Cyber Monday Special Sale - 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: spcl70

Practice Free L4M3 Commercial Contracting Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the CIPS L4M3 Exam the most current and reliable questions . To help people study, we've made some of our Commercial Contracting exam materials available for free to everyone. You can take the Free L4M3 Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

Which of the following is the best definition of consideration in contract law?

A.

Full statement about something to provide

B.

The act of thinking carefully about one thing

C.

One thing given in exchange

D.

Formal discussion between people who are trying to reach an agreement

Question # 7

Maximum Score 1

An effective key performance indicator should be:

A.

Standardised, meaningful, achievable, realistic, typical

B.

Sustainable, measurable, analysed, realistic, timely

C.

Specific, measurable, achievable, realistic, timely

D.

Specific, meaningful, analysed, realistic, typical

Question # 8

Which of the following are true statements about RFQ process? Select TWO that apply.

A.

Buying organisation should only send RFQ to pre-qualified suppliers

B.

RFQ process requires the suppliers to submit their technical proposals

C.

RFQ process creates heavier administrative burdens than tendering process

D.

Price is often the only variable in the RFQ and quotations

E.

RFQ process is not suitable for low value purchase

Question # 9

According to rule of contract formation, which of the following is a valid acceptance?

A.

The person orally agrees to pay the offered price

B.

The person states that she is able to pay the offered price

C.

The person asks for a lower price

D.

The person says that she will think about it overnight

Question # 10

Which of the following are advantages of using a model form contract in negotiations between buyer and seller?

These contracts can save time in negotiations

Each contract is approved by the courts

These contracts are appropriate for all complexities

The contracts are well-known to both parties

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Question # 11

Which of the following is most likely to reduce ITT preparation time while maintaining the clarity of tendering documents?

A.

Using request for quotation

B.

Standardising documentation whenever possible

C.

Monitoring usage

D.

Eliminating pre-qualification stage from all tendering processes

Question # 12

Which of the following are always included within a framework agreement? Select TWO that apply:

A.

Exact quantity to be purchased

B.

Call-off procedure

C.

Exact price to be paid

D.

Duration

E.

Insurance

Question # 13

The pricing arrangement in which markup is added into cost base to calculate the final price is known as...?

A.

Fixed Price approach

B.

Market based approach

C.

Price indices

D.

Cost plus pricing

Question # 14

Maximum Score 1

The nature of the "Battle of the forms" is when both buyer and supplier are attempting to ...

A.

Secure their own terms and conditions

B.

Create a collaborative relationship

C.

Create a performance specification

D.

Form a joint contract

Question # 15

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Question # 16

Social and environmental criteria are often incorporated into which of the following type of specification?

A.

Design specification

B.

Technical specification

C.

Conformance specification

D.

Output specification

Question # 17

Which of the following is the international standard for labelling hazardous substances?

A.

GPS

B.

HSE

C.

CODEX STAN 1-1985

D.

GHS

Question # 18

Maximum Score 1

Contract terms are statements by the parties to the contract as to what they understand their rights and obligations to be under the contract. It is important from the outset that there is a genuine agreement between the parties as to what the contract terms are. After the contract has been made, it is too late for either party to alter its terms unilaterally.

Which of the following is another role that negotiated contract terms might play?

A.

Defining conditions and contingencies that may alter the arrangement

B.

Ensuring any future contracts will be on the buyer's terms

C.

Providing a guarantee that the supplier will never fail to perform under any circumstances

D.

Identifying the type of contractual disputes in which the courts might decline to adjudicate

Question # 19

A large company supplies a lot of products. Their shipments are often delayed and customers are not satisfied. Which of the following KPIs is most likely to be applied to this situation?

A.

Technical support

B.

OTIF delivery

C.

Delay damages

D.

Consignment stock availability

Question # 20

Maximum Score 1

When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?

    A confidentiality clause designed to protect either party

    A clause stating how long the service is to be outsourced

    A clause stating how long the employees can take for holiday

    A contract variation and price adjustment clause

A.

1 and 4 only

B.

1 and 2 only

C.

3 and 4 only

D.

2 and 4 only

Question # 21

Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:

A.

Short turnaround times

B.

Quick implementation

C.

Driving forward planning culture

D.

Lower administration costs

E.

Reducing risks of bribery and corruption

Question # 22

Consequences and actions that arise from certain KPI scores must be...? Select TWO that apply.

A.

Mutually agreed

B.

Deliberately omitted

C.

Documented

D.

Unilaterally imposed by the purchaser

E.

Terminated

Question # 23

XYZ Ltd is negotiating a long-term supply contract of important parts with a supplier. Dave, procurement manager teams up with Alla, legal manager to construct a service level agreement. Dave is concerned that poor performance of supplier may cause damages to the operations of the organisation. Which of the following can be used in conjunction with SLA to compensate the buying organisation in case of supplier's poor performance?

1. Warranties

2. Force majeure clauses

3. Penalty clauses

4. Service credits

A.

1 and 3 only

B.

3 and 4 only

C.

1 and 2 only

D.

4 and 2 only

Question # 24

One of the important features in the formation of a contract is the need to have a 'consensus ad idem' between the contracting parties. 'Consensus ad idem' can be translated as meaning:

A.

A promise to commit the contract to written form

B.

A meeting of minds where all parties have the same understanding of the terms

C.

Let the buyer beware before agreeing the contract

D.

An agreement on the main item of the contract

Question # 25

Which of the following are among five 'pillars' of information assurance?

1. Recovery plan

2. Availability

3. Non-repudiation

4. Governance

A.

2 and 3 only

B.

1 and 2 only

C.

1 and 4 only

D.

3 and 4 only

Question # 26

Blakenall District Hospital (BDH) is a large hospital that is a major part of the government’s health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub-contractors. Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy hascaused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?

A.

No, variable pricing would only benefit the suppliers

B.

Yes, this type of arrangement would provide absolute certainty when budgeting

C.

Yes, this pricing arrangement would reimburse the fluctuation of material prices

D.

No, price adjustment should be applied to short-term supply contract only (3-month duration or less)

Question # 27

In what way might a contract clause be used to stop the supplier from making unwarranted price increases during the term of the contract?

A.

The buyer deletes any contract clauses that may refer to stage payments

B.

The buyer inserts a contract clause that stipulates the invoice payment dates

C.

The buyer inserts a price adjustment clause in the contract

D.

The buyer deletes any contract clauses that may refer to price increases

Question # 28

A senior buyer is preparing specification for the next purchase. He intends to embed social and environmental criteria that align with his organisation's overarching strategy. Which of the following provides the social and environmental objectives that an organisation pursues?

A.

Economic performance

B.

Procurement Systems and Technology

C.

Economy of scale

D.

Organisation’s CSR policies

Question # 29

A procurement professional is preparing a sale & purchase contract of a machinery. Which of the following clauses should be added to the contract? Select TWO that apply

A.

Supplier selection mechanism

B.

Insurance requirements

C.

Period of hire

D.

Ratio decidendi

E.

Guarantees

Question # 30

Transformers & Rectifiers Ltd wanted to buy some specialist gaskets. They sent a request for quotation with specification to Needs Ltd. The supplier replied with a quotation in which had its own terms and conditions. The buyer edited delivery terms on the quotation and sent the document back to Needs Ltd. Gaskets were delivered to Transformers’ premise with an invoice from Needs Ltd. Which of the following is most likely to be the governing terms if the two companies must settle the dispute at court?

A.

Edited terms and conditions

B.

Terms and conditions in the request for quotation

C.

Terms and conditions in the invoice

D.

Terms & conditions in the original quotation

Question # 31

Maximum Score 1

Buyer O has placed an order for the supply and installation of six new servers for a total amount of £600,000 from Supplier A. Which of the following could potentially be treated as examples of a liquidated damages clause within the contract for the supply of the servers?

    If the supplier delivers any of the servers late, £1,000 per server will be deducted from the order per day

    This contract is subject to delay remedies of £X - the amount to be agreed by both parties during delivery

    The sum for breach of the completion date for the order is £40,000 per day up to a maximum of 50% of the contract price

    If the performance of any of the servers degrades within five years, a full refund of £600,000 will be provided

A.

1 and 2 only

B.

3 and 4 only

C.

1 and 3 only

D.

2 and 4 only

Question # 32

What is the pricing method that incentivises the supplier to control their costs?

A.

Penetration pricing

B.

Cost-plus pricing

C.

Target Costing

D.

Skimming pricing

Question # 33

A school has a contract for the supply of fruit for break time. The school needs the fruit delivered by 10am every morning to be served at 10:30am. How would this best be covered in a commercial agreement?

A.

Note on each purchase order

B.

Pricing schedule

C.

Sales of Goods Act 1974

D.

Contractual term

Question # 34

Maximum Score: 1

Which of the following are examples of a lack of 'capacity' to enter into a contract?

    A contracting party has a severe mental disorder

    A contracting party has failed to concentrate during negotiations

    A contracting party is 19 years of age

    A contracting party (corporation) has acting 'ultra vires' (beyond its defined legal powers)

A.

1 and 2 only

B.

1 and 4 only

C.

2 and 3 only

D.

2 and 4 only

Question # 35

Which of the following is the contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise?

A.

Indemnity clause

B.

Liquidated damage clause

C.

Insurance clause

D.

Exclusion clause

Question # 36

Which of the following are likely to be advantages of using request for quotation? Select TWO that apply:

A.

Lower administration costs

B.

Short turnaround times

C.

No specification required

D.

Helping the buying organisation assess both price and quality

E.

Encouraging suppliers to submit creative solutions

Question # 37

In a contract, express terms and implied terms may contradict on the same issues. Under which of the following circumstances, implied terms will override express terms?

A.

Implied terms are created by trade customs

B.

Contracting parties are silent on a matter that was not included in express terms

C.

No circumstances. Express terms always take precedence over implied terms

D.

Implied terms are created by law which prevents them to be overridden

Question # 38

Which of the following statements is FALSE on contracts for the leasing of assets?

A.

The party responsible for maintenance, insurance and taxes is subject to negotiation

B.

In lease agreement, the possession and right of use of an asset are transferred to the lessee

C.

The ownership of leased asset is transferred to the lessee at the end of the period

D.

The lessee may bear some risks of ownership, such as the liability to insure the asset

Question # 39

Carillion Ltd is a major construction contractor in the UK. The company commits to continuous improvement and sets out a performance management program that is integrated across the organisational, individual, and supplier levels. To ensure that the suppliers acknowledge the program, every time negotiating the contract terms with suppliers, the procurement team of Carillion appends a performance management framework to the draft document as a schedule. Is the action of procurement team appropriate?

A.

No, because the framework will increase the complexity of the contract

B.

No, because the performance management should be solely developed by suppliers

C.

Yes, because the framework should have legal standing as a part of contract

D.

Yes, because Carillion wants to implement early supplier involvement

Question # 40

A tire manufacturer entered into a contract with a distributor. In the contract, the distributor is prohibited from selling the tire under the price list. The distributor must pay $5 for each tire sold in breach. The amount of $5 is known as...?

A.

Penalty

B.

Quantum meruit

C.

Liquidated damages

D.

Caveat Emptor

Question # 41

Which of the following would be useful tools to incentivise supplier innovation over the duration of the contract?

1. Gainshare arrangement

2. Liquidated damages

3. Service credits

4. Fixed bonus payments

A.

3 and 4 only

B.

2 and 4 only

C.

1 and 4 only

D.

1 and 3 only

Question # 42

Buyer D agrees a contract with Supplier C which includes the words 'to be agreed' in relation to the date for delivery of the goods. At the time of the contract, Buyer D is aware that the goods take two days to produce and one day to deliver. Buyer D contacts the supplier one week later, requesting the goods be delivered the following day. Supplier C is unable to deliver the next day but rather delivers the goods three days later. Is it the case that Buyer D can legally refuse to pay for the goods because Supplier C is in breach of contract?

A.

Yes, because the delivery date is an express term within the contract

B.

Yes, because the goods should have been delivered within three days

C.

No, because the goods were delivered within a reasonable time

D.

No, because there is a contract in place and the delivery date does not matter

Question # 43

Maximum Score 1

The Bravo Engineering Company is negotiating a maintenance contract with Express Deliveries Ltd. This large logistics company uses modern robotic storage and picking warehouse machinery to identify, sort, and facilitate over 200,000 orders each day. The volatile nature of the business means that the parties should build maximum flexibility into the performance management aspects of the contract.

Which of the following would be most appropriate to set out the parties’ obligations under the maintenance contract?

A.

A formal appendix to the maintenance contract

B.

A non-binding side-agreement to the maintenance contract

C.

A Service Level Agreement issued after the maintenance contract

D.

A clause that disclaims all accountability for the contract for the buyer

Question # 44

CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost - target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:

A.

Accrual expense

B.

Final price

C.

Purchaser goodwill

D.

Supplier share

E.

Actual cost

Question # 45

Which of the following statement is true about one-off contract?

A.

Suppliers have many opportunities to improve the quality during the performance of one-off contract

B.

One-off contracts can be used for services and works

C.

Ad-hoc purchase is not a type of one-off purchase

D.

One-off contracts only apply to low-value, low-risk purchase

Question # 46

Which of the following should be applied when measuring frequency of on-time deliveries during a contract period?

A.

Qualitative assessment

B.

Numerical measure

C.

Binary measure

D.

Subjective measure

Question # 47

Why would you use a non-disclosure agreement?

A.

To protect parties, where information has been shared that is not in the public domain

B.

To allow parties the freedom to disclose confidential information to the public domain

C.

To agree between parties what information is and is not confidential and what can be in the public domain

D.

To give parties permission to share all information in the public domain

Question # 48

Prior to circulating the service specification to a tendering supplier, it is good practice for the purchasing organisation to request completion of a non-disclosure agreement. Is this statement correct?

A.

No, because the non-disclosure agreement has no legal standing

B.

Yes, because the non-disclosure agreement protects intellectual property

C.

Yes, because the non-disclosure agreement encourages transparent bidding

D.

No, because the non-disclosure agreement only applies after contracting

Question # 49

Which of the following is an invitation to treat?

A.

Purchase order

B.

Invoice

C.

Price list

D.

Tender bid

Question # 50

Under which of the following scenarios an RFQ is most likely to be used?

A.

Purchase of a small number of standardised products under a framework agreement

B.

Purchase of complex machinery

C.

Design of a unique and complex software code

D.

When the buying organisation does not know the requirements in details and needs the input from suppliers

Question # 51

RL Corporation are developing a specification for a new piece of equipment. They have no prior experience of procuring the item. The procurement manager wants to understand the benefits and risks of conducting market dialogue to help inform the procurement strategy. Which of the following are three potential advantages of market dialogue? Select THREE that apply.

A.

There is no need to conduct a full procurement process

B.

More collaborative supplier relationships can be developed

C.

Organisations can clarify and optimise the requirements

D.

The procurement process becomes significantly quicker

E.

Purchasers can gauge market interest and competition

F.

Market dialogue is risk-free as there is no contract or agreement

Question # 52

Nestle gave away records of “Rockin’ Shoes” or a voucher to people who sent in three wrappers from Nestle’s 6d. milk chocolate bars as well as 1s 6d. Which of the following were the consideration of Nestle’s customer? Select TWO that apply

A.

Three wrappers

B.

1s 6d

C.

“Rockin’ Shoes” record

D.

The voucher

E.

Milk chocolate bar

Question # 53

When writing an implementation section for an IT requirements specification, which factors would be appropriate for inclusion? Select TWO that apply.

A.

Required response timeframes for service requests

B.

Mandatory training required for supplier’s staff

C.

Details of applicable legal and regulatory standards

D.

Integrations required with existing systems

E.

Lists of technical terms and abbreviations

Question # 54

A procurement manager is preparing a long-term contract with a major supplier. She decides to use the variable pricing arrangement using price indices. The payment terms describe the circumstances and mechanism where the price is allowed to change. In order to successfully manage this type of contract, the buying organisation should have...?

A.

Good market knowledge

B.

Selection of base year

C.

Value for money

D.

Economy of scale

Question # 55

Which of the following can be considered as implied terms in a contract?

1. Case law

2. Statute

3. Trade custom

4. A term can never be implied, it must always be expressed by the parties

A.

1,3 and 4 only

B.

1, 2 and 3 only

C.

1, 2 and 4 only

D.

2, 3 and 4 only

Question # 56

When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?

A.

Right

B.

Risk

C.

Legal responsibility

D.

Contractual obligation

Question # 57

Under English law's general legal principles of contract formation, which of the following are likely to be offers? Select TWO that apply.

A.

Invitation to tender

B.

Quotation

C.

Purchase order

D.

Advertisement

E.

Catalogue

Question # 58

Which of the following is an agreement between service provider and user that quantifies the minimum quality of service?

A.

Service charter

B.

Service guarantee

C.

SLA

D.

Service standard

Question # 59

Royal Naval Hospital at Rockstown, Anyport manages a fleet of nine ambulance vehicles. During busy periods, it becomes very difficult to keep track of the location of each ambulance (and the nature of their journey). Continual problems lead to the proposal for a new control system (ERNS).

For this ERNS project, the procurement department has drafted a specification in which only a bullet point list of basic requirements was written down. The procurement manager understands that the specification should be developed more specifically but a cross functional team from the Hospital could not do that. A senior buyer suggests that some of Hospital's pre-qualified suppliers could support them in developing the specification.

Which of the following should be a priority approach of procurement department in developing dialogue with those suppliers about specification development?

A.

Internal discussion

B.

General networking

C.

One-to-one meeting with the suppliers

D.

Request for quotation from the suppliers

Question # 60

Which of the following should be used in a contract for window cleaning during the next three months?

A.

Variable pricing arrangement

B.

Fixed pricing arrangement

C.

Standard schedule of rates

D.

Cost-plus arrangement

Question # 61

A service contract is going to be expired, which data source is good to create specifications for ITT?

1. Incumbent supplier

2. Maintenance services

3. Alternative supplier

4. User's knowledge

A.

1, 2 and 3

B.

1, 3 and 4

C.

1, 2 and 4

D.

2, 3 and 4

Question # 62

Bandpro is a reseller of branded computer products to the private and public sector. The procurement team must purchase 500 items each day solely by multiple phone calls and emails to suppliers. Due to this practice, it takes a lot of time to track and collect relevant documents.Some important documents even get lost, which makes procurement audit more burdensome. Which of the following would increase the robustness of audit trails in procurement activities?

A.

Every evidence must be recorded by paper

B.

Adopt e-procurement

C.

Spend less time on auditing procurement procedures

D.

Rectify non-compliant activities

Question # 63

Under hire purchase agreement, when will the ownership of asset legally belong to the purchaser?

A.

When the final instalment is paid

B.

When the purchaser takes possession of the asset

C.

When the down payment is made

D.

When the agreement is signed

Question # 64

To expand its operation, Steel Co. decides to build a new plant. Despite of excitement, the senior management is very concerned about the complexity and risks of such project. Hugo, the procurement manager, suggests that the company can adopt a model form of contract. What is the advantage of using model form of contract?

A.

It shifts the balance of power in the favour of the buyer rather than the contractor

B.

The company could avoid the need to draft a complex contract from blank

C.

Model form of contract eliminates the need for legal advice totally

D.

The company does not need to draft the drawings as well as specification anymore

Question # 65

Maximum Score 1

Denny is putting together the final version of a contract to send out to a supplier. He places certain documentation into additional contract schedules at the end of the main contract.

Which of the following would be suitable inclusions to the additional schedules? Select TWO that apply.

A.

Financial statements

B.

Health and safety commitments

C.

Suppliers references

D.

Non-disclosure agreement

E.

A blank RFQ form

Question # 66

A supermarket purchases a new batch of house cleaner from new supplier. The supermarket is concerned about possible damage that the house cleaner may cause to consumers' floor. What type of insurance must they cover?

A.

Fire and explosion insurance

B.

Product liability insurance

C.

Professional indemnity insurance

D.

Public liability insurance

Question # 67

A category buyer is purchasing medical gases for a hospital, but is experiencing volatile and unfavourable market conditions due to multiple global external factors. Owing to the volatility, the hospital's finance director has tasked the buyer with providing certainty of costs for the next 18 months. Which of the following pricing methods will enable budgeting certainty, despite the highly volatile market conditions?

A.

A fixed pricing arrangement

B.

A cost plus award fee agreement

C.

Fixed pricing with economic price adjustments

D.

A penetration pricing strategy

Question # 68

A procurement professional is drafting payment terms for a commercial contract. He is considering about payment method if defective products are found. Which of the following should be embedded in payment terms to control this issue?

A.

Remedies for late payment

B.

Pay-less notice

C.

Invoice preparation

D.

Retention clause

Question # 69

In order to monitor supplier’s performance, an organization decides to draft performance management frameworks. Which of the following are the components of a performance management framework? Select THREE that apply:

A.

Targets

B.

KPIs

C.

Consequences

D.

Indemnity

E.

Force majeure

F.

Justification

L4M3 PDF

$33

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

L4M3 PDF + Testing Engine

$52.8

$175.99

3 Months Free Update

  • Exam Name: Commercial Contracting
  • Last Update: Dec 4, 2025
  • Questions and Answers: 233
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

L4M3 Engine

$39.6

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included