3 Months Free Update
3 Months Free Update
3 Months Free Update
The following defect management process is in use at a company… What is the most important recommendation you would make for the defect report template in this process?
You are a test manager in charge of integration, system, and user acceptance testing for a bank. You are working on a project to upgrade an existing ATM to allow customers to obtain cash advances from supported credit cards.
The system should allow cash advances from €20 to €500 (both inclusive) for all supported credit cards. The supported credit cards are American Express, VISA, Eurocard, and Mastercard. The system should be easy to use for all users, including new users. The organisation is currently in a transition to Agile and already well on its way.
In the test plan, the following items are listed under the heading"Items and features to be tested":
All supported credit cards
Language localisation
Valid and invalid advance
Usability
Response time
Which of the following topics would be most important for you to address in detail in the test plan?
You have been contracted to manage the user acceptance testing of a new reservation system for a travel agency. The reservation system is being developed by a third party. Detailed specifications are available, and an estimate of the total development effort exists. The system will be delivered in four agreed increments.
Which of the following estimation techniques would be most appropriate to use in this context?
You are involved in the selection of a test management tool and have decided to calculate the ROI for the two potential tools: TestMaker and ImproveIT.
TestMaker is priced at €15,000 with yearly maintenance costs of €1,500. Its traceability to requirements feature is strong and the defect management process can easily be customised to meet the needs of the organisation. Effort for test management activities is expected to decrease by 20%.
ImproveIT is priced at €20,000 with yearly maintenance costs of €2,500. Its traceability feature is also strong and has a high level of usability. It also has interesting options for adding extensions to its features in the future. Effort for test management activities is expected to decrease by 30%.
Based on the calculated ROI, which tool would you suggest?
Assume that you have calculated the following costs of quality:
Average cost of detection: €350
Average cost of internal failure: €250
Average cost of external failure: €4,500
The average costs of detection and internal failure are calculated using the number of defects found prior to release, while the average cost of external failure is calculated using the number of defects found after release.
What is the saving in cost of quality for each defect found in testing?
You are a test manager in charge of integration, system, and acceptance testing for a bank. You are working on a project to upgrade an existing ATM to allow customers to obtain cash advances from supported credit cards. The system should allow cash advances from €20 to €500 (both inclusive) for all supported credit cards. The supported credit cards are American Express, VISA, Eurocard, and Mastercard. The system should be easy to use for all users, including new users.
In the master test plan, the following items are listed in the section named "items and/or features to be tested":
I. All supported credit cards
II. Language localisation
III. Valid and invalid advances
IV. Usability
Assume that the project has now been completed, and the ATM system has been in use for just over two months. You are planning a retrospective meeting for the testing work performed.
Which of the following areas is most likely to be considered in this retrospective?
During which test planning task are the test design techniques to be applied during the project, identified and selected?
You are currently leading an independent test team. Based on the information given in the scenario, identify how the team could be improved most effectively.
You are a test manager developing a master test plan. As part of the master test plan, you are defining exit criteria for the various test levels.
Which of the following exit criteria would be most appropriate and SMART for component testing, and which one would be most appropriate and SMART for system testing?
i. 95% of the tests prepared are executed successfully
ii. All test cases have been run
iii. 80% decision coverage for all tests run
iv. At least 30 defects have been found
v. At least two weeks of test execution
vi. No more open defects
Which of the following is not a key decision when defining a project test strategy?