a subject matter expert (SME) in a specific area. This expertise will be required for many future projects.
What should the project manager do?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
A junior project manager with experience in predictive projects has joined a company that uses hybrid approaches for project delivery. A senior project manager with experience in hybrid approaches is assigned to be a coach. Match the activity descriptions on the left to the correct tools on the right.

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
Two key team members suggest different options to prevent time overruns and delays. There is a conflict between these two team members because of their divergent views.
What should the project manager do next?
An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.
What should the project manager recommend?
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.
What should the project manager have done to avoid this situation?
An intern is replacing a critical resource midway through a sprint To help the intern get up to speed, the project manager assigns a senior engineer in the team as the intern ' s mentor Two months later, the project goes into critical status, delaying the release milestone by a month.
What should the project manager have done to avoid this scenario?
A project manager is working on a large project with a very difficult client. During
the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.
How should the project manager approach this?
A product owner has provided the team with a prioritized backlog for the initial
launch of a new product. After analysis, the team concludes that some work is missing to
support the initial launch and provides this information to the product owner. The product
owner acknowledges the missing work and adds it to the bottom of the backlog. The team is
not happy with the prioritization that the missing work received.
What should the project manager do in this situation?
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project The deliverables must be changed to align with the new quality standards
What should the project manager do?
In a project management team meeting, one of the team members always argues with the project manager about the objective, timeline, and deliverable of any assigned task.
What should the project manager do to manage this conflict?
The operations director complains to the CEO about the outcome of a project ' s first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log
How should this complaint be addressed?
An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.
What should the project manager of the ongoing project do?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project ' s key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
A project manager is assigned to oversee the deployment of a new product that
will be used by the entire organization. A key success factor for the project is the timely
and successful adoption of the new solution by all entities.
What should the project manager do to ensure the success of this critical project?
A project manager is responsible for providing a budget estimate for a long-term project that will be executed over several years. Which essential task should the project manager implement at this phase?
When reviewing the project team ' s performance the project manager realizes that the team velocity is not fast enough to meet the next review gate goal What should the project manager do?
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
An organization uses a hybrid approach to project management. A project manager has been assigned to an external project, project A, where two of the three modules in the project require machine learning skills. The only machine learning expert in the project manager ' s organization is engaged in an internal project, project B, that is about to end.
What should the project manager do?
A key agile project team member takes a leave of absence in the middle of an iteration and will not return to work for a while What should the project manager do next regarding the feature on which the team member was working?
A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?
The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.
What strategy should the project manager use in order to keep delivering value in a restricted environment?
An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country’s unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?
An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.
What should the project manager do to avoid this situation in the future?
A project lead conducted coordination meetings to estimate the budget and confirm the timeframe for a new project. Due to internal resource challenges, outsourcing some activities could be implemented during execution. What should the project lead ensure before submitting the project for a stage gate review to receive the needed investment?
A project is being planned with two hardware deliverables and one software deliverable that will be used to monitor the operation of the two hardware deliverables. When preparing the consolidated project schedule, what should be the top priority for the project manager?
A major issue regarding conflicting priorities has been highlighted by the project team with respect to a few stakeholder requirements.
What should the project manager do?
A project manager is assigned to a large complex project with cross-functional dependencies. The project enters a new phase requiring new stakeholders to be added with conflicting priorities. How should the project manager ensure successful engagement with the stakeholders?
A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed. What should the project manager do?
During a project audit, several risks are identified. The auditors realize that the team is having trouble quantifying and qualifying these risks.
What should the project manager do?
There are several dependent work streams in a project. Some of the project stakeholders feel that coordination among project team members and progress visibility are lacking.
What should the project manager do?
A project team member tells the project lead that expecting a similar delivery output for every day of the sprint is not realistic. The project lead reports this to the project management office (PMO). What should the project lead do?
An organization that is running several simultaneous projects suddenly experiences a surge of resignations, leading to a lack of talent. Consequently, some of the projects have been missing key milestones. What should the project manager do to recover from the delays?
A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?
A project manager is leading a project with a risk management plan detailing strategy and actions if any of the identified risks become an issue. One of the identified risks becomes an issue, but the project manager acknowledges that the response considered in the risk management plan may not be the best.
What should the project manager do?
A project manager is leading a project with a negative risk that has just become an issue. The risk has been recorded, and a response plan has been set. However, a project team member proposes a response that differs from the response recorded in the risk management plan, which the team member believes will be cheaper and equally effective.
What should the project manager do?
A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed.
What should the project manager do to deliver business value to the client?
A new project manager is taking over a project to deliver a new payroll management system that is running behind schedule. In addition, costs are rising due to many late changes requested by the client. What should the project manager do first?
A project manager is leading a complex project. The project stakeholders include individuals from different countries, cultures, and languages.
What can the project manager do to manage this diverse group of stakeholders?
It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some of the features are not meeting the iteration-level definition and must be placed back into the backlog.
What should the project manager do?
A team identifies a critical set of tasks that have not been included in the Kanban board, and there is not enough budget for the work hours needed to complete the activities. What solution should the agile project manager implement?
A project manager has been assigned to a project. The project deadline has been established but, based on the number of stakeholders to engage and interview, it will be difficult to complete the project within the timeline. How should the project manager address this challenge?
Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?
A project manager is leading a contract for a new market that was awarded to their company. The client wants to jump-start the market with the informal sector traders.
What should the project manager do?
An agile team of specialized engineers has completed some tasks later than planned and with a lower quality than expected. The situation is limiting the value the team is creating for the business. What should the project manager do next?
During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible. What should the project manager do first to address this?
A company started a project to create a new product that will be delivered in iterations. The artwork development plan included extensive consultation and validation before the build. The company changed the focus of the project to speed to market because one of their competitors announced the launch of a similar product. What should the project lead do?
A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when the project deliverables are considered complete.
How should the project manager respond?
A project manager is assigned to lead a team comprised of business executives. After several roadmaps were denied by the sponsor, the project manager asks to be removed from the project. The sponsor urges the project manager to find a solution as the sponsoring organization requested their assignment. What should the project manager do?
A project manager has just started a new project for an organization that dislikes budget and schedule deviations. The project stakeholders are very engaged and want to ensure there is clear visibility of the project’s risks and progress. How should the project manager handle stakeholder expectations?
A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately. How should the project manager approach the software development life cycle with this customer?
After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?
The project team embraces and encourages open communication and collaboration. However, the project manager is used to an approach based on the chain of command and formal hierarchy.
What should the project manager do?
During project implementation, a critical performance issue is identified by team members. What should the project manager do?
A project manager is executing a project on time and on budget. Before a stage gate review, the project manager receives the regular business management report, but this time it indicates a negative impact on the project success factors. What should the project manager do?
A project manager is in the beginning stages of delivering a project and is assessing and prioritizing identified risks. What should the project manager do next?
After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?
An ongoing project is facing a challenging situation where the customer is not satisfied. The team is new to agile development and frequently communicates with the customer and gives regular status reports. What should the project lead do to satisfy the customer?
Near the closing stage, a project is delayed due to staff shortages. In order to meet the mandatory deadline, additional resources are necessary, but there is no additional budget.
What should the project manager do first to obtain the funding to hire the needed resources?
A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?
A project manager has been assigned to a new agile project with a lot of rapidly changing knowledge areas.
How should the project manager manage knowledge transfers on this project?
An agile project team is working on a large project involving multiple cross-functional teams in different geographical locations. Some team members are not clear on the next tasks.
Which strategy should the project lead implement to help the team?
There are several dependent work streams in a project. Some project stakeholders feel that coordination among team members and progress visibility are lacking. What should the project manager do?
A product is facing performance issues that will significantly decrease the manufacturing yield expected, increasing the cost. This will be an issue as it will limit one of the high-margin contracted goals. Because it is a breakthrough development, the speed to market is key. What should the project manager do?
A project manager is working on a project. A few months after the project has launched, the project manager starts receiving complaints from business unit managers about the lack of updated project information. What should the project manager do?
A project team has deployed an email marketing campaign across different countries. In one country, the end users have been opting out of the campaign because they think the email is spam. What should the project manager do first?
A key stakeholder asks the project manager to complete all deliverables sooner than the agreed-upon schedule. The project is halfway complete and currently has a schedule performance index (SPI) of 0.9 and a cost performance index (CPI) of 1. What should the project manager do first before committing to the stakeholder?
A complex project is being developed in phases as per the original plan. Half of the systems have been handed over to the customer for operational use. There is no delay in the schedule. However, the customer is still not happy because some of the systems handed over are no longer useful due to changes in the environment. What should the project manager have done to avoid this?
A project manager notices a product owner has been unresponsive over the last few weeks. During one-on-one sessions, the product owner is unable to provide complete information, leading to rework of the project stories. What should the project manager do first?
A new project includes important product features that should be delivered as soon as they are completed during the following quarter. The project team consists of junior and senior technicians.
Which two actions should the project manager take to deliver product features as soon as possible? (Choose 2)
A project sponsor is transitioning their division to an agile environment and has emphasized that project team members and stakeholders should collaborate to achieve deliverables. On a few occasions, progress has been interrupted by one stakeholder who is unfamiliar with agile approaches. What should the project manager do first?
During a blueprint review meeting, the finance department representative is not comfortable with a proposed solution that favors another department. As a result, document approval is delayed, which impacts the project schedule.
What should the project manager do?
A project manager is leading a project with a negative risk that has just become an issue. The risk was recorded and a response plan was set. However, a project team member proposes a response that differs from the response recorded in the risk management plan and believes it will be cheaper and equally effective. What should the project manager do?
A project is in its fourth iteration out of eight with a delivery performance of 95%. A project stakeholder asks the project manager about the status of a specific deliverable not visible in the status report. What should the project manager do?
A project manager is leading a complex project. The team is being challenged with frequent, incremental, and uncontrolled changes to the project. What should the project manager do?
During daily team coordination meetings, team members constantly ask which tasks they should focus on first. How should the project manager ensure the team is fully productive?
A project to develop an enterprise resource planning (ERP) system for a university is ongoing. The system should improve business processes through digitalization and elimination of human errors, and also provide end users with simplified and easily accessible services. What should the project manager do to ensure achievement of the intended business value?
An experienced project manager has recently joined a troubled project. The project is impacted by multiple delays caused by a vendor’s late delivery of new servers. Due to budget restrictions, the project manager cannot switch vendors, and the project must be completed within a maximum of 90 days as agreed. What should the project manager do?
A project manager is hired to work on a very large, complex project that requires the team to complete a significant number of specialized tasks. What strategy should the project manager incorporate to help organize, assign, and monitor these tasks?
During project implementation, a critical performance issue is identified by team members.
What should the project manager do?
A project is almost complete when a key stakeholder raises a concern because the functionality of their preferred requirement was not showcased in the prototype. The prototype has already been approved and developers have started work on the final application. What should the project manager do next?
A project manager is leading a hybrid project. A project team member has not been delivering on time; as a result, the project is about to be delayed.
What should the project manager do?
A project manager is working on a large event and developing budgets for sign-off. The stakeholders and project sponsor are all working remotely using various tools to ensure that all documentation is tracked and handled discretely and appropriately. The primary stakeholder has missed several deadlines for the milestone sign-offs, resulting in the project manager being forced to find alternative suppliers for items, now at higher costs. When questioned regarding the delays, the stakeholder says the notifications hadn’t appeared in their email inbox. How should the project manager proceed?
It is taking several additional iterations for a project team to complete planned backlog items. The project manager notices that some features are not meeting the iteration-level definition and must be placed back into the backlog. What should the project manager do?
A project manager faces a major conflict within their project team that should be resolved as soon as possible. Which form of communication should the project manager use to deal with the conflict?
A project manager presents the project schedule to the customer, including the detailed phases for the whole project. The customer complains that the project timeline is longer than expected and does not want to wait until the end to see results. What should the project manager do first?
A project manager is working on an agile project. The organization does not have experience with agile delivery. During business case development, the new product owner asks when project deliverables are considered complete. How should the project manager respond?
Shipping problems are impacting the supply chain worldwide, and the project ' s primary vendor has indicated potential delays in supplying certain equipment that will be ordered later in the project. What should the project manager do with this information?
A new project manager has been hired at a company that has suffered many project failures. The project manager has been tasked with delivering a software product for the company’s biggest customer. The customer has not been able to articulate how a major piece of functionality should work. The project manager wants to deliver value immediately.
How should the project manager approach the software development life cycle with this customer?
A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.
What should the project manager do next?
A project manager is leading a team delivering new software to a finance team. The new software will streamline the finance team’s monthly closing activities and reporting. What should the project manager use to promote knowledge transfer for the new solution?
During a status meeting, a project manager reported that a project is on track. However, the project sponsor thinks the project is behind schedule because a few tasks have already passed their planned finish dates but are still in progress. How should the project manager revise the report and demonstrate the project is on schedule?
A project team member has lost enthusiasm and is experiencing low morale for a
project they were once excited about. What should the project manager do?
At the end of a project, one of the suppliers is facing financial difficulties and is
pushing the project manager to obtain financial, legal, and administrative approval in order to
communicate formal project closure and ensure the transfer of liability. What should the
project manager do next?
A hybrid project is experiencing several issues with both the agile delivery of the
product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable
What should the project manager do to resolve this?
A project manager has experience working with a specific provider that has been
requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?
The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two things should the project manager do? (Choose two)
During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?
In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan
What should the project manager do?
A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.
What should the project manager do to avoid these challenges?
A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and. as part of the risk management, has identified new products that can support a growing customer base.
What should the project manager do next?
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification for the product.
What should the project manager do to proceed with the project management plan?
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams. As a team facilitator, what should the project manager do to avoid this?
A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company ' s CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs)
What should the project manager do to control this situation?
A project manager is working on a large project in another country and realizes that
only a few people from the project team are working on all of the releases. What should the
project manager do to prevent this in the future?
An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project
How should the agile leader ensure successful delivery?
A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
A subcontractor informs the project manager that they are unable to supply a key
component to the project. What should the project manager do?
A project manager is in the process of creating a strengths-based team and is
organizing a series of workshops to identify and document the strengths of each project team
member. During this session, there are multiple team members who are not actively
participating. These meetings are becoming futile due to a lack of participation.
What should the project manager do?
A retail company identifies that it is losing sales because customers are not promptly
informed about promotions and sales points. The company needs to react quickly. A project charter is created along with requests to develop a mobile application for the customer. The marketing department has a long list of features to add to the application, but there are no specifications.
Considering the objective to deploy customer value, which project life cycle approach should be chosen?

A new project manager is managing a hybrid project. The project manager wants to be
a servant leader to support the team by removing impediments but is not receiving feedback
from the team about the issues and risks they are facing.
What should the project manager do?
Due to a recent company merger, a project manager from company B has been
assigned to a team that is comprised of team members from company A. At the start of the
project, conflicts arise due to a lack of clarity on processes and the project manager ' s
relationship with company B.
What should the project manager do to resolve this conflict?
A hybrid project manager has taken over a large-scale software development project m a highly regulated environment. During a handover session the outgoing project manager explains that they devised their own status reports which is different from the project management office ' s (PMO ' s) status report style. The project stakeholders are extremely particular about the information they receive in updates and do not believe the PMO ' s status reports have sufficient enough information
How should the new project manager proceed*?
A project manager is leading a project that is in the execution phase. During a team
meeting, the project manager realizes that there are two team members who lack the
technical skills required for some of the upcoming tasks.
What should the servant leader project manager do next?
A project manager resigned from a recently approved project. A new project manager has been assigned to the project and needs to determine the delegated authority. What should the new project manager do next?
A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?
A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?
A project manager has been assigned to a project that is in progress. The project
manager is looking for information regarding why the project is being completed.
What should the project manager do first?
While working on a poorly defined internal project, a project manager receives
multiple change requests from senior management. What should the project manager do first?
A project manager submits a version of the software that the project team created. During the review meeting, a team member informs the project manager of a recent regulation that requires a dual verification process in the software. However, the product sponsor strongly insists there should be no updates to the software.
What should the project manager do?
A project manager finds out that the required project status reports have not been
filled out by most team members. These status reports are urgently needed to compile a
comprehensive status report for the project sponsor.
What should the project manager do to address this situation?
A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.
What should the project manager do?
A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype
What should the project manager do to accelerate this solution?
A customer interacts directly with a Scrum team and continually requests changes in
priorities. This causes confusion among the team members and they complain to the project
manager.
What should the project manager do?
An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work
What should the project manager do?
During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
A business improvement opportunity to reduce energy usage has been identified.
The project manager has assembled a team that includes site engineers to deliver this project.
However, due to production imperatives, the site engineers may not be fully focused on the
project.
How should the project manager manage the team?
A project manager working on a large-scale network implementation is frustrated
with the hardware supplier. Their deliveries have been consistently late and frequently do not have vital components. The project manager ' s company has decided to cancel the contract and move to a new supplier, but the only other option is an overseas company.
What should the project manager do first to proceed with this change?
An organization ' s management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team ' s progress will be hindered by their lack of knowledge.
Which two project events will assist the project manager to ascertain if this is the case? (Choose two)
A government agency is developing a new connectivity policy. The assigned project
manager is a famous economist with international recognition. The team is eager to work with
the project manager, but feels intimidated. The project manager realizes that a junior
economist, whose tasks are behind schedule, is especially intimidated by the situation.
What should the project manager do first?
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project ' s schedule and budget. What should the project manager do next?
A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities
What should the team do differently during planning for the next iteration " ?
A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.
Which distribution list should the project manager use when sending out invitations?
A company has transitioned and is now delivering projects using a hybrid approach instead of a predictive approach. The distributed project team ' s knowledge of agile is varied. The project manager feels the new methodology will impact the timely delivery of the project.
What should the project manager do?
A project requires testing of the final product to be done at another department ' s
testing facility, which is known for having low availability. This situation could potentially
impact the project schedule.
What should the project manager do next?
A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.
What should the project manager do to ensure effective communication throughout the project?
As a project is reaching completion, the project sponsor tells the project manager to
immediately close the project and to move on to another project. Which critical task should the
project manager complete before closing the project?
A key project stakeholder does not attend any of the project meetings and is
providing false information that the project team is not delivering on time. What should the
project manager do to address this situation?
A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team ' s integration leads is a subject matter expert (SME) m this integration area. The other team ' s integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other
What should the project manager do first to resolve this situation?
A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.
What should the project manager do to address this concern?
During a meeting with a customer, it was determined that participants of the meeting
had different draft versions of an important design document. What should the project
manager do first to ensure that this does not happen again?
The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?
During the early phases of a project, mitigation actions were not executed in a
timely manner; therefore, the project schedule was impacted. Several project stakeholders are
now frustrated with the delays.
What should the project manager have done to manage the issue?
A project manager is working on a highly complex project. During the execution of
the project, the local government changed certain environmental regulations, which could
potentially delay the project.
What immediate action should the project manager take?
A complex, high-value agile project includes sprint demonstrations with the customer
every four weeks. Executive management is concerned about the project ' s progress and
wants more frequent updates on the project status.
What should the project manager do?
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule
What should the project manager do?
A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project ' s cost and schedule.
What should the project manager do first?
An equipment vendor will implement a new production line for a client company. The year-long project will include 2- to 4-month long iterations; however, the client ' s project manager has no agile experience.
How should the project manager ensure that the client is effectively represented in the daily meetings?
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concem9
A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90°.© of the market The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90% coverage
What should the project manager do?
A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder ' s presence has had a negative impact on the team ' s morale, while also impacting productivity
How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?
A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.
What should the project manager do?
The main project stakeholder was fired and replaced by another stakeholder. The
new stakeholder reviewed the project scope and requested numerous changes, arguing that
the stakeholder ' s team is unhappy with the results to date.
What should the project manager do?
A new project manager has been assigned to an environmental project. After
reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.
Why is this situation problematic?
A project manager is working on a project with multiple workstreams. One of the
workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen
again?
A project stakeholder has expressed concern that the established success criteria for
the project are not being met. What should the project manager do next?
One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.
What should the project manager do next?
A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person
What should the project manager do first?
A project team that is very experienced in enterprise resource planning (ERP)
systems implementation is currently planning the delivery of a new ERP project. There is a
requirement to reuse the client ' s security subsystem developed by a third party. The client
states that integration with the security subsystem must be done by the client ' s team. The
project manager does not want to have such an external dependency.
What should the project manager do first?
A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities
What should the project manager do next?
Eight people have been working on a project for an extended period of time. The
scope has changed significantly and the product owner has been replaced multiple times. The
team members are feeling disassociated from the project.
What should the project manager do to ensure team alignment with the goals?
A project has been running successfully for 2 months. At a regular project meeting,
the team raises several potential obstacles to future progress. The obstacles include vendor
delivery performance, technical performance of a subsystem, and conflict with another division of the organization.
What should the project manager do next?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A project team has been together for a long time and has been led by three different
project managers. Lately, the performance of one of the team members has been declining
and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and
sustained?
A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the
customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during
project execution?
In a software project using an agile approach, there have recently been work
overruns. After assessing the situation, the project manager concluded that the overruns are
occurring because of insufficiently refined product backlog items.
What should the project manager do to correct this issue?
A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team
What should the project manager do first to solve the situation?
The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.
What should the project leader do to solve this situation?
During the sprint planning of a project, the team members have a disagreement
about the comparative size of the backlog items and if they would fit into the next sprint.
Considering a hybrid approach, what should the project manager do?
The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action
What two actions should the project manager take ' ? (Choose two)
At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining What will help the project manager understand why this has occurred?
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?
In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch
What should the project manager do to realize benefits?
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late. Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck

Two weeks after the approval of the project management plan for a global project, the project manager noticed that it was approved based on a different level of understanding by international stakeholders and is not what the project manager presented for approval What should the project manager have done to prevent this from happening?
A project manager meets with external stakeholders to explain the objectives and outline expectations for a new project. A key stakeholder appears to support the project, with the condition that other unrelated projects will receive financial support Due to cultural sensitivities the project manager is reluctant to be direct with the key stakeholder on this matter The project cannot proceed without the support of this stakeholder.
What should the project manager do?
A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?
The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.
What does that project manager need to do to make the team work in a collaborative way?
A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished
How should the project manager approach this situation?
A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals
What two options will help the team initially address this obstacle? (Choose two)
A high-performing team member’s performance has been consistently increasing over the past year, leaving other peers behind The project manager has been reluctant to publicly recognize the team member’s contributions for fear of discouraging others The project manager is also concerned that the team member may leave if not rewarded for the contributions made.
What should the project manager do?
The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?
A large project is affecting the neighborhood in which it is located The neighbors are not satisfied with the project and their resistance to the project may affect the project deadline
What two actions should the project manager take ' ? (Choose two)
During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting The ongoing conflict is preventing tasks and deliverables from being completed The project manager contemplates changing their leadership style
What should the project manager do?
The team has reported the following impediments at the daily standup meeting Drag each impediment on the left to the action that the project manager needs to take on the right

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project ' s success?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager ' s actions on the right

A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?
Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement
What should the project manager do next?
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project ' s lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
During a documentation audit of an international company it was identified that the last version of the project schedule was from one month ago even though the project manager knew it was recently updated How should the project manager have handled documentation for the project?
Drag the organizational characteristics on the left to the correct scenario on the right

A key stakeholder for a construction project has been spending a lot of time at the site and interrupting the team ' s efforts What should the project manager do in this situation?
As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change
What should the project manager do?
The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?
A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
What should the project manager do?
A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.
What should the project manager do?
During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays On which area should the project manager focus?
A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager’s project
Which two actions can the project manager take to bring the team back on track? (Choose two)
A new regulation has been approved that will impact the deliverables in the fourth phase of the project The delivery is following an iterative approach and is currently completing the second phase.
What should the project manager do next?
After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
A large multi-year project requires highly skilled staff for successful deployment The management team and the project sponsor have analyzed the resource requirements and agreed to have permanent staff hired for the project to avoid potential budget overrun However there is a risk of staff turnover during the course of the project, which may have an impact on the delivery
Which two actions should the project manager take to mitigate this risk? (Choose two)
A company is working on a project and is using a hybrid approach to streamline a customer service process. At the end of the second iteration, a business analyst joins the team to learn about the financial and scheduling aspects of project management.
What should the project manager do to support the business analyst?
A project manager is tracking a project, but a key stakeholder will not accept the project ' s key performance indicator (KPI) results Which tool or technique should the project manager use?
A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog
What should the project manager do?
One team member is not as active as the rest of the team during a brainstorming session The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired The team member appreciates the project manager ' s concern The project manager then decides to change the time and room for the meeting to ensure everyone can participate
What interpersonal skill did the project manager use?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?
A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch
On what should the project manager focus?
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year
Which project approach suits the scenario?
A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
What should the project manager do first?
A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint
What should the project manager have done to avoid this situation?
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework
What should the project manager do in this situation?
A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component
What should the project manager have done to prevent this delay from happening?
An agile team is geographically separated across multiple continents, and the project manager of identifying the tools to manage the communication among the virtual teams Drag the appropriate tool on the left to each project task on the right

A client is structured as a matrix organization for an agile project The project manager is working on-site with key stakeholders from different parts of the organization
How should the project manager handle the different stakeholders?
A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.
What action should the project manager take to motivate the project team ' s performance?
A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change
What should the scrum master do?
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations
What should the project manager do?
During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?
A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities
How should the stakeholder be engaged in the project?
A team has different ideas on how to address a feature of a product under construction and; although the sprint began two days ago, they have still not reached a consensus. What should the project manager do?
During an ongoing project a key resource asks the project manager about the project purpose and if it is aligned with the organization ' s strategy What should the project manager share with the key resource?
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client ' s needs.
What should the project manager do?
Drag the to the correct scenario on the right

A company ' s project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team ' s performance?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
The following table shows the business value created and the development effort required to implement various features in a product

Which feature should the team prioritize first? Enter the feature name in the box below

The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .

What should be the priority order in the product backlog?
A product company is transforming the way it develops and releases products in the market Executives believe that this is a high-risk initiative, and this initiative must be successful
What should the project manager do in this scenario?
The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project
What should the project manager do to reduce negative impacts to the project?
A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter
What should the project manager do?
A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?
During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team
How should the project manager handle this situation?
The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.
What does the project manager need to do first?
How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?
An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?
An agile project is running activities to define the minimum viable product (MVP) During the session, the project manager identifies some mandatory regulations but there is no consensus to include these regulations in the MVP because it may extend the duration of the project
What should the project manager do?
A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project
What should the project manager have the project team update to ensure proper communications to stakeholders?
In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0.75 and the cost performance index (CPI) is 1 25 The project manager must provide the first project status review soon and wants to emphasize that the project is under control
How should the project manager report the project status to key stakeholders?
The product owner decides to launch a product after a couple of releases knowing that the minimum viable product (MVP) lacks some features One of the key stakeholders the marketing vice president is not happy with the results and questioned the release decision.
What should the project manager do?
A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
For the purposes of quality assurance a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available
Why is an attendance list important?
From previous lessons learned working with a client, a project manager notes that the client ' s turn-around times on documents sent for approval were very slow and well outside of the agreed timelines At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A project manager has been assigned to handle a company’s newest product. The product is in the conceptual stages and no one is sure about the success or marketability of the product. Management wants to deliver the product in 3 months.
What should the project manager do next?
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.
What should project manager to do next to minimize the impact on the project?
A company ' s CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,
What should the project manager do first?
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A project manager received the project charter for a new product. The project is expected to have two main deliveries: the hardware part that has detailed specifications already defined, including a sample machine, and the user interface software that has only a basic specification and a
requirement for a user experience design approach.
Which project management approach should the project manager use?
Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager ' s first step in addressing the problem?
A project manager for a digital transformation project has already received the business needs for the project. When gathering requirements, the project manager discovers that not all of the requirements can be delivered with the available resources, but that some of the requirements will be
enough to add business value.
With the project on a fixed budget, what should the project manager do next?
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer ' s contribution and thinks that the developer deserves a reward.
What should the project manager do?
we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.
What should the project manager do?
During a kick-off meeting at the start of project execution, the vendor presents a
migration plan to client stakeholders. The director of the business unit that owns the solution being migrated demands the ability to make the final go/no-go decision about whether the systems go live.
What should the project manager do?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?
A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member ' s lack of experience does not negatively impact the project?
A project manager is working on a project that will transform the organization ' s operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?
A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?
A self-organizing team brings an internal problem to the project manager. What should the project manager do as a servant leader?
During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.
How should the project manager address the situation?
A project manager is managing a hybrid project that is using a contractor for a few key deliverables. The contractor has been hired to perform an important delivery, but has not yet confirmed that they can meet the required schedule.
What should the project manager do?
A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project
What should the project manager do?
A project manager has been assigned to a project where collaboration with the business is a critical key factor. The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved
How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.

A solution designer in an agile team often passes the design information to team members without any documentation, This has resulted in misunderstandings within the team.
What should the agile leader do?
A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team ' s performance?
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix
What should the project manager do with regard to community engagement in this situation ' '
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager ' s performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.
What should the project manager do first?
A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product ' s vital information with the team and the product owner.
What does the project lead need to do to prevent a risky situation in the next iterations?
An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but
the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?
During a project to develop a new pharmaceutical product, the project manager was informed that there has been a change in government regulations regarding the materials of the project.
What should the project manager do?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
During the development of a product, multiple identified risks have now become issues, which is hindering the team ' s velocity. What should the project manager do in this situation?
A company has undertaken a large transformation project using agile practices. The project sponsor has asked the project manager to promote the new values identified in the intended transformation to the project team
What should the project manager do?
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.
What should the project manager do?
A company has transitioned and is now delivering projects using a hybrid approach
instead of a predictive approach. The distributed project team ' s knowledge of agile is varied.
The project manager feels this new methodology will impact the timely delivery of the project.
What should the project manager do?
A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs
to be delivered to the customer as a ready-to-use product .
Based on this scenario, what should the project manager focus on throughout the project life cycle?
A healthcare company requires all new employees to attend mandatory computer-based training courses, Because some of the employees work with highly sensitive patient data, the training covers various aspects of data security. In spite of this training, data breaches continue to occur in
one of the project teams.
What should the project manager do?
An agile project is in the seventh iteration with multiple changes being accommodated from the project start due such as regulatory changes technological innovations market competition and other changes What should the project manager do to manage these continuous changes coming into the project?
A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager ' s supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team
What should the project manager do?
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
A project manager is assigned to a new project. Many of the project deliverables need to be outsourced.
What should the project manager use to document the project deliverables?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
A project manager is working toward a deadline to prepare a client report. The project manager prepared a meeting agenda but not a single meeting has gone according to plan True, meetings always end in arguments and no action items come out of it. The project manager is very frustrated and seeks help from the project sponsor
What should the project manager have created to prevent this situation1?
A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
A large and complex program in an agile environment has experienced an increase in
escalations from the client side. The rates and responsibilities are unclear, and the client does not have any direction regarding the escalation process.
What should be done to resolve this issue?
A project learn member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager ' s priority in this situation?
An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager ' s management approach?
A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market
How should the project manager address this issue?
Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.
What should the project manager do to engage the stakeholders?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis? (Choose two)
An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

A new project manager is assigned to a project that will deliver a new and optimized credit system. The project manager is allowed to use a hybrid approach which is new to the organization to manage the project and new tools
In order to deliver the project successfully, what should the project manager focus on as part of the plan?
During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred
What should the project manager do to address this issue?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?
A project manager needs the team to define the steps and identify the risks of migrating data to a new system.
What type of leadership should the project manager use to accomplish this?
A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?
Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government ' s cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?
A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team
members and stakeholders who have contradictory opinions.
What should the project manager do?
A major national company known for quality products has just selected a small subcontracting firm to assist with a project. The project manager from the subcontracting firm is meeting with the project team to ensure that the project is delivered according to the customer ' s standards
in order to ensure this, what should the project manager define and document?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
A team is having a hard time completing work due to unclear requirements. They have not been able to complete an iteration successfully in several months.
In order to help the team, what should the project leader do?
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?
One phase of a project took much longer than initially anticipated The key stakeholders expressed their concern regarding a potential project delay. What should the project manager do?
A bank has decided to initiate a project to transition from serving small businesses and entrepreneurs to mid- and large-scale businesses The country ' s economy is struggling, and some stakeholders cannot agree on this transformation need
What should the project manager do ' ?
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit
Which two rules are appropriate tor the project manager to instill in the team? (Choose two)
In an agile project, two key stakeholders disagree about a major new requirement. Recognizing that this could lead to potential issues, what should the project manager do next?
A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing
Which three corrective actions should the project manager perform? (Choose three)
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose three)
A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members
Which three actions should the project manager take? (Choose three)
Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution
document.
What should the project manager do to avoid a delay in the project?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
A project management office (PMO) has been trying to implement an adaptive approach for the project management framework. The project manager has been asked to use adaptive tools in the next project. Awareness of adaptive tools is very low in the company, and many stakeholders are concerned about moving to a hybrid approach.
What should the project manager do?
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder in order to provide necessary resources. However, the stakeholder is refusing to get involved because the stakeholder believes there is no benefit in using the project deliverable.
What should the project manager do to resolve this?
A project manager is leading a project and is asked to negotiate on behalf of their organization. The organization requires that three quotes from different suppliers be acquired prior to submitting a purchase request to the finance department.
What should the project manager do to align with this requirement?
A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes.
What should the project manager have done to avoid this issue?
During the project planning phase, the customer explained the importance of delivering the project results proposed in the scope as soon as possible.
What should the project manager do first to address this issue?
A project lead accepted an assignment for a project that is still in the feasibility study phase. There are many uncertainties about project specifications, including poor alignment among the project sponsors on the final targets of the project. Which approach should the project lead choose to deliver business value?
During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project
manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?
A team member has very strong technical skills and is interested in a leadership role. A leadership position opens up outside of the team in the organization. The project manager has observed that the team member has a major gap in communicating in a professional manner.
What should the project manager do?
The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:
• The marketing director is the key stakeholder. as the project will create a new product for the company.
• The finance director is providing funding and does not have much time to follow the tracking of the project.
• The sales representatives assigned to the team provided some negative feedback on the requirements
• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

A project manager is leading the development of a mobile banking application using a hybrid approach. The team has been holding daily standup meetings each workday
morning. Due to an unexpected issue, 50% of the team has to work from home. The bank ' s management directed the team not to have in-person daily standups. Various team members are complaining about this, stating that there is a lack of information sharing among the team
What should the project manager do?
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed
for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?
A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project ' s ongoing changes.
What should the project manager do?
A key project stakeholder has started to escalate all issues and main requirements to the project sponsor. The project manager is concemed about the team not receiving direct communications from this stakeholder.
Which two actions should the project manager take to improve the relationship with the stakeholder? (Choose two)
During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much
experience in development.
What should the project manager do?
A defect is identified during user acceptance testing that could significantly impact the system ' s performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
An innovation project with a budget of over US$30 million is expected to have a large impact on the technology industry. The business area is concerned if the project will meet stakeholder expectations and raised this concern with the project manager.
What should the project manager do to manage business concerns and expectations before starting the project?
While managing a project using a hybrid approach, the project manager realizes that there is a high level of rework due to quality issues. Because
of that, each feature is taking longer than initially estimated.
What should the project manager do to address the issue?
A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project
manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two)
A project manager ' s new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the
project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager ' s background includes a couple of years’
experience as an agile practitioner working as a scrum master.
What should the project manager do at the start of the project?
A construction project for a nuclear power plant will reduce the region ' s energy dependence on external electricity supplies. The project manager has received support for
the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan?
A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?
During a project ' s stakeholder identification stage, team members are struggling to identify the level of influence for two stakeholders. One is considered important, while the second is not quite as important as the first one. For this project, stakeholder engagement is a critical activity.
What should the project manager do?
A project manager is reviewing the team ' s Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.
Will the project manager meet this objective?
A project manager is facilitating meetings with a diverse team, considering that the team members come from different cultures and have different backgrounds. What should the project manager do to facilitate effective communication?
While sizing a user story in planning poker, one team member believes the user story should be 8 points. Another believes the story should be 2 points.
What should the scrum master do?
A company is building a minimum viable product (MVP). How should the project manager help to ensure the company builds a high-quality product?
A project team member contacts the project manager to say they are not familiar with the regulations to complete some activities. What should the project manager do?
A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.
What should the project manager do?
A project manager is facilitating an iteration retrospective. The iteration did not go well and the committed functionality was not delivered to users. The project involves a vendor team for the build and an internal quality assurance (QA) team. In the past, there were tensions between the vendor and the internal team.
What should the project manager do?
A project team has not been meeting its deliverables because they are not receiving adequate resources to do their job. What should the project manager do for the team to meet the upcoming deliverables?
A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?
To ensure effective team communication and processes, a standard set of software including video conferencing is defined for a virtual scrum team. Several team members are reporting problems with their access and cannot adhere to team processes.
How should these issues be resolved?
A product owner is continuously adding requirements to a project that will significantly impact project delivery. How should the project manager address this?
A project team is struggling to meet the project deadline due to a recurring conflict between two team members. What should the project manager do?
Construction work is preventing the project team members from entering the building where their offices are located.
What should the project manager do next?
A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor ' s feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.
How should the project manager mitigate this situation?
The project stakeholders represent diverse organizational functions and have differing opinions about project goals. The project has been approved, but change requests could result if the stakeholders do not align on the functionality needed and the minimum viable product (MVP).
What should the project manager do?
A key stakeholder of a project wants to include additional work before completion.
What should the project manager do?
A project is approaching the closing phase. While preparing for the final steps, the quality system is updated in accordance with new international quality standards, resulting in new deliverable/approval procedures.
Which action should the project manager take?
A software development project is about to start. The product owner and project manager cannot agree on which programming language to use from the available two. The company lacks experienced developers in the product owner ' s preferred language; however, they are very skilled in the other language.
What should the project manager do?
During a contract renewal meeting, an organization ' s commercial team and the customer are disagreeing and negotiations are failing. What should the project manager do to reach an agreement that will satisfy all parties?
After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?
A virtual project team has members located on four continents. The project director is concerned about the declining motivational levels of team members and feelings of noninclusion by other team members. The project director has tasked the project manager with finding a solution.
What should the project manager do?
A project is in the execution phase and there are disagreements between two key stakeholders about the project ' s scope. One stakeholder is adamant about expanding the scope and the other stakeholder is content with the current arrangement.
What should the project manager do?
Presented with flowcharts of the organization ' s operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.
What should the project manager do?
A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.
How should the project manager improve the team ' s understanding?
A project manager is in the process of authoring the communications management plan for a new project. One of the project ' s stakeholders has a habit of posting work updates on social media, which may include confidential project status updates.
What should the project manager do?
During planning, a virtual project team agreed to the project reporting structure and established a meeting cadence that fits multiple time zones. One month into execution, the project manager notices that certain members are disengaged during project meetings.
What should the project manager do to resolve this issue?
A project manager is approached by two new product owners who were instructed by their managers to join a new agile team. Both product owners were told they could start working with the new agile team immediately.
What should the project manager do to advise both product owners?
A project is on schedule. However, during a site visit, a project manager notices that the contractor ' s productivity is low.
What should the project manager do?
A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?
A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.
What should the project manager do?
Due to their different ideas regarding the execution of a project, a conflict has occurred between two stakeholders.
What should the project manager do to resolve the conflict?
A project is starting with a team that is located all over the world. None of the team members have worked together before. The project goal is ambitious with an aggressive timeline.
What should the project manager do?
A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.
What should the project manager do to address this risk?
A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.
What should the project lead do?
During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.
What should the project manager ask the team to do next?
Generative artificial intelligence (AI) now helps produce documents on most projects across an organization and is yielding great benefits. Despite this change, a project manager notices that very few members of their current team know the AI tools available within the company. Consequently, they do not know how to use them effectively.
What should the project manager do?
A project is using a Scrum team from a new vendor to deliver a component. Engaging a new vendor was identified as a delivery risk that, if eventuated, must be escalated to the board. The project manager and product owner work well with the Scrum team, but the vendor misses the first release by a couple of weeks.
What should the project manager do?
An organization has successfully delivered many projects using only predictive approaches. The organization has now decided to add some agile development processes into their standard deployment framework.
What should the project manager take into account first when building the schedule for this new project?
A team member increased the estimated completion time for their activities on the critical path. This action, however, has caused friction among the team members. The project manager reviewed the key performance indicators (KPIs) that show the issue.
What should the project manager do first?
A project team is working on a critical release and the customer wants this feature to be made available as early as possible. The business owner suggests an enhancement during the product demo.
How should the project manager address this request?
A project team member who was a top performer in the planning phase of a project was easily irritated during the fifth sprint of the software development phase. The team member ' s attitude and behavior made the other team members feel uncomfortable.
What should the project manager do?
A project manager ' s team has been working very hard to meet a critical deadline. Some project team members are experiencing burnout due to the high workload.
What should the project manager do first to manage the team ' s workload effectively?
The sponsor calls the project manager and questions why the stakeholders have not received updates for over 1 month. The project recently implemented a project management information system (PMIS) that provides real-time access to various project status measurements and information. The project manager is certain that all stakeholders have the opportunity and permissions for status updates.
How should the project manager proceed?
The team ' s velocity is inconsistent, leading the product owner to believe the team is creating too many points in their user stories.
What should the scrum master do first?
The project manager is planning a project with several legal aspects for the city ' s municipality. The project is expected to take a year and will require a lot of paperwork since it involves multiple stakeholders, including the city ' s court.
What three actions should the project manager do? (Choose 3)
During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?
A new employee has joined the management team and wants to get a quick overview of all the agile team ' s projects. What should the agile team lead recommend to the employee as a first step to gain this understanding?
The scope of a construction project that is being planned by a multinational company requires that services are procured via contract from an external provider. When considering communication channels, what should the project manager do to help maximize delivery success with this provider?
A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?
A project manager has identified the key stakeholders for the project. The project manager wants to use their expertise to help the stakeholders understand and support the project objectives and benefits.
What should the project manager do?
A project manager is leading a project that is kicking off next month. The project manager realizes that there are many stakeholders that need updates on different aspects of the project at different frequencies.
What should the project manager do first to ensure each stakeholder has the information they need?
In the execution phase of a project, the development team is informed by the IT security department that one of the external platforms that the team is using will be uninstalled for the whole organization.
What should the project manager do first?
A department lead requested additional items be included in the project during the execution phase. Their acceptance is mandatory before the project can be closed.
A project manager is new to an organization that typically follows a hybrid approach but is shifting to incorporate more agile. A dedicated project team has been provisionally assigned. The new project manager needs to review the internal environment in order to build a high-performing team.
To build a high-performing team, which three factors should the project manager evaluate? (Choose 3)
A project manager was appointed to lead an already approved project. While reviewing the benefits management plan, the project manager finds out that the information about the forecasted value of the project may not be accurate.
What should the project manager do?
Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?
A project manager is leading a diverse global team. The team members disagree about the requirements for a recently approved change request. The conflict among the team members has resulted in low morale and decreased performance.
What should the project manager do?
During a meeting with the customer, it was observed that the features delivered during the last few iterations were not meeting the planned expectations.
What should the project manager do?
A project manager is developing the project schedule with the project team. The team members estimate that an optimistic duration is 5 days, the pessimistic duration is 20 days, and the most likely duration is 11 days.
What duration should the project manager use?
A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.
What type of contract and project approach should the project manager consider?
A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidated damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.
What should the project manager of the contracting company do?
A project manager notices that a team member is upset during a team meeting. The project manager assesses the situation and determines that the team member does not collaborate with some of the other team members.
What should the project manager do?
A government approved the construction of a river dam to enable year-round farming in a community. At the project kickoff meeting, a key stakeholder in the community disagrees with the location of the dam.
What should the project manager do first?
A project manager has been assigned a project team with members in two different locations. The project manager noticed that the productivity of a senior team member in the other location is much lower than the local junior team members.
What should the project manager do to address the issue?
A project manager is leading a diverse project team that includes new and experienced team members. A conflict has occurred between two team members. One team member prefers using digital tools for project communication. The other team member prefers in-person meetings and phone calls for communication.
What should the project manager do to manage this conflict?
A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
Which first two actions should the project manager perform? (Choose 2)
A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.
What is the first step the project manager should take?
At the first retrospective meeting, a developer in a newly formed team points out that frequent delays in documenting the requirement solution are impacting the workflow. The developer wants to know why the analyst is not doing their job on time. Confronting the analyst causes a conflict that quickly escalates. The analyst is certain that the documentation process is not solely their function.
What should the project manager do to resolve the conflict and prevent future conflicts as the team matures?
During a planning session, the development team and the product owner are arguing about the effort needed to deliver a specific feature in a software development project. The product owner says that the feature can be developed in one week, whereas the team estimates that it will take at least two weeks. After several hours of discussion, they have not reached an agreement.
What should the project lead do?
An experienced project manager is in a meeting with project key stakeholders when they are informed that a senior manager with extensive experience on similar projects will join the project steering committee. The project kick-off meeting is scheduled for the following week.
What should the project manager do next?
A project manager is leading a project with a team that is comprised of both experienced and inexperienced team members. What should the project manager do to ensure an effective project team?
Project stakeholders have provided a team with requirements that will take at least one year to complete. The project sponsor advised that they need to see some return on investment (ROI) soon.
What should the project manager do?
A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.
Which tool should the project manager use for this purpose?
A project manager is leading the construction of a branch office building for a national bank. The project manager is informed that the regulatory authority has closed the bank.
In closing this project midway, which activities should the project manager execute first?
A project manager leads an agile development project. During the sprint planning meeting, the development team expresses concerns that the proposed scope of the next sprint is much larger than expected given the current resource allocation. The project manager believes the scope is essential to meet the project milestones.
How should the project manager approach negotiating an agreement with the team to ensure the project remains on track?
A project manager leads a regulatory initiative with tight, non-negotiable timelines. During a status meeting, a key stakeholder asks if a critical milestone associated with the reporting functionality can be moved up by 4 weeks.
What should the project manager do first?
A project manager is assigned to a research project. The project team has been selected and has worked together on other projects. Based on the project documentation, team members seem to be working at their own pace and have had little interaction with the project manager.
What should the project manager do to have a high-performing team?
A team member has escalated an issue to the project manager, stating that they have done their part of the job. Their concern is that there is still no response from the other party in the service level agreement (SLA). The team member is eager to find a resolution for the reported issue.
What should the project manager advise the team member to do to ensure that the project escalation mechanism is effective?
During a sprint planning, the development lead highlights the importance of working on technical debt tasks that are critical for the product performance. However, the tasks will consume most of the team ' s capacity and they will not be able to work on product feature development.
What should the project manager do?
A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.
What should the project manager do?
A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager ' s organization, the client organization, and the local community.
What should the project manager do after identifying the stakeholders?
An agile team member discovers an impediment that is preventing them from doing their work efficiently. At which of the meetings should they bring up this impediment for resolution?
A large, multinational organization is reevaluating its policy on project management approaches. Team members are complaining about having different processes for each project they are on. Currently, predictive, agile, and hybrid methodologies are being used. A project manager is now part of a team working on standard criteria for approach selection for new projects.
What should the project manager recommend?
A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project ' s value and caused a delay in the approval.
What should the project manager have done to avoid this setback?
A project manager is appointed to a project that has just been approved. The project manager has extensive experience in hybrid projects, and the project team has performed many projects within a predictive framework. However, the project sponsor believes that the project needs to be executed using agile approaches.
What should the project manager do to select the most effective project framework?
A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.
However, that tool is not available in one team member ' s country.
How should the project manager deal with this situation?
The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.
What should the project manager do?
A state-of-the-art product was delivered at the end of a project life cycle. However, the customer claims the product was not designed to specifications.
What should the project manager have done to avoid this issue?
A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.
What should the project lead do?
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
Update the issue log and refer to the resource management plan to address the situation.
Ask the team for extra work to fulfill the project commitment.
Reduce the scope of the project and inform stakeholders.
A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.
What should the project manager do first?
A multinational company is rolling out a new software platform within its subsidiaries. However, the distributed project team struggles to meet regularly. As a result, the project milestones are not being achieved.
What should the project manager do first?
A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.
This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of
their time to projects regardless of their complexity.
What should the project manager do as a servant leader to help achieve this transformation?
A project team ' s performance is being impacted by impeding internal procedures that are affecting the progress of activities and team autonomy. What should the project
manager do first to address this situation?
A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager
do to get this information?
During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?
Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?
A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.
What should the project manager do?
A project manager leads a project that implements a new process throughout the organization. The rollout is done in stages and the project manager planned a demonstration for the pilot business units. A manager from a business unit that is scheduled for a later date asks to be invited to the sprint review.
What should the project manager do?
A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact
project implementation.
What should the project manager do next?
A project manager is working with the same project team as in the last two construction projects. The project manager managed this team on a micro level for the last two
projects. However, now the project manager would like to use a different leadership style to allow the team to make their own decisions.
What kind of leadership style should the project manager utilize for the current project?
An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?
An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager
advises the product owner that some of the functional requirements are not aligned with the chief information technology officer ' s (CTO) strategy.
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers ' group was not consulted, and they use the site for a monthly market.
What should the project manager do to move forward with the project?
In a global project, the main definitions were developed in country A, and the delivery of the project will be completed in phases in countries B, C, and D. Country B discovers that one of the legal requirements was not addressed.
What should the project manager have done to avoid this situation?
The change control board (CCB) has approved a change request to add a new component within a product. The operations manager discovers the change after its approval and complains that the implementation of the change will cause significant disruption to the production line.
What should the project manager do first?
A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.
What should the project manager do?
During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.
What should the project manager do next?
During the execution of a project, a key stakeholder complains to the project manager about recent communications.
The key stakeholder explains that the relevant information from the project team was incomplete and late. As a result, the key stakeholder is beginning to disengage from the project.
What should the project manager do?
A project manager had to schedule additional planning sessions to add requirements from an international stakeholder. The stakeholder expressed concern about the product not meeting the client ' s needs.
Which factor should the project manager have considered when developing the product?
Key decision makers are meeting to define the objectives of a new database migration project. There are many disagreements about scope and time lines among the leaders of various company departments.
How should the project manager impartially prioritize the requirements to be integrated?
A member of a testing team in an agile project works well with the project team. However, in the previous two iterations, this team member ' s performance was poor, and the team had difficulty meeting the iteration goals.
How should the project manager handle this situation?
A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?
A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.
How should the project manager communicate with the local community?
A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.
What should the project manager do?
Drag the communication event on the left to the main subject discussed during the event on the right.

A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team ' s effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.
How should the project manager handle the situation?
A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business. What should the project
manager do to ensure business value is delivered early?
A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile.
What should the project manager recommend?
A team member has experienced personal conflicts on past projects, making them nervous about working on the current project. The project
manager knows this team member could add value to the project.
What should the project manager do to get the most value from this team member?
During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal
impact on project resources. However, the client has only been focused on the next milestone.
How should the project manager approach this situation?
The project manager of a globally dispersed team evaluates the organization ' s current virtual engagement tools and strategies. A couple of the remote team members are not participating effectively in virtual meetings.
Which action should the project manager take to improve remote engagement?
A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with
another team to ensure the continuity of deliverables.
What should the project manager do?
A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.
What should the project manager do to ensure the project scope is completely defined?
A company is starting a critical project with a strict deadline. During the first planning meeting, the team realizes that the list of requirements has
too many items to allow on-time delivery.
What should the project manager do first?
A team decides to adopt an agile approach for their new project. During a sprint, the project manager realizes that there is a need to show progress and optimize the collaboration among teams.
Which tool should the project manager use?
In a daily standup meeting, a project manager notices that a team member ' s reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.
What should the project manager do?
A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?
A project is about to start with a global project team. Travel is not a viable option for project team members, so most will participate virtually.
What should the project manager do to engage the team?
An agile team is required to address a technical, complex requirement that has no visual deliverable to show the customer. What guidance should the product manager provide to improve the requirement development?
A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change
in project scope.
How should the project manager respond to this requirement?
A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.
What should the project manager do?
A project has recently completed its production go-live, meeting the project ' s completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.
How should the project manager address the customer ' s requests?
An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).
What should the project lead do?
A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of
the team members were stressed due to over commitments.
What should the project manager do?
A project manager works with a multifunctional team. During a review meeting, two team members disagree on the development approach.
What should the project manager do?
A project manager is managing a project with team members who are working all over the globe. The project manager notices that each team
member ' s deliverables do not meet the requirements.
What should the project manager do first?
A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource ' s departure?
A global program is being kicked off, and various distributed teams are involved in delivering the initiative. Besides planning and executing the scope for the initiative, team
interactions must be considered.
How should the project teams interact in their meetings?
A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?
An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project
execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.
What should the project manager have done to prevent this from happening?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
During a monthly review meeting, a high-performing team member raised a concern about the quality feedback mechanism. The team member expressed that they are not able to deliver high-quality output.
What should the project manager do first?
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and followup calls with key stakeholders. The team seems to be disengaged.
How should the project manager approach this situation?
A project manager schedules virtual daily standup meetings for a project, but half of the team members regularly join late or miss the meeting all together. What should the project manager do?
A project team Is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.
What should the project manager do?
A company is working on a project to develop an integration of their existing systems. There are known issues in production.
What should the project manager do?
A team has individual daily start times for each team member. Sometimes the overlap between team member working hours is short. During those
times, the interactions and work as a team are reduced and ineffective.
What should the project manager do?
A project manager is in the process of closing out a project and has been asked by the project management office (PMO) to confirm that the transfer of knowledge to the operations team for support operations has been successfully completed. Which technique should the project manager apply to verify the knowledge transfer?
A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.
In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?
An organization is transitioning to agile delivery, and a new team has been assembled. A project is not going well because the variation of the team velocity is very high and every sprint delivers less than committed. A new project lead with a strong technical background has been assigned to the project.
What should the project lead do?
A project manager has completed an assessment of the project team ' s performance. Some team members have performed poorly on their assigned tasks.
What should the project manager do?
An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?
An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.
What should the team lead do next?
A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws.
What should the project manager have done to prevent this?
A large multi-national company works on a project in an emerging-economy country. All business matters are conducted in local currency. During the course of the project,
the budget becomes the primary concern due to currency instability in the country.
What should the project manager do next?
A project manager notices that a new junior team member ' s suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed.
What should the project manager do next?
3 Months Free Update
3 Months Free Update
3 Months Free Update