Pre-Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free PSM-I Professional Scrum Master I Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the Scrum PSM-I Exam the most current and reliable questions . To help people study, we've made some of our Professional Scrum Master I exam materials available for free to everyone. You can take the Free PSM-I Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

Who creates a Product Backlog Item’s estimate?

A.

The Development Team after clarifying requirements with the Product Owner.

B.

The Product Owner with input from the Development Team.

C.

The most senior people in the organization, including architects and subject matter experts.

D.

The Scrum Master.

E.

The Development Team, alone.

Question # 7

In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.

Which of the following two actions should the Scrum Master support? (Choose two.)

A.

Cancel the Sprint. Send the entire team to an advanced Scrum training and then start a new Sprint.

B.

Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan. Once the time-box for the Sprint Planning meeting is over, start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

C.

Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast. Then start the Sprint.

D.

Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

E.

Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting.

Question # 8

(Why do the Developers need a Sprint Goal?

Choose the best answer.)

A.

A Sprint Goal only gives purpose to Sprint 0.

B.

Sprint Goals are not valuable. Everything is known from the Product Backlog.

C.

A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.

D.

The Developers are more focused with a common yet specific goal.

Question # 9

Every Scrum team must have a Product Owner and Scrum Master.

A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a business analyst in the Development Team.

C.

False. A Scrum Master is only required when asked for by the Development Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Question # 10

The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.

A.

True

B.

False

Question # 11

What is the function or purpose of management in Scrum?

(choose the best answer)

A.

To identify and remove people that are not working hard enough.

B.

To present the Scrum Teams with insights and resources that help them improve.

C.

To monitor the productivity of the Developers.

D.

To continually monitor staffing levels of the Scrum Team.

Question # 12

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the people doing the work.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

Question # 13

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started

using the product. The stakeholder is unhappy with the quality of the product. What are two good options for the

Scrum Master? (Choose the best two answers.)

A.

Wait to bring this up until the Sprint Retrospective.

B.

Encourage the Product Owner to put quality specifications on the Product Backlog and express the

stakeholder’s concern to the Developers.

C.

Bring the concern to the testers to improve how the Product is verified.

D.

Explain to the Product Owner that it is up to the Developers to decide on acceptable quality standards.

E.

Coach the Product Owner on how to talk with the Developers about this concern.

Question # 14

When does a Developer become accountable for an item in the sprint Backlog?

(choose the best answer)

A.

During the Daily Scrum

B.

Never am Developers on the Scrum Team share accountability tor items in the

C.

As soon as a Developer on the Scrum Team can accommodate more work

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers

Question # 15

When do Development Team members take ownership of a Sprint Backlog item?

A.

At the Sprint planning meeting.

B.

During the Daily Scrum.

C.

Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each one may be done by an individual Development Team member.

D.

Whenever a team member can accommodate more work.

Question # 16

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

A.

The Scrum Masters from each Scrum Team define a common Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

D.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

Question # 17

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

A.

Its productivity is likely to decrease.

B.

Its productivity is likely to stay the same.

C.

Its productivity is likely to increase.

Question # 18

(Who must attend the Daily Scrum?

Choose the best answer.)

A.

The Scrum Master and Product Owner.

B.

The Developers and Scrum Master.

C.

The Developers.

D.

The Developers and Product Owner.

E.

The Scrum Team.

Question # 19

How do you know that a Scrum Team is cross-functional? (Choose the best answer.)

A.

Scrum Team has all the skills to create an increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Scrum Team.

D.

Every member of the Scrum Team is able to perform every task.

Question # 20

When is it most appropriate for a Scrum Team to change the definition of “Done”?

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

Question # 21

Which best describes the Product Backlog?

A.

It is allowed to grow and change as more is learned about the product and its customers.

B.

It provides just enough information to enable a Scrum team to start the design phase of a product.

C.

It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.

D.

It is baselined to follow change management processes.

Question # 22

Which three of the following are feedback loops in Scrum? (Choose three.)

A.

Sprint Review.

B.

Release Planning.

C.

Sprint Retrospective.

D.

Refinement Meeting.

E.

Daily Scrum.

Question # 23

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.

A.

True

B.

False

Question # 24

Who is responsible for clearly expressing Product Backlog items?

A.

The Scrum Master, or the Scrum Master may have the Development Team do it.

B.

The Scrum Master.

C.

The Product Owner.

D.

The business analyst who represents the Product Owner in the Development Team.

Question # 25

How often should Scrum Team membership change?

A.

As needed, while taking into account a short term reduction in productivity.

B.

Never, because it reduces productivity.

C.

As needed, with no special allowance for changes in productivity.

D.

Every Sprint to promote shared learning.

Question # 26

In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams?

A.

Understanding the product, the product vision and the rules of the Scrum framework, the group divides itself into teams.

B.

It doesn’t really matter because you can rotate the teams every Sprint to spread knowledge.

C.

Check with the allocation department to see who has worked together before and make these the first teams.

D.

Create a matrix of skills, seniority, and level of experience to assign people to teams.

Question # 27

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

A.

There should be six Product Owners, one tor each Scrum Team.

B.

There should be six Product Owners, reporting to a Chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Question # 28

What it the main reason for the Scrum Master to be at the Daily Scrum?

A.

To gather status and progress information to report to management.

B.

To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.

C.

He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.

D.

To make sure every team member answers the three questions.

Question # 29

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update management on what is being worked on.

D.

Answer QUESTION NO:s from the Development Team about items in the current Sprint.

Question # 30

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Development Team’s ability to deliver.

D.

Its Definition of “Done”.

E.

All of the above.

Question # 31

Which of the following are true about the length of the Sprint? (Choose two.)

A.

The length of the Sprint should be proportional to the work that is done in between Sprints.

B.

It is best to have Sprints of consistent length throughout a development effort.

C.

Sprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing.

D.

Sprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint.

E.

All Sprints must be 1 month or less.

Question # 32

What does it mean to say that an event has a time-box?

A.

The event must happen at a set time.

B.

The event must happen by a given time.

C.

The event must take at least a minimum amount of time.

D.

The event can take no more than a maximum amount of time.

Question # 33

The time-box for a Daily Scrum?

A.

Two minutes per person.

B.

15 minutes.

C.

15 minutes for a 4 week sprint. For shorter Sprints it is usually shorter.

D.

4 hours.

E.

The same time of day every day.

Question # 34

Who creates the Definition of Done?

(choose the best answer)

A.

The Scrum Master

B.

The Product Owner

C.

The scrum Team

D.

The Developers

Question # 35

What two factors are best considered when establishing the Sprint length? (Choose two.)

A.

The organization has mandated similar length sprints.

B.

The level of uncertainty over the technology to be used.

C.

The frequency at which team formation can be changed.

D.

The risk of being disconnected from the stakeholders.

Question # 36

Scrum has a role called “Project Manager”.

A.

True

B.

False

Question # 37

A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

A.

Allow the Development Team to self-manage and determine for itself what to do.

B.

Set up the meeting and tell the Development Team that is how it will be done.

C.

Ask the Development Team members to alternate who is responsible for meeting setup.

D.

Inform management and ask them to solve it.

Question # 38

Which statement best describes the Sprint Review?

A.

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

B.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

C.

It is a mechanism to control the Development Team’s activities during a Sprint.

D.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

Question # 39

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

A.

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Question # 40

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Question # 41

During the Sprint Retrospective a Scrum Team has identified several high priority process improvements.

Which of the following statements is most accurate? (Choose the best answer.)

A.

The Scrum Team may add items to the Sprint Backlog for the next Sprint.

B.

The Scrum Team should choose at least one high priority process improvement to place in the Product

Backlog.

C.

The Scrum Team should decline to add a process improvement to the Sprint Backlog when things are

running smoothly.

D.

The Scrum Master selects the most important process improvement and places it in the Sprint Backlog

Question # 42

What is the time-box for the Sprint Planning meeting?

A.

4 Hours for a monthly Sprint.

B.

8 Hours for a monthly Sprint.

C.

Monthly.

D.

Whenever it is done.

Question # 43

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

A.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

B.

The Scrum Masters from each Scrum Team define a common Definition of Done.

C.

When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition Of Done.

D.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

Question # 44

A Scrum Team is a cohesive unit of professionals that consists of which of the following? (Choose all that

apply.)

A.

Users.

B.

One Scrum Master.

C.

Developers.

D.

Customers.

E.

One Product Owner.

Question # 45

A Sprint Retrospective should be held:

A.

At the end of each Sprint.

B.

At the beginning of each Sprint.

C.

Only when the Scrum Team determines it needs one.

D.

At the end of the last Sprint in a project or a release.

Question # 46

The length of a Sprint should be:

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of these answers are correct.

Question # 47

Which topics should be discussed in the Sprint Review?

A.

The Scrum process, and how it was used during the Sprint.

B.

Coding and engineering practices.

C.

Sprint results.

D.

All of the above.

Question # 48

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.

Question # 49

True or False: The Product Owner makes sure the Developers select enough from the Product

Backlog tor a Sprint to satisfy the stakeholders.

A.

True

B.

False

Question # 50

What enhances the transparency of an increment?

A.

Doing all work needed to meet the definition of “Done”

B.

Reporting Sprint progress to the stakeholders daily

C.

Keeping track of and estimating all undone work to be completed in a separate Sprint.

D.

Updating Sprint tasks properly in the electronic tracking tool.

Question # 51

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Question # 52

Which of these may a Development Team deliver at the end of a Sprint?

A.

Failing unit tests, to identify acceptance tests for the next Sprint.

B.

An increment of software with minor known bugs in it.

C.

An increment of working software that is “done”.

D.

A single document, if that is what the Scrum Master asked for.

Question # 53

(How is management that is external to the Scrum Team involved in the Daily Scrum?

Choose the best answer.)

A.

Management gives an update at the start of each Daily Scrum.

B.

Managers are not required at the Daily Scrum.

C.

The Product Owner represents their opinions.

D.

The Scrum Master speaks on their behalf.

Question # 54

What is the purpose of a Sprint Review?

A.

To take time to judge the validity of the project.

B.

To inspect the product increment with the stakeholders and collect feedback on next steps.

C.

To review the Scrum Team’s activities and processes during the Sprint.

D.

To build team sprint.

Question # 55

You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)

A.

Introduce a bonus system for the top performers in the team.

B.

Have the Scrum Team members introduce themselves to each other and give a brief background of their skills and work history.

C.

Have the development managers for each Development Team member introduce their direct reports and go over their responsibilities on the Scrum Team.

D.

Ensure the Scrum Team members have compatible personalities.

E.

Ensure the team understands they need a definition of “Done”.

F.

Ask the Product Owner to discuss the product or project, its history, goals, and context, as well as answer questions.

Question # 56

What happens if the Development Team cannot complete its work by the end of the Sprint?

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Question # 57

What is the time-box for the Sprint Review?

A.

As long as needed.

B.

2 hours for a monthly Sprint.

C.

4 hours for a monthly Sprint.

D.

4 hours and longer as needed.

E.

1 day

Question # 58

If burndown charts are used to visualize progress, what do they track?

A.

Accumulated cost.

B.

Individual worker productivity.

C.

Work remaining across time.

D.

Accumulated business value delivered to the customer.

Question # 59

Who starts the Daily Scrum?

A.

The person coming in last. This encourages people to be on time and helps to stay within the time-box.

B.

Whoever the Development Team decides should start.

C.

The person who has the token.

D.

The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

E.

The person who last broke the build.

Question # 60

Who has the final say on the order of the Product Backlog?

A.

The Development Team.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Stakeholders.

E.

The CEO.

Question # 61

What happens if the Scrum Team cannot complete its work by the end of the Sprint?

(choose the best answer)

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it does not happen again.

Question # 62

When can a Development Team cancel a Sprint?

A.

It can’t. Only Product Owners can cancel Sprints.

B.

When functional expectations are not well understood.

C.

When the Product Owner is absent too often.

D.

When the selected Product Backlog items for the Sprint become unachievable.

E.

When a technical dependency cannot be resolved.

Question # 63

As the Sprint Planning progresses, the Developers realize that the workload may be greater

than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

A.

Recruit additional Developers before the work can begim

B.

The Developers ensure that the Scrum Team is aware, start the Sprint, and

monitor progress.

C.

The Developers work overtime during this Sprint

D.

Cancel the Sprint

E.

Remove or change selected Product Backlog items.

Question # 64

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Question # 65

What is the typical size for a Scrum Team?

(choose the best answer)

A.

7 plus or minus 3.

B.

At least 7.

C.

9

D.

10 or fewer.

Question # 66

When a Development Team determines that it will not be able to finish the complete forecast, who has to be

present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)

A.

The Development Team.

B.

The Product Owner and all stakeholders.

C.

The Product Owner and the Development Team.

D.

The Scrum Master, project manager and Development Team.

Question # 67

Which three behaviors demonstrate that a team is self-organizing? (Choose three.)

A.

Stakeholders walking in at the Daily Scrum to check progress and work with the Scrum Master to optimize the functional scope for the Sprint.

B.

The Development Team members are working within the boundaries of their functional description and nicely handing off work from analyst to developer to tester to integration.

C.

The Product Owner doesn’t need to be at Sprint Retrospectives.

D.

The Development Team creating their own sprint backlog, reflecting all work that is part of the definition of “Done”.

E.

The Development Team has all the skills needed to create a releasable Increment.

F.

Development Team members collaboratively selecting their own work during the Sprint.

G.

The Development Team inviting external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.

Question # 68

Who is responsible for the Sprint Backlog?

(choose the best answer)

A.

The Scrum Team.

B.

The Scrum Master.

C.

The Developers.

D.

The Product Owner.

Question # 69

What are two responsibilities of testers in a Development Team? (Choose two.)

A.

Verifying the work of programmers.

B.

Everyone in the Development Team is responsible for quality.

C.

Tracking quality metrics.

D.

Finding bugs.

E.

Scrum has no “tester” role.

Question # 70

Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)

A.

How is the Sprint proceeding?

B.

What did I do yesterday that helped the Development Team meet the Sprint Goal?

C.

Why were you late?

D.

What will I do today to help the Development Team meet the Sprint Goal?

E.

How many hours did I spend on the project yesterday?

F.

What will I be working on tomorrow?

G.

Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?

Question # 71

Select two ways in which technical debt impacts transparency. (Choose two.)

A.

When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.

B.

It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.

C.

As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.

D.

It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.

Question # 72

During a Sprint Retrospective, for what is the Product Owner responsible?

A.

Participating as a Scrum Team member.

B.

Summarizing and reporting the discussions to the stakeholders that he/she represents in the Scrum Team.

C.

Capturing requirements for the Product Backlog.

D.

The Product Owner should not take part in Sprint Retrospectives.

Question # 73

When is it most appropriate for a Scrum Team to change the Definition of Done?

(choose the best answer)

A.

During Product Backlog refinement.

B.

During the Sprint Retrospective.

C.

During Sprint Planning.

D.

Prior to starting a new project.

Question # 74

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?

A.

There are no such activities. The next Sprint starts immediately after the current Sprint.

B.

Refine the Product Backlog.

C.

Work with the Quality Assurance departments on the Increment of the current Sprint.

D.

Update the project plan with stakeholders.

Question # 75

What is the timebox for the sprint Review? (choose the best answer)

A.

1 day

B.

4 hours for a one-month Sprint.

C.

As long as needed

D.

2 hours for a one-month Sprint.

Question # 76

The IT manager asks a Development Team for a status report describing the progress throughout the Sprint.

The Development Team asks the Scrum Master for advice. The Scrum Master should:

(Choose the best answer.)

A.

Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.

B.

Tell the Development Team to figure it out themselves.

C.

Tell the Development Team to fit the report into the Sprint Backlog.

D.

Create and deliver the report to the manager herself.

E.

Ask the Product Owner to send the manager the report.

Question # 77

Which three of the following are time-boxed events in Scrum? (Choose the best three answers.)

A.

Release Planning.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Question # 78

For which of the following is the Scrum Master responsible?

(choose the best answer)

A.

Properly adopting and using the Scrum framework.

B.

Keeping track of resource allocation.

C.

Managing the performance of the Scrum Team.

D.

The meetings and the objectives that a Scrum Team sets for itself.

Question # 79

(What is the Product Owner responsible for during the Sprint Retrospective?

Choose the best answer.)

A.

Summarizing and reporting the discussions to the stakeholders that they represent in the Scrum Team.

B.

The Product Owner should not take part in Sprint Retrospective.

C.

Participating as a Scrum Team member.

D.

Capturing requirements for the Product Backlog.

Question # 80

Which of the following are true about the Product Owner role? (Choose two.)

A.

The Product Owner is one person.

B.

The Product Owner is accountable for ordering the Product Backlog.

C.

Multiple people can share the Product Owner role on a Scrum Team.

D.

The Product Owner role can be played by a committee or a team of people.

Question # 81

Why should the Product Owner be present at the Daily Scrum?

A.

He/She doesn’t need to be there.

B.

To hear about impediments in functionality.

C.

To represent the stakeholders’ point of view.

D.

To participate as a Scrum Team member.

Question # 82

(A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?

Choose the best answer.)

A.

The Scrum Master is responsible, they remove impediments.

B.

The Product Owner is responsible, they control the return on investment (ROI).

C.

The hiring manager is responsible, they hired the Developer.

D.

The Scrum Team is responsible.

Question # 83

Which statement best describes Scrum?

A.

A defined and predictive process that confirms to the principles of Scientific Management.

B.

A complete methodology that defines how to develop software.

C.

A cookbook that defines best practices for software development.

D.

A framework within which complex products in complex environments are developed.

Question # 84

(When does a Developer become accountable for an item in the Sprint Backlog?

Choose the best answer.)

A.

During the Daily Scrum.

B.

Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.

C.

As soon as a Developer on the Scrum Team can accommodate more work.

D.

At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.

Question # 85

Who must attend the Daily Scrum?

A.

The Scrum Master and Product Owner.

B.

The Development Team.

C.

The Development Team and Product Owner.

D.

The Scrum Team.

E.

The Development Team and Scrum Master.

Question # 86

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

Question # 87

The purpose of a Sprint is to produce a done Increment of product.

A.

True

B.

False

Question # 88

A Scrum Master is introducing Scrum to a new Team. The Team has decided that a Sprint

Retrospective is unnecessary. What action should the Scrum Master take?

(choose the best answer)

A.

Comply with the decision of the self-managing team.

B.

Begin facilitating productive and useful Sprint Retrospectives.

C.

Call a meeting between the ScrumTeam and senior management

D.

Consult with the Product Owner to see how they feel about the situation.

Question # 89

How should a Scrum Team deal with non-functional requirements?

(choose the best answer)

A.

Manage them during the Integration Sprint prior to the Release Sprint.

B.

Assign them to the lead developers on the team.

C.

Ensure every Increment meets them.

D.

Make sure the release department understands these requirements, but it is not the

Scrum Team ' s responsibility.

PSM-I PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PSM-I PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Professional Scrum Master I
  • Last Update: Apr 10, 2026
  • Questions and Answers: 298
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PSM-I Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included