Which of the following individual should respond to the risk with the preplanned risk response?
You are the program manager for your organization. Part of your role as the program manager is to train John, a new program manager, on the program processes within a program. John is confused as to when the program team can be acquired in the program management lifecycle. When will the program team be acquired for a program?
You are the program manager for your organization. You and your program team have been creating and transferring the program benefits to operations as feasible in your program execution. The process of delivering the program's benefits describes what process in program management?
A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program.
As a result, the program manager must do which of the following?
During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.
Which will provide the greatest value to clarify stakeholder perceptions?
After a company's senior executive management meeting, the CEO issues a mandate to automate a new- client on-boarding process that would effectively eliminate the current, manual, paper-based process. The assigned program sponsor selects a program manager.
Both the program sponsor and the program manager must ensure that the program charter contains which of the following?
You are the program manager for your company and are monitoring and controlling several aspects of your program. You want to make certain that you're including all areas that need to be monitored and controlled. Which one of the following is not something you'll have to monitor and control as a program manager?
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement. A tolerance range is set.
If the tolerance range is too narrow on a program, what effect will multiple minor changes have on the program?
A key stakeholder’s requirement contradicts the organization’s strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement.
What should the program manager do first?
Which of the following can be used to help you or other project managers on future projects?
A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.
What should the program manager do to address these key stakeholders' concerns?
A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results?
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
You are the program manager for the NHQ Program. Your program has a budget of
$4,500,000 and has lasted for two years. Your program has just completed its final
deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?
Which of the following statements is the most accurate when it comes to program change requests for the program scope?
Which of the following can be an effective tool during quality control to help determine the how the problem occurred?
A program manager needs to establish direction and identify the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined, assessed, and documented.
Which document will be created to support this activity?
Which of the following is responsible to sign off on the closure documents of a project?
You are the program manager of the YGH Program. A vendor has recently completed his contracted work for your program. You agree that the vendor has completed the procured work so what document should you and the vendors now sign?
In a program's definition phase, a program manager in country A is assigned to expand a restaurant chain into country B. The program manager creates the program team by identifying the required project management resources.
Which of the following represents an initial step needed to evaluate available resources that are aligned with the program's needs?
Communication is large percentage of program execution as the program manager must communicate with the appropriate stakeholders. In larger programs face-to-face communication is not always possible. When emails are used what verbal aspect of communication is lost?
Hal is the program manager for his organization. He would like your organization to provide his program with 4 tons of pea gravel for a construction project in his program. Hal send you a statement of work and an IFB. What document should you provide to Hal?
If a risk has a probability of 60 percent and an impact of -$57,000 what will the expected monetary value of the risk event be?
Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?
Which of the following statements are true regarding program scope changes? (Choose three.)
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
Which of the following documents is described in the statement below?
"It is a type of procurement document used to request proposals from prospective sellers of products or services."
You are the program manager for your organization. You have proposed a program that will cost $750,000
and will last for four years. Management is concerned with the cost of the program in relation to the return your
program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?
All of the following are resources that you will need to monitor and control in a program environment except for which one?
Julie is the program manager of the NHQ Program for her organization and she believes the program is now complete. Julie is closing her program, and she's working with her program sponsor to review the program's deliverables and benefits. Janet, the program sponsor, is very pleased with the program and agrees that the program has met the program scope. What should Julie and the program sponsor do next?
After taking over a program, a program manager reviews the program’s status and discovers that stakeholders do not know how the program is performing in relation to schedule and costs. The program manager establishes earned value (EV) metrics and determines that the program has a budget of US$2.1 million, is three months into a nine-month timeline, and the planned value (PV) at the three-month point should be US$320,000. The program has spent US$350,000 and the EV is US$340,000.
Based on this information, the program manager determines which of the following?
You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?
The program manager defines the program objectives, requirements, and develops a high-level road map.
To ensure program alignment with the enterprise strategic plan, the program manager should work with which of the following?
A software deployment program for a multinational organization requires the engagement of subcontractors. During the program planning phase, the contracts manager informs the program manager that the primary subcontractor's agreement includes incentives that would potentially conflict with program objectives.
What should the program manager do first?
Molly is the program manager for her organization and she is creating a program plan that defines the benefits of the program and how her program and team will create the benefits for the organization. What plan is Molly creating in this scenario?
A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated, only 60 percent has been achieved.
What should the program manager do to ensure benefits realization?
A component project of a program is completed, and will provide the intended incremental benefits.
How should the program manager proceed with the component transition?
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?
An organization supports both programs and projects for various industries. What is a portfolio?
A global financial system is being delivered by the program team to allow access from anywhere in the world. Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted to validate compliance with this new regulation. This event, which was not anticipated at this phase of the program, will generate additional work for the program team. This effort is not included in the current program roadmap and benefits delivery plan.
What immediate actions should the program manager take?
The chief executive officer (CEO) informs the program manager that the delivery date for project A must be compressed by two months to accommodate market needs. Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?
You are the program manager of the GHY Program. Your program team has identified a risk dealing with the materials you will be using in the program. It is possible that if the materials are not installed properly they will cause serious damage in future phases of the program. Your team has recommended additional training and a consultant to help the team members install the material accurately to reduce the likelihood of the risk event. You agree and the team executes the risk response. What type of risk response have you implemented in this situation?
You are the program manager of the OFE Program. You are working with your program team and project managers to ensure that there is consistency in the execution of the program plan. You stress that the work has been planned and now the team must accurately complete the work. You want to ensure that the work is done correctly the first time in the program. What type of process are you stressing to your program team and project managers?
Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?
You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?
Which of the following plans should a project manager implement if a selected risk strategy fails to be fully effective?
You are the program manager for your organization and are about to execute your procurement management plan. You need to procure materials for your program and you want only the vendor to provide you with a price for the goods you need to procure. What type of a document should you provide to the vendor in this
scenario?
You are the program manager of the NQA Program. In this program you're planning which contract types you'll allow into the program and which ones you will not. One contract type you won't accept is the cost plus percentage of cost contract. Which of the following is a valid reason you would not allow this contract type into your program?
Which one of the following is NOT a component of the risk monitoring and controlling process?
Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?
The program charter for a new, five-component program has been approved.
What should the program manager use to communicate the program's intended direction and the linkage between organizational strategies and planned work?
You are a program manager for a large construction program. You need to ensure that the projects in the program are in accordance with the schedule. You are tracking start and finish dates for them. Which of the following processes are you on?
An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts, the program manager discovers the program may be shut down due to lack of funding.
To ensure continued funding for the program, what should the program manager do next?
You are the program manager for your organization and are working with your team to identify stakeholders in the program. Where should the identified stakeholders and their information be recorded?
Small changes that bypass the organization's change control procedures are called.
Donna is the project manager for her organization. She is preparing a plan to manage changes to the project
should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?
Which of the following risk identification techniques is described in the statement below?
"It is used to gather information where participants don't know each other nor do they have to be present at the same location."
You are the program manager for your organization. Management is considering a new program but they are worried about the program risks that may affect the program success. You know that there are three positive risks responses and three negative risk responses that each risk can have. Management asks you which risk response would be most appropriate for a large risk event if they wanted to hire a third-party to own the risk event for the program. What risk event is most appropriate?
You are the program manager for your company and evaluating the sellers to determine the seller to buy from. In your analysis you've created a histogram to display the pros and cons for each seller. You've created five categories of interest and assigned values to each category for each vendor. Your five categories are:
Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?
All of the following are resources that need to be monitored and controlled except for which one?
A company CEO issues a mandate to automate a new-client onboarding process to replace manual and paper-based procedures. After the program sponsor and program manager obtain formal acceptance of the program charter, what should be done next?
Part of program management is to understand how the communication model works in a program. The program manager must be able to effectively communicate with the program team and stakeholders. What component of the communication model is responsible for carrying the message?
Which of the following documents describes the details for each component in the WBS?
Complete the following phrase about quality management: Quality isinto a program, notinto a program.
A program manager is identifying and verifying risks as outlined in the risk management plan.
The results will be recorded in which of the following?
The program manager plans to address a negative cost variance generating a red flag in the program management status report.
What should the program manager do?
Holly is the program manager for her program. She is creating with her team a plan that will address how the program team will achieve program goals based on who the program will need to interact with in the program. This plan should define all of the people, groups, and other entities the program needs to interact with in order to move the program forward. On what plan is Holly working?
Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?
You are the program manager for your program and are creating a communications management plan. Management wants you to address the type of communications based on the number of communication channels you'll have within the program. Currently there are 345 stakeholders in your program but next week you'll have 387 stakeholders. How many more communication channels will you have next week in your program?
A two-year program is coming to an end. Many of the initial governance board members have moved from their current posts or left the company. Several new members have joined, but have a short association with the program, which changes the board’s expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change
request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?
An experienced program manager is leading a development program in a new company. While reviewing company procedures for formulating a program, they discover there is no company practice for managing key suppliers.
What should the program manager do first to obtain program approval?
Paul is the program manager for his company. He along with his team is working on the Monitor and Control
Program Changes process. The process will need several inputs. Which one of the following items is NOT an input to the Monitor and Control Program Changes process in the program management?
Which of the following represents the duration of activities against a calendar?
During the selection of source process, you assign certain points towards various categories to judge the vendors. Which type of source selection process is it?
An ice cream company wants to introduce a new flavor to a new market. The executive sponsor requests a sampling for the test market and the sample group provides negative feedback. As this type of program had previously been conducted by the company, the program manager QUESTION NO:s whether similar results were experienced during testing.
What should the program manager do next?
You are the program manager for your company and management wants you to identify how you'll make decisions in the program planning processes. What program management document should serve as the baseline for all future program decisions?
Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality assurance for a project within your program?
A program is developing a next-generation product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet.
What activity should the program manager perform next?
You are hosting a meeting with all of the vendors that have received a copy of your statement of work. In this meeting, you'll be discussing the statement of work, clarifying the details, and answering any QUESTION NO:s the vendors may have about the project. What is this meeting called?
What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?
Hans is the program manager for his organization. His current project has seven constituent projects that each will create deliverables for the organization. Who is responsible for the project deliverables in this scenario?
A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end. What should be completed first to close all appropriate contracts?
You are the program manager for your organization. One of the projects within your program is to install 15,000 light fixtures throughout your organization's corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?
You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager,
create at this time?
You are the program manager for your organization. Your program will create a new condominium in your community. There are several concerns about the condos including the timing, the local economy, the environment, and the proposed schedule. You and your team are creating the program management plan to address these concerns along with identifying the constituent projects that will build the structures and deliverables. What group will need to review your program plan to approve the plan before you may proceed in the work?
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
You are a program manager for an environmental program. The program involves installation of windmill across the country. During execution of the project, a stakeholder raises a change request to add an additional module with the existing installation. The program governance board has approved the change request. Which of the following is true regarding this scenario?
A program manager is responsible for constructing a US$50 million building. Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1.5 years. However, heavy demand for steel is causing price increases and delivery delays. If this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1.25 years.
What is the expected time of delivery?
Tom is the program manager for his organization. He has to balance the resources he'll be using in the program with the demand for operations to use the same resources. What program document can Tom reference to determine the availability of certain program resources, such as application developers, engineers, and technical writers?
Which of the following documents contain a list of all problems, unfavorable events, or situations that occurred so far in the program?
A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?
Andy is the program manager of the HQN Program. This program is nearing its completion and there is still
$25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?
On which of the following documents you work throughout the risk management processes?
Which of the following is not a template element that is designed to make the project more effective?
You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?
You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?
A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country’s branches by the end of the fiscal year. Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support
the regulation, as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured.
What should the program manager do to address the risk?
Which of the following shows the ratio between a task's budgeted and actual costs?
You are the program manager of the NHQ Program for your organization. Your program has 14 constituent projects that are all creating benefits and deliverables for your program. You have recently terminated the GHW Project in your program because you've made trade-offs with other program projects and the deliverables of the GHW Project are no longer affordable. What project management activity should happen in the GHW Project?
Harriet is the program manager of a large program that has a high profile and visibility in her organization. Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?
June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components’ strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools.
Which of the following must be addressed?
A program manager initiates a new global program to create a higher level of protection for a company's intellectual property. The company exhibits a relaxed culture and environment, and is intolerant of processes to the point of being considered process-adverse. However, the company's culture is tolerant of long-term program activities, provided there is continuous progress on improving the protection of its intellectual property. Expectations for rapid progress are low.
What should the program manager do next?
A program manager is concerned because several change requests in a component project are causing delays to the program's work package milestones. There are insufficient skilled resources within the component project to complete both the change requests and the milestone tasks.
What should the program manager do next to address this risk?
A new program manager joins a multi-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization.
At the next stakeholder meeting, what should the program manager present to address their concerns?
You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?
A program manager has four projects pending approval. Senior management asks the program manager to identify a project for potential elimination based on the return on investment. The program manager has the following information to guide and support the decision:
Which project should the program manager select to be cancelled?
Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?
You are the program manager for your organization. A new program is about to initiated and Marcy, your assistant, asks you about the themes that all new programs must map to. All of the following are themes that you can discuss with Marcy except for which one is not a program theme?
You have created a control chart for a repeatable process in your program. You have discovered that the seven most recent measurements are all on the positive side of the mean in your control chart. What is this phenomenon called?
You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?
A new program is being initiated for the HNQ Organization. The program manager is working with the
business analyst and management to define several attributes of the program. All of the following are identified during program initiation except for which one?
Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.
A program manager is leading a program to transform an organization's sales and customer service operations by introducing a new customer relationship management (CRM) solution. As the program progresses, the sponsor and other stakeholders are satisfied with the pace of the program's performance.
A stakeholder from the sales department now requests a new feature to integrate the CRM platform with another application. The program manager advises that this is out of scope, as it will require analysis and development and be a project on its own. The program manager then requests additional funding via the formal change management process and the new scope is approved.
What should the program manager do next?
A program manager notices that one project manager tends to withdraw during important team discussions to avoid conflict.
What technique could the program manager use to gain more input from this project manager?
An R&D group director approves a major program’s charter. Although the director has a high level of understanding of the program’s scope, they are unsure of how the program manager can be successful in delivering the program’s commitments.
What should the program manager do to align stakeholders with planning and monitoring the program’s progress?
You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?
A program manager assigns project managers to five component projects and continues to develop the program team.
Which of the following represents the program manager's strategy?
A program manager joins a team to fix a troubled enterprise-wide customer relationship management (CRM) system. Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository for similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity.
What should the program manager do with the knowledge gained from this activity?
Terri is the program manager for her organization and she's working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope. Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?
Two project managers in your program, Marcy and Mary, are not agreeing with the scheduling of project resources and they have asked for your help to determine the resolution. They are refusing to speak with each other and each is telling you that the other person is scheduling project resources for the project that are already scheduled to complete the work. In the communication model, what component represents the disagreement of these two project managers and their refusal to speak with each other about a resolution?
Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B’s program manager has just advised that program B has been closed.
What should program A’s program manager update and review first with the stakeholders?