3 Months Free Update
3 Months Free Update
3 Months Free Update
Where can you define that a network is a "header-account assigned" or "activity-account assigned"?
Which combination allows you to assign the material components in one WBS element to different grouping WBS element?
There are 2 correct answers to this question.
Response:
You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?
Please choose the correct answer.
Response:
Can you specify in the application which status profile should be used the first time you set a user status where a status profile has not yet been defined in the project profile?
Please choose the correct answer.
Response:
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?
There are 2 correct answers to this question.
Response:
Based on which of the following; reservations or purchase requisitions can automatically be created for a project?
There are 2 correct answers to this question.
Response:
Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response?
Please choose the correct answer.
Response:
You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system.
Which of the following business processes can be mapped in Sales and Distribution?
There are 3 correct answers to this question.
Response:
How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities?
Please choose the correct answer.
Response:
What do you use in the parameters for network type to specify whether a workflow is to be generated in the case of purchase order relevant change?
Please choose the correct answer.
Response:
Which of the following items can be included in the planned costs for an activity besides the cost of the activity?
There are 3 correct answers to this question.
Response:
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?
Please choose the correct answer.
Response:
What is the transaction code for editing the planning profile?
Please choose the correct answer.
Response:
When using budgeting and active availability control, which business transactions affect the current budget?
There are 3 correct answers to this question.
Response:
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.
Response:
Which type of billing is generally used in plant engineering and construction projects?
Please choose the correct answer.
Response:
Which of the following cannot be entered when using service activities in networks for planned and unplanned services?
Please choose the correct answer.
Response:
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response: