3 Months Free Update
3 Months Free Update
3 Months Free Update
When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint'
(choose the best answer)
If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?
What are two good ways for the Development Team to make non-functional requirements visible? (Choose two.)
A Scrum Master is essentially the same thing as a traditional PM (Project Manager).
You are the Scrum Master for four Scrum Teams working from the same Product Backlog. Several of the developers come to you complaining that work identified for the upcoming two Sprints will require full-time commitment from a technical specialist who is external to the teams. What are two key concerns for the Scrum Master to take into account in this situation? (Choose two.)
When many Scrum Teams are working on a single product, what best describes the Definition of Done?
(Choose the best answer.)
The Product Owner is not collaborating with the Development Team during the Sprint. What are two valuable actions for a Scrum Master to take? (Choose two.)
Which two things should the Scrum Team do during the first Sprint?
(choose the best two answers)
True or False: The Product Owner makes sure the Developers select enough from the Product
Backlog tor a Sprint to satisfy the stakeholders.
In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however.
Which of the following two actions should the Scrum Master support? (Choose two.)
Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
Who is responsible for the sizing of Product Backlog items?
(choose the best answer)
A Development Team asks their Product Owner to re-order the Product Backlog. The team is waiting for an external supplier to deliver a specific software component. Without that component there won’t be enough work in the next Sprint to occupy the full team. The Product Owner asks the Scrum Master for help. What would be good advice to give the Product Owner?
Who is accountable for clearly expressing Product Backlog items? (Choose the best answer.)
How should a Scrum Team deal with non-functional requirements?
(choose the best answer)
The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.
What should the Developers do?
(choose the best answer)
What factor should be considered when establishing the Sprint length?
(choose the best answer)
A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)
One of the Scrum events is the Daily Scrum. What are two intended outcomes ot the Daily
Scrum?
(choose the best two answers)
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
When must the Product Owner participate in the Dairy Scrum? (choose the best answer)
If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
What does it mean for a Scrum Team to be cross-functional?
(choose the best answer)
True or False A scrum Master fulfills the same role as a traditional Project Manager
User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What should the Scrum Team do?
(choose the best answer)
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
Which statement best describes the Sprint Backlog as the output ot the Sprint Planning?
(choose the best answer)
During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)
In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams?
True or False A high-performance scrum Team ensures that each increment is complete by running a Release Sprint.
Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose two.)
Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)
Which two ways of creating Development Teams are consistent with Scrum’s values? (Choose two.)
How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?
(choose the best answer)
You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)
The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.
Every Scrum Team must have a Product Owner and Scrum Master. (Choose the best answer.)
What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose two.)
A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team?
(choose the best answer)
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
What is the function or purpose of management in Scrum?
(choose the best answer)
Which three of the following are true about Scrum? (Choose the best three answers.)
For the purpose of transparency, when does Scrum say a new increment of working software must be available?
When multiple Scrum Teams are working on the same product, should all of their Increments be
integrated every Sprint? (choose the best answer)
Which of the following are true about the Product Owner role? (Choose two.)
As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?
Which are characteristics of the Daily Scrum?
(choose the best two answers)
To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, a Development Team to implement those ideas and a Scrum Master to help guide the process.
Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)
An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)
Developers are self-managing, which of the following do they manage? (choose the best answer)
The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.
What should the Developers do?
(choose the best answer)
Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the quality of the product, and the Product Owner agrees with the stakeholder’s assessment that the quality is low. How should the Scrum Master respond to the Product Owner?
(choose the best two answers)