Weekend Special Sale - 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 75special

Practice Free PRINCE2-7-Practitioner PRINCE2 Project Management Practitioner (Version 7) Exam Questions Answers With Explanation

We at Crack4sure are committed to giving students who are preparing for the PRINCE2 PRINCE2-7-Practitioner Exam the most current and reliable questions . To help people study, we've made some of our PRINCE2 Project Management Practitioner (Version 7) exam materials available for free to everyone. You can take the Free PRINCE2-7-Practitioner Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.

Question # 6

The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.

Under which heading of the change management approach should this requirement be recorded?

A.

State characteristics

B.

Enabling activities

C.

Resources

D.

Responsibilities

Question # 7

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board

B.

Yes, because the project board should collect and review work-package progress directly from each delivery team

C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances

D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages

Question # 8

PROCESSES

During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.

During which activity should this clarification of the mandate and business expectations take place?

A.

Appoint the project management team

B.

Appoint the project executive and manager

C.

Select the project approach

D.

Plan the initiation stage

Question # 9

During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.

Is this an appropriate application of the ‘manage by exception’ principle, and why?

A.

Yes, because establishing a minimum and a preferred number of charging bays creates a defined scope tolerance that enables the design team to work within an agreed range without needing to escalate every individual design decision

B.

Yes, because specifying a minimum and a preferred number of charging bays constitutes a quality tolerance that the design team must meet within the agreed work package

C.

No, because the precise number of electric charging bays to be included should be fully specified in the product description for the underground car park rather than treated as a tolerance

D.

No, because the project board should approve the precise number of charging spaces rather than delegate a permissible range to the design team

Question # 10

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

Question # 11

During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.

Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

A.

Yes, because standardized portfolio role descriptions give every project manager a consistent and well-understood baseline of responsibilities, removing the need for individual discussion

B.

Yes, because it is the project executive’s responsibility to appoint the project manager and establish their responsibilities as part of the ‘starting up a project’ process

C.

No, because each project manager must have a clear understanding of their own individual responsibilities and formally accept those responsibilities before commencing project work

D.

No, because it is the portfolio manager’s role, rather than the project executive’s, to define the project manager’s responsibilities for projects within the portfolio

Question # 12

During stage 4, the business identifies a need for additional funding to extend LouisShopping advertising beyond project closure so that more businesses are attracted to Louistown. The project board must communicate the business need and resulting direction to the project team.

Which role should lead this business-related ongoing direction?

A.

Project executive

B.

Project manager

C.

Project assurance

D.

Senior user

Question # 13

A high-level requirement that the design should be consistent with its surroundings was recorded during ‘starting up a project’. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.

Which management product should be updated with this information?

A.

Project product description

B.

Work package

C.

Product flow diagram

D.

Project plan

Question # 14

The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.

Is this an appropriate approach to leading successful change, and why?

A.

Yes, because restricting the CTO’s involvement would protect the project’s reputation from untested proposals

B.

Yes, because influential stakeholders should be excluded when their preferred solutions create delivery uncertainty

C.

No, because the project manager should record the technological concerns only as risks requiring formal responses

D.

No, because the CTO should remain engaged so that their influence can support adoption across the organizational ecosystem

Question # 15

During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.

Is this an appropriate use of the ‘give ongoing direction’ activity, and why?

A.

Yes, because a project board member may raise concerns and provide ongoing direction within the authority delegated to the board

B.

Yes, because the senior user has an obligation to formally approve key specialist products produced during stages 2 and 3 as a standard action within the ‘give ongoing direction’ activity

C.

No, because the ‘give ongoing direction’ activity is only triggered when the project manager proactively requests a review by the project board, not when individual board members identify concerns independently

D.

No, because the Heritage Director should first seek the agreement of the full project board before raising individual concerns, to ensure a unified project board position is presented to the project manager

Question # 16

Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.

During which ‘managing a stage boundary’ activity should this recommendation be developed?

A.

Update the project plan

B.

Prepare the next stage plan

C.

Evaluate the stage

D.

Request the next stage

PRINCE2-7-Practitioner PDF

$27.5

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PRINCE2-7-Practitioner PDF + Testing Engine

$44

$175.99

3 Months Free Update

  • Exam Name: PRINCE2 Project Management Practitioner (Version 7)
  • Last Update: Oct 4, 2026
  • Questions and Answers: 56
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PRINCE2-7-Practitioner Engine

$33

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included