Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?
A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?
A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.
Which approach will better cope with the requirements’ volatility?
A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?
A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.
At this point, the business analyst should first:
When a change request is received, the business analyst is responsible for:
A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.
What should the business analyst do to ensure that the business need can be validated?
Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.
Which type of elicitation technique did the business analyst use in this instance?
A company is developing a new product for a customer and is required to verify and validate the product against the customer's acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer
does not believe that the product meets the requirements.
This occurred because the customer's acceptance test plan:
Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:
What is a standardized, effective, and efficient way to manage changes to project documentation?
After a project was delivered, the business analyst learns of a project objective with no associated requirement. What would have helped determine this issue before delivery?
A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?
A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?
While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis
favors a custom-developed solution, either built internally or using contract labor.
To prepare the recommendation, what should the business analyst do?
A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.
Which next step should the business analyst take?
What should be done to ensure that the product design meets the stated requirements?
The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.
Which project artifact could the test team review to help identify acceptance criteria?
Two weeks prior to the delivery date, a customer changes the business requirements. What should the business analyst do?
The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.
What should the team do to reduce the risk of rework?
The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?
A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
A business analyst has been assigned to Project Y. After a requirements gathering session, the project manager asks the business analyst to identify which requirements would be considered in scope and out of scope, based on the business need.
What document should the business analyst use to determine the relationship of the requirement to the business need?
The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.
Which decision role was used?
Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?
A business analyst is working on a project's acceptance criteria. In an early collaboration with the company's stakeholders, the business analyst identified several user groups within the company: "Purchaser," "Shipper," "Customer," and "Agent." These user groups
categorize stakeholders with similar needs and create a detailed narrative.
Which technique did the business analyst use for evaluating the solution's acceptance criteria?
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:
For a large, highly complex project with significant risk, which elicitation technique should be used to analyze input to and output from the product?
Last year, a company registered a high number of complaints about its customer service. Which of the following tools or techniques can help to identify the high-priority changes needed to improve that service?
The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred. The project manager has requested that the business analyst provide a list of rejected and deferred requirements.
What should the business analyst have done to complete this request?
A key component of the business analyst's role during acceptance testing is to:
A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.
Which technique should be followed?
A business analyst captures an application's current limitations and consults with end users to identify new features for the next version.
What can be used to analyze this information and determine project scope?
Which of the following best describes the function of the requirements baseline?
A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.
What would be the most viable technique to use in this scenario?
The document that defines the process for managing requirements revisions is the:
A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?
A major stakeholder of a project is surprised to learn that a particular requirement was not implemented during the latest launch.
The business analyst tells the stakeholder that the requirement status was changed to "deferred ”
What could have prevented the stakeholder from being surprised about the status change?
Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?
Which tool is the most appropriate to aid in development of measurable and actionable requirements for a new project?
A project team has been assembled to streamline accounts payable processes in all divisions of the company. As part of the planning activities, the business analyst is working to identify stakeholders.
Which of the following techniques would the business analyst use to identify stakeholders?
A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?
A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
Which technique should the business analyst use to investigate the problem?
During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.
Which corrective action should the business analyst take?
After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides
enough information to check if the requirement has been met.
Which of the following would work best in this case?
A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project: the ordering process takes too long and often ends in incorrect orders.
What step should the business analyst take next?
A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.
What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will
need to have a discussion about the budget?
When managing a product backlog, which statement best describes how to determine the value of backlog items?
A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new
functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create
project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?
A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.
Which technique or tool should be used?