3 Months Free Update
3 Months Free Update
3 Months Free Update
where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.
What are some benefits of planning with planned independent requirements? Note: There are 2 correct answers to this question.
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?
Under what circumstances can you change the material type for a material if stocks, reservations, or purchasing documents exist? Note: There are 2 correct answers to this question.
How can you limit the validity of a bill of material (BOM)? Note: There are 2 correct answers to this question,
Which of the following processes lead to an entry in the MRP planning file?
Note: There are 3 correct answers to this question.
What data can you maintain in the subitems of a bill of material (BOM)?
Note: There are 2 correct answers to this question.
What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.
Where do you maintain data to determine the duration of an operation for production? Note: There are 2 correct answers to this question.
How can you characterize dependent requirements in material requirements planning?
Note: There are 2 correct answers to this question.
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?
Your project team decided to use a make-to-order planning strategy material in discrete manufacturing.
what is the impact of this decision?
Note: there are 2 correct answers to this question
What could be the reason for different combinations of components in a multiple bill of
material (BOM)?
Note: There are 2 correct answers to this question.
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.
You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?
Which time elements can be reduced by a reduction strategy?
Note: There are 3 correct answers to this question.
You Have a scheduling agreement with a vendor, you want classic MRP to automatically create
schedule lines in case of material shortage, what must you do?
Note: there are 2 correct answers to this question.