Which of the following must be considered in order to meet Energy and Atmosphere Prerequisite, Fundamental Refrigerant Management if the tenant requires 24-hour cooling in a server room?
A Client is fitting out a building with area 20,500 ft2 (1 904.5 m2) and wishes to pursue the Energy and Atmosphere Credit, Enhanced Commissioning. Who may be appointed as the Commissioning Authority (CxA) for the project?
Which of the following would contribute to the Location and Transportation Credit, Surrounding Density and Diverse Uses, Option 2. Diverse Uses?
In the pre-design phase, a plumbing engineer identified that the low-flow fixtures which met the Owner's requirements could achieve total reductions in indoor water usage of 39%. Which strategies should be assessed to meet the Owner's Project Requirements goals of 45% reduction?
For the achievement of Materials and Resources Credit, Interiors Life Cycle Impact Reduction, Option 1. Interior Reuse, how are hazardous materials accounted for in the calculation?
The Commissioning Authority (CxA) must report results, findings and recommendations directly to the
Which of the following prerequisites or credits is affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit, Thermal Comfort?
For Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification, the final Cx report must include the
Discussing the project goals to help identify the credits and options that the team should attempt is an example of
Drywall is purchased from a local manufacturer for a total materials cost of $10,000 USD. The specification of the drywall is:
· 5% of the product is comprised of post-consumer recycled paper sourced from a pulp mill 25 mi. (40 km) away;
· 50% of the product is post-consumer recycled gypsum attained from a facility 30 mi. (48 km) away;
· new gypsum is extracted from a mine 175 mi. (282 km) away.
What is the contributing value of the drywall to Materials and Resources Credit, Building Product Disclosure and Optimization - Sourcing of Raw Materials, Option 2. Leadership Extraction Practices?
Which systems must be commissioned to earn Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification?
The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction ensures that eligible newly installed plumbing fixtures will
A tenant moves into an existing building where no modifications to the building envelope will be made. What credit would be affected by the visible light transmittance of the existing exteriorglazing?
Best practices recommend that the LEED AP confirm that minimum program requirements have been met
For a retail LEED Interior Design and Construction project, the products include 25% by cost Cradle to Cradle v3, Gold certified products, and 25% by cost products assessed with the GreenScreen List Translator. Which of the following Materials and Resources and Innovation credits can the project team achieve?
A 1,500 ft2 (139 m2) mobile home is built in the downtown area of a major city. 90% of the project's gross floor will be
completed by the time of occupancy. LEED certification is being sought. Which rating system would be the most
appropriate one to use?
A project team wants to achieve Materials and Resources Credit, Building Product Disclosure and
Optimization - Material Ingredients. By what means can a product demonstrate their material ingredient optimization?
For an Interior Design and Construction project to earn Innovation Credit, LEED Accredited Professional, who must submit their credentials as a principal participant of the project team?
Which of the following appliances are included in Water Efficiency Prerequisite, Indoor Water Use Reduction?
A proposed LEED project will be located within the boundary of a development that has been successfully certified at the Silver level under LEED for Neighborhood Development. The project will earn 10 points from the Location and Transportation Credit, LEED for Neighborhood Development Location. How many additional credit points are available to the project team under the Location and Transportation category?
A luxury hotel project is one point away from attaining LEED Platinum certification. The LEED AP is recommending that the team pursue Innovation Credit, Innovation, Option 3. Additional Strategies. Which of the following credits would be applicable?
A renovation project includes both a new kitchen sink and shower and an existing lavatory and water closet within the LEED project boundary. How would the project perform the Water Efficiency Credit, Indoor Water Use Reduction calculations?
What should a team focus on first to significantly improve energy performance or achieve the lowest possible operation cost?