Pre-Summer Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free PSPO-I Professional Scrum Product Owner (PSPO I) Exam Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the Scrum PSPO-I Exam the most current and reliable questions . To help people study, we've made some of our Professional Scrum Product Owner (PSPO I) Exam exam materials available for free to everyone. You can take the Free PSPO-I Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

What might indicate to a Product Owner that she needs to work more with the Scrum Team?

(choose the best answer)

A.

The acceptance criteria do not appear to be complete.

B.

She is not working full time with the Scrum team.

C.

People leave the Scrum Team.

D.

The Increment presented at the Sprint Review does not reflect what she thought she had asked for.

Question # 7

True or False: Dependencies could influence how the Product Owner orders Product Backlog items.

A.

True

B.

False

Question # 8

Who is accountable for tracking the remaining work toward the Sprint Goal?

(choose the best answer)

A.

The Developers.

B.

The Project Manager.

C.

The Product Owner.

D.

The Scrum Master.

Question # 9

Scrum requires that the Product Owner must use which of the following techniques?

(Choose the best answer)

A.

Feature burn-up.

B.

There is no required technique.

C.

Critical Path Analysis.

D.

Burndown chart.

Question # 10

Which statement best describes the Sprint Backlog as the output of the Sprint Planning?

(choose the best answer)

A.

It is a complete list of all work to be done in a Sprint.

B.

Every item has a designated owner.

C.

Each task is estimated in hours.

D.

It is the Developers plan for the Sprint.

E.

It is ordered by the Product Owner.

Question # 11

How much of the Sprint Backlog must be defined during the Sprint Planning event?

(choose the best answer)

A.

Just enough to understand design and architectural implications.

B.

Enough so the Developers can create their forecast of what work they can do.

C.

The entire Sprint Backlog must be identified and estimated by the end of Sprint Planning.

D.

Just enough tasks for the Scrum Master to be confident in the Developers ' understanding of the Sprint.

Question # 12

What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of

productivity?

(choose the best two answers)

A.

By keeping high value features high in the Product Backlog.

B.

By facilitating Scrum Team decisions.

C.

By ensuring the meetings start and end at the proper time.

D.

By removing impediments that hinder the Scrum Team.

Question # 13

The Scrum Team should have all the skills needed to:

(choose the best answer)

A.

Complete the project within the date and cost as calculated by the Product Owner.

B.

Do all of the development work, except for specialized testing that requires additionaltools and environments.

C.

Turn Product Backlog items into a valuable, useful Increment.

Question # 14

True or False: A Product Owner should measure product value by the increase in the team ' s velocity.

A.

True

B.

False

Question # 15

Which of the following are true about the Product Owner?

(choose the best two answers)

A.

The Product Owner is one person.

B.

The Scrum Team can have multiple Product Owners.

C.

The Product Owner can be represented by a committee or a team of people.

D.

The Product Owner is accountable for ordering the Product Backlog.

Question # 16

What is the timebox for the Sprint Review?

(choose the best answer)

A.

2 hours for a one-month Sprint.

B.

1 day.

C.

4 hours for a one-month Sprint.

D.

As long as needed.

Question # 17

A Product Owner is accountable for maximizing the value of the product that is the result of the work of the Scrum Team. Which of the following can be delegated to others, while the Product Owner remains accountable for the work?

(choose the best two answers)

A.

Attending the Sprint Retrospective.

B.

Attending the Sprint Review.

C.

Ordering Product Backlog items.

D.

Developing and communicating the Product Goal.

Question # 18

How often should Scrum Team membership change?

(choose the best answer)

A.

Every Sprint to promote shared learning.

B.

As needed, with no special allowance for changes in productivity.

C.

Never, it reduces productivity.

D.

As needed, while taking into account a short-term reduction in productivity.

Question # 19

An organization has decided to adopt Scrum, but management wants to change the

terminology to fit with terminology already used. What will likely happen if this is done?

(choose the best answer)

A.

Without a new vocabulary as a reminder of the change, very little change mayactually happen.

B.

The organization may not understand what has changed within Scrum and thebenefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Question # 20

Who should make sure everyone on the Scrum Team does their tasks for the Sprint?

(choose the best answer)

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Scrum Team.

E.

All of the above.

Question # 21

When might a Sprint be cancelled?

(choose the best answer)

A.

When the Developers determine the product plan is infeasible.

B.

When it becomes clear that not everything will be finished by the end of the Sprint.

C.

When the sales department has an important new opportunity.

D.

When the Sprint Goal becomes obsolete.

Question # 22

Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency?

(choose the best answer)

A.

The Product Backlog is only updated at the Sprint Review, when both the ScrumTeam and the stakeholders are available.

B.

Product Backlog items should hold no more than 8 points of work, which is theaverage in the range of acceptable sizes of 1, 2, 3, 5, 8, and 13.

C.

Product Backlog items must be sized such that the highest ordered items are no bigger than a Sprint.

D.

The Product Backlog is only updated at a release planning meeting with thestakeholders and the change control board present.

E.

The Product Backlog is continually kept up to date with the most recent insights.

Question # 23

During the Sprint Retrospective a Scrum Team has identified several high priority process

improvements. Which of the following statements is most accurate?

(choose the best answer)

A.

The Scrum Team may add the items to the Sprint Backlog for the next Sprint.

B.

The Scrum Team should decline to add a process improvement to the Sprint Backlogwhen things are running smoothly.

C.

The Scrum Team should choose at least one high priority process improvement toplace in the Product Backlog.

D.

The Scrum Master selects the most important process improvement and places it inthe Sprint Backlog

Question # 24

You are the Scrum Master of a new, to be developed Product. Development is going to require

45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

(choose the best answer)

A.

What is the right mixture of senior and junior people on each team?

B.

Who are the subject matter experts on each team?

C.

Who are going to be the team leads?

D.

How will we make sure all teams have the right amount of expertise?

Question # 25

Why is it important that there is only one Product Owner per product?

(choose the best three answers)

A.

The Scrum Master knows who acts as their backup while on vacation.

B.

It would confuse the stakeholders if they had to work with more than one person.

C.

It is clear who is accountable for the ultimate value of the product.

D.

It helps avoid barriers to effective communication and rapid decision-making.

E.

The Scrum Team always knows who determines the order of the ProductBacklog.

Question # 26

Who is accountable for clearly expressing Product Backlog items?

(Choose the best answer)

A.

The Product Owner.

B.

The business analyst who represents the Product Owner.

C.

The Scrum Master.

D.

The Scrum Master, or the Scrum Master may have the Developers do it.

Question # 27

Who has the final decision about the order of items in the Product Backlog?

(choose the best answer)

A.

The Scrum Master.

B.

The Stakeholders.

C.

The Scrum Team.

D.

The Developers.

E.

The Product Owner.

Question # 28

What activities would a Product Owner typically undertake in the period between the end of the

current Sprint and the start of the next Sprint?

(choose the best answer)

A.

There are no such activities. The next Sprint starts immediately after the currentSprint.

B.

Refine the Product Backlog.

C.

Update the project plan with stakeholders.

D.

Work with the Quality Assurance departments on the Increment of the current Sprint.

Question # 29

True or False: The Product Owner must write all of the Product Backlog items (e.g., user stories, requirements, etc.) on the Product Backlog before handing them over to the Scrum Team.

A.

True

B.

False

Question # 30

True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.

A.

True

B.

False

Question # 31

True or False: Multiple Scrum Teams working on the same product or system all select work

from the same Product Backlog.

A.

True

B.

False

Question # 32

Which approach is best for Scrum Teams in order to produce valuable Increments?

(choose the best answer)

A.

Each Developer works on the component where they feel that they can contribute.

B.

Each Scrum Team works on an independent set of components.

C.

Each Scrum Team is accountable for developing functionality from beginning to end.

D.

Each Scrum Member works only as an independent layer of the system.

Question # 33

What typically happens if the Product Backlog is not sufficiently clear at Sprint Planning?

(choose the best answer)

A.

The Product Owner should select the Sprint Goal for the Scrum Team so that work can begin.

B.

The Developers will find it difficult to create a Sprint forecast they are confident they can meet.

C.

Nothing in particular.

D.

The Scrum Master should not allow this to happen. Look for a new Scrum Master and re-start the Sprint.

E.

Sprint Planning is canceled so refinement can be done first.

Question # 34

The Product Owner is the person who will be held accountable if a product does not achieve its goals or deliver value. Does this mean that the Product Owner has the final say over the Definition of Done?

(choose the best answer)

A.

Yes, the Product Owner decides the Definition of Done. The Developers may beconsulted.

B.

No, the Scrum Team decides the Definition of Done, if it is not a standard of the organization. The Product Owner is just one member of the Scrum Team.

Question # 35

Which of the following is an example of an Increment?

(choose the best answer)

A.

A plan for the overall product release.

B.

A mock-up of the product marketing materials.

C.

A design for the product.

D.

A product roll-out plan.

E.

A valuable, useful set of product features.

F.

All of the above.

Question # 36

When does the next Sprint begin?

(choose the best answer)

A.

The Monday following the Sprint Review.

B.

Immediately after the conclusion of the previous Sprint.

C.

Immediately following the next Sprint Planning.

D.

When the Product Owner is ready.

Question # 37

Who is on the Scrum Team?

(choose all that apply)

A.

Scrum Master.

B.

Product Owner.

C.

Developers.

D.

Project Manager.

E.

None of the above.

Question # 38

What does it mean for a Scrum Team to be cross-functional?

(choose the best answer)

A.

The Scrum Team includes not only developers but also business analysts, architects,and testers.

B.

The Scrum Team includes skilled individuals who together have all the skillsnecessary to create value each Sprint.

C.

Developers on the Scrum Team work closely with business analysts, architects,developers, and testers who are not on the team.

D.

The Scrum Team is a virtual team drawing from separate teams of business analysts,architects, developers, and testers.

Question # 39

The Developers find out during the Sprint that they are not likely to build everything they forecast. What would you expect a Product Owner to do?

(choose the best answer)

A.

Skip Product Backlog refinement activities.

B.

Inform management that more Developers are needed.

C.

Change the Sprint Goal.

D.

Re-work the selected Product Backlog items with the Developers to meet the Sprint Goal.

E.

Cancel the Sprint.

Question # 40

True or False: Cross-functional teams are optimized to work on one component or layer of a system only.

A.

True

B.

False

Question # 41

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

(choose the best answer)

A.

Methods of communication.

B.

The way the Scrum Team does Sprint Planning.

C.

Skills needed to improve the Developers ability to deliver.

D.

The Definition of Done.

E.

All of the above.

Question # 42

Which of the following are criteria to order Product Backlog items?

(choose all that apply)

A.

Value of Product Backlog items.

B.

Dependencies between Product Backlog items.

C.

Dependencies to other products.

D.

The availability of the Scrum Master.

E.

All of the above.

Question # 43

Which statement best describes a Product Owner ' s responsibility?

(choose the best answer)

A.

Ensuring that the work meets the commitments to the stakeholders.

B.

Maximizing the value of the work the Scrum Team does.

C.

Keep stakeholders from distracting the Developers.

D.

Directing the Developers.

Question # 44

What is the accountability of the Product Owner during Sprint 0?

(choose the best answer)

A.

Determine the composition of the Scrum Team to meet the release plan.

B.

There is no such thing as Sprint 0.

C.

Create the overall release plan to ensure that organizational goals are met.

D.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

E.

Gathering, eliciting, and analyzing the requirements to build the Product Backlog.

Question # 45

Which is NOT a valid consideration when ordering a Product Backlog?

(choose the best answer)

A.

Dependencies on other Product Backlog items.

B.

Importance to customers.

C.

Alignment with business strategy and goals.

D.

Tools and techniques.

E.

Risk.

Question # 46

When must the Product Owner participate in the Daily Scrum?

(choose the best answer)

A.

When the Scrum Master asks the Product Owner to attend.

B.

When the Product Owner is actively working on items on the Sprint Backlog;however, they participate as a Developer.

C.

When there are impediments to discuss.

D.

When the Product Owner needs to represent the stakeholders ' point of view to theDevelopers.

Question # 47

A Scrum Master is working with a Scrum Team that has Developers in different physical

locations. The Developers meet in a variety of meeting rooms and have much to do logistically

(for example: reserve meeting rooms and set up conference calls) before the Daily Scrum.

What action should the Scrum Master take?

(choose the best answer)

A.

Allow the Developers to self-manage and determine for themselves what to do.

B.

Ask the Developers to alternate who is responsible for meeting setup.

C.

Set up the meeting and tell the Scrum Team that is how it will be done.

D.

Inform management and ask them to solve it.

Question # 48

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)

A.

Add them to the Product Backlog to ensure transparency.

B.

Run the integration and regression tests before the end of the Sprint, andcapture the open work for the Sprint Backlog of the next Sprint.

C.

Add them to the Definition of Done so the work is taken care of every Sprint.

D.

Put them on a separate list on the Scrum board, available for all to see.

Question # 49

A new Developer is having continuing conflicts with existing members of the Scrum Team,

which is impacting the delivery of the Increment. If necessary, who is responsible for removing

the Developer from the Scrum Team?

(choose the best answer)

A.

The Product Owner is responsible, they control the return on investment (ROI).

B.

The Scrum Team is responsible.

C.

The Scrum Master is responsible, they remove impediments.

D.

The hiring manager is responsible, they hired the Developer.

Question # 50

When can Developers cancel a Sprint?

(choose the best answer)

A.

When functional expectations are not well understood.

B.

When the selected Product Backlog items for the Sprint become unachievable.

C.

They cannot. Only Product Owners can cancel Sprints.

D.

When the Product Owner is absent too often.

E.

When a technical dependency cannot be resolved.

Question # 51

At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the

Definition of Done. What two things should happen with the undone Product Backlog item?

(choose the best two answers)

A.

Review the item, add the done part of the estimate to the velocity and create aStory for the remaining work.

B.

If the stakeholders agree, the Product Owner can accept it and release it to theusers.

C.

Do not include the item in the Increment this Sprint.

D.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

PSPO-I PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PSPO-I PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Professional Scrum Product Owner (PSPO I) Exam
  • Last Update: Apr 11, 2026
  • Questions and Answers: 173
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PSPO-I Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included