We at Crack4sure are committed to giving students who are preparing for the PRINCE2 PRINCE2-7-Practitioner Exam the most current and reliable questions . To help people study, we've made some of our PRINCE2 Project Management Practitioner (Version 7) exam materials available for free to everyone. You can take the Free PRINCE2-7-Practitioner Practice Test as many times as you want. The answers to the practice questions are given, and each answer is explained.
The target state for LouisShopping requires the car park to be monitored continuously, 24 hours a day and seven days a week, as an ongoing safety routine.
Under which heading of the change management approach should this requirement be recorded?
At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.
Is this an appropriate application of the progress practice, and why?
PROCESSES
During the ‘starting up a project’ process, the Head of the Portfolio Office explains to the prospective project executive that LouisShopping is strategically important to the LOB portfolio, must support increased business opportunities and is expected to open by the end of financial year three.
During which activity should this clarification of the mandate and business expectations take place?
During stage 2, the project board agrees that the underground car park should contain 15 rapid-charging spaces, with a scope tolerance permitting delivery of no fewer than 10 spaces. The project manager includes this tolerance in the relevant work package agreed with the team manager.
Is this an appropriate application of the ‘manage by exception’ principle, and why?
During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.
Is this an appropriate application of the business case practice, and why?
During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.
Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?
During stage 4, the business identifies a need for additional funding to extend LouisShopping advertising beyond project closure so that more businesses are attracted to Louistown. The project board must communicate the business need and resulting direction to the project team.
Which role should lead this business-related ongoing direction?
A high-level requirement that the design should be consistent with its surroundings was recorded during ‘starting up a project’. During initiation, the project manager works with Council members, residents, retailers and BuildyBrick to clarify the required design characteristics and define measurable acceptance criteria.
Which management product should be updated with this information?
The Chief Technology Officer is an influential stakeholder who strongly supports several unproven technologies for the shopping centre. Concerned about delivery risk and reputation, the project executive asks the project manager to limit the CTO’s contact with the project team and other stakeholders.
Is this an appropriate approach to leading successful change, and why?
During stage 2, the Heritage Director, acting as senior user, reviews the design and raises a concern that the previously requested heritage trail has not been addressed.
Is this an appropriate use of the ‘give ongoing direction’ activity, and why?
Near the end of stage 2, the supplier planned for the utilities and systems work becomes financially unstable and a replacement subcontractor is selected for stage 3. The project manager recommends that the replacement subcontractor’s account manager should represent the supplier interest as senior supplier.
During which ‘managing a stage boundary’ activity should this recommendation be developed?