Pre-Winter Special - 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: c4sdisc65

Prince2-Foundation PDF

$38.5

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

Prince2-Foundation PDF + Testing Engine

$61.6

$175.99

3 Months Free Update

  • Exam Name: PRINCE2 7 Foundation written Exam
  • Last Update: Oct 8, 2024
  • Questions and Answers: 461
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

Prince2-Foundation Engine

$46.2

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

Prince2-Foundation Practice Exam Questions with Answers PRINCE2 7 Foundation written Exam Certification

Question # 6

Which term is defined as the means by which an organization transitions from its current state to the target state?

A.

Change management

B.

change control

C.

Progress management

D.

Risk management

Full Access
Question # 7

Which is an assumption about the PRINCE2 customer/supplier environment?

A.

The supplier will pay for the project

B.

The customer will provide the resources to deliver the products

C.

The customer will specify the desired result

D.

The supplier will tailor the project's application of PRINCE2

Full Access
Question # 8

According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?

A.

One

B.

Two

C.

Three

D.

Six

Full Access
Question # 9

Which describes a risk effect?

A.

The uncertainty expressed as a negative or favourable occurrence

B.

The issue which is affecting the project and has resulted in a risk

C.

The impact(s) on the project objectives should the threat or opportunity occur

D.

The change in the status of a risk in response to actions taken to control it

Full Access
Question # 10

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

A.

Appointing the project board and producing the project brief

B.

Planning the initiation stage and appointing the project manager

C.

Producing the additional role descriptions and validating the project product description

D.

Verifying the project approach and capturing previous lessons

Full Access
Question # 11

Which statement describes the 'Implement' step within the recommended risk management procedure?

A.

Take planned action to respond to a risk

B.

Implement the responsibilities for risks defined in the Risk Management Strategy

C.

Assess the proximity of a risk

D.

Identify the level of risks that can be tolerated by the project

Full Access
Question # 12

Which should be provided by a project mandate?

A.

Terms of reference

B.

Detailed Business Case

C.

Stage tolerances

D.

Initiation Stage Plan

Full Access
Question # 13

Which is an objective of the 'initiating a project' process?

A.

To ensure that baselines are established and controlled

B.

To ensure that the business case is kept under review

C.

To ensure that the planned products are delivered within tolerances

D.

To ensure that user acceptance of the products is confirmed

Full Access
Question # 14

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?

A.

To identify responses to risks documented in the business case

B.

To identify information about the project environment and objectives

C.

To identify the roles to be involved in risk management activities

D.

To identify uncertainties that may impact on the delivery of the project objectives

Full Access
Question # 15

Which are benefits of using PRINCE2?

1. It removes the need for activity-based planning

2. It promotes learning and continuous improvement

3. It can be applied to any type of project

4. It defines specific leadership and other interpersonal skills required

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 16

Which is a purpose of the change theme?

A.

To prevent change to baselined products

B.

To identify, assess and control any potential and approved changes to baselined products

C.

To establish mechanisms to monitor and compare actual achievements against those planned

D.

To assess and control uncertainty

Full Access
Question # 17

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

A.

End Stage Report

B.

Team Plan

C.

Work Package

D.

Project Plan

Full Access
Question # 18

Which is a minimum requirement for applying the quality theme?

A.

To define the project’s approach to quality assurance

B.

To appoint external reviewers for quality reviews

C.

To define quality criteria in product descriptions

D.

To provide administrative support for quality controls

Full Access
Question # 19

Which is an objective of the 'directing a project' process?

A.

To create the plan to deliver the project product

B.

To select and appoint the project manager

C.

To design the project management team roles

D.

To give authority to deliver the project product

Full Access
Question # 20

What should the benefits management approach define?

A.

What actions will be taken to ensure the project's outcomes are achieved

B.

What will be used to record the effectiveness of the project's approaches

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Full Access
Question # 21

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Full Access
Question # 22

Which is a purpose of a quality register?

A.

To record cross-references to issues relating to the quality of the products

B.

To record the date a completed work package was received

C.

To provide the status of quality activities carried out for completed products

D.

To capture quality concerns about completed products

Full Access
Question # 23

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Full Access
Question # 24

Which principle helps to ensure that all changes to the outputs are agreed?

A.

Defined roles and responsibilities

B.

Focus on products

C.

Learn from experience

D.

Manage by exception

Full Access
Question # 25

What is a goal of the 'implement' step within the recommended risk management procedure?

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Full Access
Question # 26

What is established during the 'initiating a project' process?

A.

The agreed protect acceptance criteria

B.

The need for a configuration library

C.

A plan for the work or project initiation

D.

An understanding of the project's funding

Full Access
Question # 27

Which are reasons for a benefits management approach?

1. To state how improvements will be measured

2. To confirm that the benefits are realized

3. To estimate the costs of improvement

4. To define the reason for delivering the improvement

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 28

Which TWO are objectives of the ‘controlling a stage process?

1. To focus attention on achieving Work Within) the agree tolerances

2. To create follow on action recommendations for all open issues and risks

3. To understand how the quality required will be achieved

4. To ensure that the stage’s products meet-agreed quality expectations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 29

Whose approval is needed to replace a Stage Plan with an Exception Plan?

A.

Corporate or programme management

B.

Project Board

C.

Project Manager

D.

Team Manager

Full Access
Question # 30

Which is a purpose of the Directing a Project process?

A.

Provide the information required to confirm if it is worthwhile to initiate a project

B.

Enable overall control of a project to be exercised by the Project Board

C.

Establish the level of control required by the Project Board after initiation.

D.

Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved

Full Access
Question # 31

Which is an objective of the Closing a Project process?

A.

Prepare the plan for the next stage

B.

Assess any benefits that have already been realized

C.

Produce a Benefits Review Plan to identify what benefits are expected

D.

Check that all benefits are realized before closing a project

Full Access
Question # 32

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

A.

Configuration Item Record

B.

Quality Register

C.

Highlight Report

D.

Checkpoint Report

Full Access
Question # 33

Which role is responsible for creating Checkpoint Reports?

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support

Full Access
Question # 34

Which is NOT included in the PRINCE2 definition of a project?

A.

A project is a temporary organization

B.

A project's purpose is to deliver one or more business products

C.

A project is part of 'business as usual'

D.

A project is based on an agreed Business Case

Full Access
Question # 35

Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 36

Which should be funded by a change budget?

A.

Increase in agreed scope

B.

Initiation stage

C.

Change Authority

D.

Handover activities

Full Access
Question # 37

Which is a recommended quality review team role?

A.

Project Manager

B.

Assurance

C.

Project Support

D.

Administrator

Full Access
Question # 38

Which product identifies how often stakeholders require information?

A.

Communication management approach

B.

Quality management approach

C.

Change control approach

D.

Risk management approach

Full Access
Question # 39

Within which integrated element does PRINCE2 set minimum requirements?

A.

Themes

B.

Processes

C.

Principles

D.

Project environment

Full Access
Question # 40

Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?

A.

Creating a product flow diagram

B.

Writing the product description

C.

Writing a project product description

D.

Documenting the plan

Full Access
Question # 41

Which is a purpose of the business case theme?

A.

To identify which role is responsible for producing the business case

B.

To identify the project's outputs

C.

To establish the controls to manage changes that may impact the project benefits

D.

To establish a viable investment proposition

Full Access
Question # 42

According to the 'continued business justification' principle, what must project benefits be aligned to?

A.

Regular deliveries throughout the project

B.

The business objectives

C.

The direction of the project board

D.

The technology available

Full Access
Question # 43

How is the tailoring approach defined for a project?

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

Full Access
Question # 44

Which are characteristics of stakeholders?

1. They are often affected by the project

2. They agree with every project objective

3. They are only/always external to the corporate organization

4. They typically interact with the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 45

Which risk response is applied on a pain/gain basis?

A.

Share

B.

Accept

C.

Exploit

D.

Enhance

Full Access
Question # 46

Why is the 'initiating a project' process used?

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required work packages

D.

To enable corporate or programme management to give authorization to deliver a project

Full Access
Question # 47

Which is a minimum requirement for applying the risk theme?

A.

Threats must be assessed for their impact on the viability of the project

B.

A single role that is responsible for all risks must be defined

C.

The PRINCE2 risk management procedure must be followed

D.

Team managers must maintain their own risk registers

Full Access
Question # 48

How does the project board use the 'manage by stages' principle to control the project?

A.

By approving the project management team

B.

By reviewing project viability at defined intervals

C.

By ensuring that the benefits are managed and controlled

D.

By reviewing previous project closure documentation

Full Access
Question # 49

Which describes a project benefit?

A.

A specialist product of the project

B.

The result of a change derived from using the project's products

C.

An uncertain result caused by project actions

D.

A measurable improvement resulting from an outcome

Full Access
Question # 50

What is described as an organization's unique attitude towards risk taking

A.

Risk appetite

B.

Risk management

C.

Risk evaluation

D.

Risk tolerance

Full Access
Question # 51

Which process provides information for the project board to review a completed stage and confirm continued business justification?

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Full Access
Question # 52

Which is a purpose of the 'managing a stage boundary' process?

A.

To enable the project board to approve the continuation of the project

B.

To exercise overall control over the project while delegating day-to-day management

C.

To assign work to be controlled by the team manager

D.

To define the work that needs to be done to deliver the project product

Full Access
Question # 53

Where should decisions regarding the tailoring of the project be recorded?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Stage plan

Full Access
Question # 54

Which is a minimum requirement for applying the quality theme?

A.

To use lessons to inform quality planning

B.

To use the prescribed approach to quality management

C.

To use external quality standards for quality control

D.

To use user stories to inform the project product description

Full Access
Question # 55

Which is a purpose of a Project Brief?

A.

Enable the assembly of the project mandate

B.

Describe the reporting requirements of the various layers of management involved with the project

C.

Describe how changes to products will be controlled

D.

Provide a solid basis for the initiation of the project

Full Access
Question # 56

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

A.

Team Plan

B.

Stage Plan

C.

Benefits Review Plan

D.

Project Plan

Full Access
Question # 57

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Full Access
Question # 58

Which process monitors work that has been assigned to a team manager?

A.

Controlling a stage

B.

Directing a project

C.

Managing a stage boundary

D.

Managing product delivery

Full Access
Question # 59

Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

A.

Continued business justification

B.

Defined roles and responsibilities

C.

Manage by exception

D.

Manage by stages

Full Access
Question # 60

According to the 'tailor to suit the project' principle, what is the basis for effective project management?

A.

That the appropriate number and type of meetings are held

B.

That the project is divided into an appropriate number of stages

C.

That the appropriate information is provided to make decisions

D.

That the project method relates to the project’s environment

Full Access
Question # 61

Identify the missing words in the following sentence.

The 'managing a stage boundary' process should be executed [ ? ] a management stage.

A.

when a stage plan has been prepared for

B.

at the beginning of

C.

when all the delivery steps have been completed within

D.

at, or close to the end of,

Full Access
Question # 62

The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.

Which principle is the project board applying?

A.

Manage by exception

B.

Manage by stages

C.

Ensure continued business Justification

D.

Focus on products

Full Access
Question # 63

How does product-based planning help to determine the project approach?

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Full Access
Question # 64

Which role is responsible for focusing on the safety and well-being of the project team?

A.

Project executive

B.

Project board

C.

Project manager

D.

Team manager

Full Access
Question # 65

The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.

In which step of the ‘issue management technique should the change authority request this information?

A.

Deciding on changes

B.

Implementing changes

C.

Assessing issues

D.

Capturing issues

Full Access
Question # 66

According to the guidance for effective quality management, when should the requirements for a product be captured?

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Full Access
Question # 67

When does the ‘directing a project’ process start?

A.

When the project manager submits the project brief for approval

B.

When the request to authorize a project is received

C.

After the project has been authorized by the business layer

D.

After the project mandate has been received

Full Access
Question # 68

The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?

A.

The business objectives

B.

The business’ existing governance practices

C.

The project's delivery method

D.

The ways of working used on previous projects

Full Access
Question # 69

What does qualitative analysis of a risk assess, as a minimum?

A.

How soon each risk might occur

B.

The fallback plan for each risk

C.

The likelihood and the effect of each risk on objectives

D.

The speed with which the effect of each risk will be felt

Full Access
Question # 70

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 71

Which is an internal factor to consider when tailoring PRINCE??

A.

The safety legislation

B.

The environmental standards

C.

The industry's regulations

D.

The organization's procedures

Full Access
Question # 72

How should effective issue management be applied When changing management products?

A.

By changing the issue management approach at the end of each stage to reflect lessons

B.

By creating new versions of a management product when a change is approved

C.

By Implementing a change budget to fund changes to the project product

D.

By recording the required change to a management product as an off-specification

Full Access
Question # 73

According to the ‘exception management technique, which roles are MOST LIKELY to identity issues that exceed stage tolerances?

A.

Project executive AND senior user

B.

Senior supplier AND team manager

C.

Project executive AND project manager

D.

Project manager AND team manager

Full Access
Question # 74

The senior user needs to understand how user assurance will support the senior user on the project.

Which management product should the senior user review?

A.

Project plan

B.

Project management team structure

C.

Role descriptions

D.

Project log

Full Access
Question # 75

Which term is defined as a product that will not meet is quality specifications?

A.

Off-specification

B.

Request for change

C.

Concern

D.

Problem

Full Access
Question # 76

Which term is defined as being achieved as a result of the activities undertaken to facilitate the change?

A.

Outcome

B.

Benefit

C.

output

D.

Request for change

Full Access
Question # 77

Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

A.

Initiating a project

B.

Starting up a project

C.

Controlling a stage

D.

Managing product delivery

Full Access
Question # 78

In which step of the Issue management’ technique should Superseded versions be archives?

A.

Implementing changes

B.

Assessing issues

C.

capturing issues

D.

Deciding on changes

Full Access
Question # 79

Which management product Soul guide the Project management team on how to manage multiple aspects of the project?

A.

Project initiation documentation

B.

Project plan

C.

Business case

D.

Exception plan

Full Access
Question # 80

Which member of the project management team should secure funding for the project before the project stars?

A.

Project executive

B.

Project manager

C.

Senior user

D.

senior supplier

Full Access
Question # 81

What is a description of a leadership activity within a project?

A.

Understanding and working with different departments outside of the project team

B.

Agreeing a work package with a tear manager to deliver products using specific tools

C.

Ensuring that a co-located project team uses the agreed communication methods

D.

Creating a stage plan and product descriptions for the products to be created in the next stage

Full Access
Question # 82

Which is a description of a purpose of the communication management approach?

A.

To document for stakeholders the future business required to meet project objectives

B.

To document how the project team should control its interactions with stakeholders

C.

To document how to use financial incentives to motivate project team members

D.

To document the responsibilities of project team members for testing whether products are acceptable to users

Full Access
Question # 83

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Full Access
Question # 84

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?

A.

In stage of team plans to allow mare accurate scheduling

B.

As quality tolerances in product descriptions

C.

As acceptance criteria in the project product description

D.

In the quality management approach to plan the testing

Full Access
Question # 85

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Full Access
Question # 86

Which team is defined as motivating people to achieve a project’s objectives?

A.

Leadership

B.

Management

C.

Quality assurance

D.

Co-creation

Full Access
Question # 87

Which action contributes to achieving the ‘ensure continued business justification’ principle?

A.

Producing separate business cases for each customer and supplier involved in the project

B.

Defining the products that the project must produce in order to control change effectively

C.

Establishing limits of authority on the project based on defined tolerances

D.

Adapting PRINCEZ to the scale of investment and the delivery approach

Full Access
Question # 88

The project manager needs to confirm that operational teams are responsible for the running of the outputs.

During which step of the ‘organizational design and development’ technique should the project manager ensure this?

A.

Manage the ongoing changes to the project ecosystem

B.

Transition the project into the organizational ecosystem

C.

Understand the organizational ecosystem

D.

Develop the project ecosystem

Full Access
Question # 89

Thea project manager needs to report to the project board on the status of the project's issues.

Which management product should the project manager review?

A.

Project log

B.

Project brief

C.

Checkpoint report

D.

Highlight report

Full Access
Question # 90

Which TWO are objectives of the ‘starting up a project’ process?

1. To provide an interface between the corporate layer and the project

2. To provide the required authority to initiate the project

3. To plan the work required for project initiation

4. To provide business justification for initiating the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 91

Which statement describes a purpose of the 'starting up a project’ process?

A.

To appoint people ta the major rales in the project management team

B.

Ta agree how a team manager will report progress

C.

To provide Information so that the business can understand the cost of delivering the project

D.

To provide management control Listen the project manager and the team managers

Full Access
Question # 92

What is a description of a purpose of the ‘quality’ practice?

A.

To enable the project products to meet the documented expectations of the user

B.

To document fundamental information to make rational sneer (Wert commissioning the project

C.

To establish the basis for the project, to enable the work to deliver the project product to be understood

D.

To monitor the allocated work, deal with issues, and allocate additional work if required

Full Access
Question # 93

The project manager reviews the project product description to identify the detailed requirement for each product.

In which step of the quality management technique should the project manager do this review?

A.

Gathering user inputs

B.

Accepting products ay

C.

Describing the quality management approach

D.

Controlling quality

Full Access
Question # 94

The project manager needs to record the impact assessment for a specific business opportunity.

In which management product should the project manager record this?

A.

Issue report

B.

Issue register

C.

Risk register

D.

Quality register

Full Access
Question # 95

Which describes a management activity within a project?

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Full Access
Question # 96

Which should define how tools will be used to support the information needs of the project team?

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Full Access
Question # 97

Why does the project board review the PID during an end stage assessment?

A.

To confirm that project controls are adequate for the remainder of the project

B.

To notify the commissioning organization that the project has been authorized

C.

To review summarized progress to date and decide what to do next with the project

D.

To ensure that post-project reviews of operational performance are planned

Full Access
Question # 98

Which is a benefit of using PRINCE2?

A.

It promotes consistency of project work and the ability to reuse project assets.

B.

It includes techniques for critical path analysis and earned value analysis

C.

It enables a project manager to be accountable for the success of a project

D.

It prevents any changes once the scope of a project has been agreed

Full Access
Question # 99

How are team managers involved in tailoring PRINCE2 suit the project?

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Full Access
Question # 100

Which statement is CORRECT about the customer and suppliers of a project in a commercial environment?

A.

Each party may have their own business case for undertaking the project

B.

Both parties must apply the same external governance to the project

C.

The risk appetite should be collaboratively set before the project starts

D.

Management systems need to be unified for successful project delivery

Full Access
Question # 101

Which is a minimum requirement for applying the 'change' theme?

A.

Specify in the change control approach the means by which project products will be protected

B.

Document the format and contents of the issue register

C.

Produce issue reports to document the impact assessment for requests for change

D.

Delegate the change authority to the senior supplier(s) for supplier off-specifications

Full Access
Question # 102

What is documented in the project plan to support the 'manage by exception' principle?

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Full Access
Question # 103

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Full Access
Question # 104

Which is an objective of the 'controlling a stage' process?

A.

To review the business justification for the project

B.

To replan the current stage when directed

C.

To develop products to defined quality criteria

D.

To produce a learn plan for the work package

Full Access
Question # 105

Identify the missing words in the following sentence.

The six aspects of project performance to be managed are [ ? ] costs, timescales and scope.

A.

benefits, change, risk,

B.

benefits, quality, risk,

C.

change, quality, risk,

D.

benefits, change, quality,

Full Access
Question # 106

The project board Wants to consider whether td continue to operate in the same way, of Whether to change operations by means. of a project.

In which step of ‘business case management technique should this be considered?

A.

Develop

B.

Check

C.

Maintain

D.

Confirm

Full Access
Question # 107

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Full Access
Question # 108

Which management product is used to record relationships between specialist products?

A.

Change control approach

B.

Configuration item record

C.

Issue register

D.

Product status account

Full Access
Question # 109

What does the communication management approach define?

1. How versions of products will be described on information sent to interested parties

2. How information should be sent to interested parties

3. How often information should be sent to interested parties

4. How the PRINCE2 roles will be combined during the project

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Full Access
Question # 110

What is an advantage of applying the 'learn from experience' principle?

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project

Full Access
Question # 111

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

A.

are able to overturn the decisions of

B.

must be accountable to

C.

should support

D.

report to the project board and

Full Access
Question # 112

Which statement about applying the 'tailor to suit the project' principle is CORRECT?

A.

PRINCE2 can be tailored to be used with any type of project

B.

A technically complex project should NOT tailor PRINCE2

C.

The tailoring of PRINCE2 is MOST appropriate for agile projects

D.

A project which is part of a programme should NOT tailor PRINCE2

Full Access
Question # 113

Which product identifies the management stages and timescales of a project?

A.

Project Brief

B.

Project Product Description

C.

Project Plan

D.

Initiation Stage Plan

Full Access
Question # 114

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

A.

Those with a financial interest in the project

B.

Those who will manage the project on a day-to-day basis

C.

Those who will specify the desired outputs of the project

D.

Those who will create the project's outputs

Full Access
Question # 115

What product is used to maintain a record of those who have an interest in the project and their information requirements?

A.

Project Plan

B.

Communication Management Strategy

C.

Project Brief

D.

Project Product Description

Full Access
Question # 116

Which is a purpose of the Initiating a Project process?

A.

Decide if it is worthwhile to initiate a project

B.

Decide on the project approach

C.

Establish solid foundations for a project

D.

Identify the number of Work Packages required

Full Access
Question # 117

Which is NOT a purpose of the Organization theme?

A.

Define a project management team structure

B.

Define the level of tolerance for each level of the project management team

C.

Define the Project Board's responsibility for directing the project

D.

Define which role is accountable for the project's success

Full Access
Question # 118

Which is NOT a purpose of a Benefits Review Plan?

A.

Define the period over which the cost-benefit analysis will be based

B.

Describe how to measure the performance of the project's products in operational use

C.

Define the scope, timing and ownership of the benefit reviews required

D.

Describe how to measure and confirm any benefits that are to be realised after the project is closed

Full Access
Question # 119

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Full Access
Question # 120

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

A.

controls

B.

products

C.

project management team

D.

stages

Full Access
Question # 121

Why is the Initiating a Project process used?

A.

To decide which project approach is suitable for the project

B.

To fully understand how the project objectives will be achieved before committing significant resources

C.

To produce the required Work Packages

D.

To enable corporate or programme management to give authorization to deliver a project

Full Access
Question # 122

Which product records any project outcomes perceived as negative by stakeholders?

A.

Business Case

B.

Project Plan

C.

Communication Management Strategy

D.

Project Product Description

Full Access
Question # 123

Which is NOT a purpose of the Initiating a Project process?

A.

Enable a Project Board decision about the commitment of resources to a project

B.

Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

C.

Establish solid foundations for a project

D.

Enable the Project Board to decide whether it is worthwhile to initiate a project

Full Access
Question # 124

What is the collective name for individuals or groups who may be affected by a project?

A.

Customers

B.

Project Support

C.

Stakeholders

D.

Team members

Full Access
Question # 125

Which is an objective of the Initiating a Project process?

A.

Develop the corporate quality management system as part of the Project Initiation Documentation

B.

Prepare the plans for the subsequent stages

C.

Summarize how the organization's project management method will be tailored for the project

D.

Request authority from corporate management to deliver the project

Full Access
Question # 126

Which is NOT one of the PRINCE2 integrated elements?

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Full Access
Question # 127

What is the first task of product-based planning?

A.

Produce the Initiation Stage Plan

B.

Write the Project Product Description

C.

Identify dependencies

D.

Create the product breakdown structure

Full Access
Question # 128

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Full Access
Question # 129

Which statement about the Directing a Project process is true?

A.

Provides a mechanism for the Project Board to assure that there is continued business justification

B.

Covers the day-to-day activities of the Project Manager

C.

Ensures there are regular progress meetings

D.

Begins on completion of the Initiating a Project process

Full Access
Question # 130

What product defines the reporting requirements between the Project Manager and Team Manager?

A.

Project Brief

B.

Product Description

C.

Team Plan

D.

Work Package

Full Access
Question # 131

Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.

A.

a solution should be designed for

B.

an issue should be created for

C.

the agreed actions should be recorded for

D.

the chair will approve the solution to

Full Access
Question # 132

What process aims to ensure accurate progress information is provided to the Project Manager?

A.

Starting up a Project

B.

Managing a Stage Boundary

C.

Managing Product Delivery

D.

Directing a Project

Full Access
Question # 133

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Full Access
Question # 134

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

A.

Raise a request for change

B.

Raise an off-specification

C.

Write an Exception Report

D.

Amend the Work Package

Full Access
Question # 135

What is the definition of a project outcome?

A.

A measurable improvement that is perceived as an advantage by one or more stakeholders

B.

The reason for the project

C.

The result of the change derived from using the project's outputs

D.

The project's specialist products.

Full Access
Question # 136

Why is it crucial that the Project Product Description clearly defines acceptance methods?

A.

Enables Project Assurance to authorize quality activities

B.

Defines how all project products will be reviewed and approved

C.

Defines how it will be proven that the completed project product meets the customer's expectations

D.

Provides confirmation that all project products have met their quality criteria

Full Access
Question # 137

Which is a task of product-based planning?

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Full Access
Question # 138

Which product documents the information needed to demonstrate continued business justification?

A.

Business Case

B.

Communication Management Strategy

C.

Project Product Description

D.

Quality Management Strategy