Summer Special - 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: c4sdisc65

PSM-II PDF

$38.5

$109.99

3 Months Free Update

  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions

PSM-II PDF + Testing Engine

$61.6

$175.99

3 Months Free Update

  • Exam Name: Professional Scrum Master II
  • Last Update: Oct 16, 2025
  • Questions and Answers: 74
  • Free Real Questions Demo
  • Recommended by Industry Experts
  • Best Economical Package
  • Immediate Access

PSM-II Engine

$46.2

$131.99

3 Months Free Update

  • Best Testing Engine
  • One Click installation
  • Recommended by Teachers
  • Easy to use
  • 3 Modes of Learning
  • State of Art Technology
  • 100% Real Questions included

PSM-II Practice Exam Questions with Answers Professional Scrum Master II Certification

Question # 6

A Scrum Team is struggling over the fact that not all Developers work full time and that other Developers regularly work from home. To solve the difficulties in aligning daily, at the Sprint Retrospective two Developers suggest having the Daily Scrum every three days, when everyone is in the office.

What would be three key concerns if the frequency of the Daily Scrum were to be lowered?

(choose the best three answers)

A.

Opportunities to inspect and adapt the Sprint Backlog are reduced. Re-aligning is bound to become even more difficult.

B.

The Scrum Master loses the ability to update the Gantt chart properly, there by obscuring the Scrum Master's tracking of Sprint progress.

C.

Less progress information will be shared, causing the plan for the Sprint to

become inaccurate and transparency over progress toward the Sprint Goal is

reduced.

D.

Impediments are raised and resolved more slowly which might impact

productivity and progress.

E.

The Product Owner cannot accurately report progress about the state of the

forecasted work to the stakeholders.

Full Access
Question # 7

After some small experiments with Scrum, your company decides to do a complete project with Scrum. As Scrum Master; you have been invited to the "project kick-off meeting" with IT and product management

The Product Owner asks how many Sprints IT will need to first figure out architecture and infrastructure issues. What are two options to explain how such work is managed using Scrum?

(choose the best two answers)

A.

You explain that product management should not worry about such typical IT work. You inform them that you will assure that the team members reach out to the right people within the IT organization when needed During each Sprint Planning event they will keep the Product Owner updated about the additional effort it will take for that Sprint. That effort will come on top of the effort for the forecasted functional development.

B.

You explain that technical risks are best controlled when architecture and infrastructure emerge alongside the development of functionality. The additional advantage is that business value is created faster and sooner.

C.

You thank product management for understanding that these efforts indeed require effort and budget You confirm that architecture and infrastructure are best addressed before starting Scrum, but that the exact budget is difficult to calculate upfront You say you will organize this work in timeboxed Sprints of no more than 30 days to limit risk and be transparent toward product management on the actual progress.

D.

You educate the Product Owner to add this work to the Product Backlog to uphold transparency. Ask the Developers to plan work during the first several Sprints to estimate these items, while also creating some business functionality in these early Sprints

Full Access
Question # 8

A Scrum Master colleague of yours wants some guidance on what to do in the following situation. During the Daily Scrum, one Scrum Team member, who is a key central figure in the organization, drags on and on about things which actually are interesting but not relevant for the Daily Scrum, day after day. What are two suggestions you would offer to your colleague?

(choose the best two answers)

A.

You suggest taking the person aside and asking them what they believe the key outcomes are for the Daily Scrum. Effectively coaching them to help create focus during the Daily Scrum.

B.

You contact the team member's Line Manager and raise this as an impediment to the Manager, and ask that they resolve this matter.

C.

You suggest using a timer, to limit the time each person can speak at the Daily Scrum.

D.

You suggest passing a token around. The person holding the token has the floor to speak for an allotted amount of time.

E.

You suggest coaching the Developers to help them find a way to solve the problem, and own the solution.

Full Access
Question # 9

You are a Scrum Master helping to establish five Scrum Teams that will be building a product.

You discuss with them the high level of integration that the product Increment will require by the end of their first Sprint. It is a highly anticipated product, both by consumers and by the organization. Of the options raised by the future Scrum Team members, which option do you encourage?

(choose the best answer)

A.

Each Scrum Team provides a separate Increment with the functionality added by the individual team. The Sprint Review is used to identify the work needed to integrate with the other Scrum Teams. This work is then added to the Product Backlog.

B.

Each Scrum Team delivers done Increments in its own area of responsibility. Upon functional acceptance at the Sprint Review, the code is isolated for future stabilization. The release date is adjusted according to the expected work and time of such integration phase.

C.

In the first Sprint, integration is less important. The goal is to deliver business value. Functionality that is not integrated with the work of other Scrum Teams by the end of a Sprint is still reviewed to assess its potential business value. It can still be released at the Product Owner's discretion, and silent consent of the stakeholders.

D.

All Scrum Teams agree on a shared Definition of Done that describes all work needed to deliver an Increment that is the integrated sum of the work from all Scrum Teams.

Full Access
Question # 10

A multi-national company is using Scrum for product development of their five major products.

What alternatives should the company consider to decide how many Product Owners are needed for these five products?

(choose the best two answers)

A.

There is one Product Owner for each product (five in total). Each Product Owner may delegate to others for specific value, capabilities, and functionality within their product. The five Product Owners share and align work via Product

Backlog.

B.

There are as many Product Owners as needed to analyze, document, and

explain expectations and requirements with all Scrum Teams.

C.

There is one Product Owner for all five products. This person may not delegate work to others for specific value, capabilities, and functionality, given these are all the Product Owner's individual responsibility.

D.

There is one Product Owner responsible for all five products. This person may

delegate work to others for specific value, capabilities, and functionality within each product to scale their accountability.

Full Access
Question # 11

You are a Scrum Master employed by the IT department. The IT manager considers adopting Scrum tor a new project He wonders however, what the value is in having all team members attend this meeting called "Daily Scrum" every day. The organization already has its employees attending so many mandatory meetings.

What are two outcomes of the Daily Scrum you inform him about, to express the importance of the Daily Scrum?

(choose the best two answers)

A.

During the Daily Scrum the Developers will bring up problems that are hindering their progress, and tor which they nave no means to resolve, this provides an opportunity to resolve those impediments.

B.

The Daily Scrum serves tor the Developers to report to you, as a Scrum Master, all updates on the tasks to the Sprint, as registered in the Sprint Backlog. You can then use the team's updates to plan their work tor the next day, making sure that every team member is assigned the right tasks.

C.

Through the snort, daily alignment of the Daily Scrum the Developers build and improve a shared understanding of the most important work to be undertaken in the next 24 hours, to achieve the best possible progress toward the Sprint Goal. This daily opportunity to inspect and adapt Will enable the Developers to tackle any unforeseen circumstances that might otherwise disrupt the team's progress.

D.

During the Daily Scrum, the Developers need to update the Scrum board with

their current status and progress, at a task level. This is crucial to ensure that the IT manager can go up to the room at any time and view the team's actual

progress.

E.

The Developers will produce a status report indicating what each individual has done the past working day, and now much time that has taken. The accumulated

reports will support discussing how the Sprint went at the Sprint Review

meeting. It will provide detailed insights into the accuracy of estimates versus

actual time spent, which can be used to create better estimates at the

subsequent Sprint Planning meeting.

Full Access
Question # 12

Self-management is more effective when it happens within boundaries.

Select two relevant boundaries for self-management provided by the Scrum framework.

(choose the best two answers)

A.

Timeboxing work to allow for frequent inspection.

B.

Clearly defining sub-responsibilities and handovers within the Scrum Team.

C.

Creating a valuable and useful Increment by the end of each Sprint.

D.

Having an even number of members in a Scrum Team to be able to do pair programming and be more productive.

Full Access
Question # 13

During a Sprint Review, the Product Owner determines that she is going to release thecurrentIncrement to production. The stakeholders ask to stop the Sprint to react more quickly to the user feedback that is expected after this release. The Product Owner prefers to continue the Sprint to make progress with the next release. You facilitate a discussion on how to proceed.

What are two acceptable results of this discussion?

(choose the best two answers)

A.

Continue sprinting but shorten the Sprint length to allow for shorter feedback loops.

B.

Stop sprinting and let the Developers work on new customer requests as they

arise.

C.

Continue sprinting and include the customer feedback in the Product Backlog.

D.

Continue sprinting but allow customer feedback to change the Sprint Goal within the Sprint.

Full Access
Question # 14

Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product The stakeholder is unhappy with the slow performance, a complaint that the Product Owner agreeswithAs the Scrum Master how will you move this forward?

(choose the best answer)

A.

Encourage the Product Owner to bring the performance concerns to the rest of the Scrum Team and work together to improve the Definition of Done

B.

Wait to bring this up in the next Sprint Retrospective as this is the appropriate time for the Developers to re-consider the Definition of Done.

C.

Bring the concern to the quality assurance members of the Scrum Team and ask them to improve how the system is tested.

D.

Explain to the Product Owner that it is up to the Developers to decide on acceptable performance standards as they own the Definition of Done

Full Access
Question # 15

Towards the end of Sprint Planning, the Product Owner and the Developers have not been able to reach a clear, mutual understanding about the highest order Product Backlog items. Because of this, the Developers could not figure out how many Product Backlog items they could forecast for the upcoming Sprint. The Product Owner did make it clear what business objective he is hoping to achieve with this Sprint. Which of the following two actions would you support?

(choose the best two answers)

A.

They discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur.

B.

The team splits up and everybody takes as much time as they need to study the Product Backlog items first. The Product Owner should be available to answer individual questions. The group reconvenes when all team members are better prepared and restart the Sprint Planning meeting before the Sprint can start.

C.

If all agree, they can continue the Sprint Planning meeting as a team past its timebox, until an adequate number of Product Backlog items are well enoughunderstood for the Developers to make a complete forecast. Then start the Sprint.

D.

The Developers forecast the most likely Product Backlog items to meet the business objective and create a Sprint Backlog based on a likely initial design and plan. Once the timebox for the Sprint Planning event is over, they start the Sprint and continue to analyze, decompose, and create additional functionality during the Sprint.

Full Access
Question # 16

Which of the following affect the outcome of a Sprint?

(choose all that apply)

A.

The complexity of the problem being solved.

B.

The complexity of the requirements.

C.

The skills and working relationships of the people on the Scrum Team(s).

Full Access
Question # 17

Five new Scrum Teams have been created to build one product. A few of the Developers ask the Scrum Master who will coordinate the work between the different Scrum Teams. What should the Scrum Master do?

(choose the best answer)

A.

Visit the five Scrum Teams each day to facilitate alignment and synchronization of their Sprint Backlogs.

B.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.

C.

Teach the Product Owner to work with the lead developers on ordering Product

Backlog in a way to avoid too much technical and development overlap during a

Sprint.

D.

Teach them that it is their responsibility to form Scrum Teams with the skills and knowledge to create an Increment by the end of every Sprint.

E.

Advise the teams to reduce interdependence by working in separate branches and organizing a specific Sprint every four development Sprints to manage integration.

Full Access
Question # 18

True or False: Using Scrum ensures that adding more resources to a project proportionally increases the value delivered.

A.

True

B.

False

Full Access
Question # 19

Which two options describe how project budgeting and financial forecasting work in Scrum?

(choose the best two answers)

A.

Scrum does not align with traditional accounting practices. The financial

department needs to be given a fixed cost per Sprint per team.

B.

Several Sprints may be funded as a single release, with the result of each Sprint being releasable product

C.

The only funding is for the run cost (time and materials) of the Scrum Teams, so no budgeting process is needed_

D.

It is ideally revisited as frequently as each Sprint to ensure value is being

delivered for the investment spent.

Full Access
Question # 20

The Developers are waiting for an external supplier to deliver a specific product component that they need to integrate and use. Without that component there will not be enough work in the next Sprint to occupy the full team. They ask their Product Owner to re-order the Product Backlog. The Product Owner asks the Scrum Master for help. What would be good advice for the Product Owner?

(choose the best answer)

A.

Tell the Product Owner that the Product Backlog needs to be re-ordered to maximize utilization of the Developers. It is important to keep productivity high through proper use of the capacity available

B.

Tell the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog. Timeline of the flow might be influenced by such dependencies and require some level of Product Backlog re-ordering

C.

Tell the Product Owner to remove all work involving the external component from the Product Backlog and create a new backlog for it. The work can then be planned in one or more separate Sprints as soon as the component is available.

Full Access
Question # 21

A Scrum Team consists of Developers working from globally distributed locations. Organizing the Scrum events requires conferencing tools that are not easily available within the organization. The Developers propose doing a Daily Scrum only on Tuesdays. Which are the most appropriate responses for their Scrum Master?

(choose the best two answers)

A.

Help the Developers understand that lowering the frequency of communication will only increase the feeling of disconnect between the team members.

B.

Coach the Developers on why a daily frequency is important as an opportunity to update the Sprint Plan and how it helps the team organize work toward achieving the Sprint Goal.

C.

Acknowledge and support this self-managing team's decision

D.

Have the Developers vote to make sure there is consensus within the team

Full Access
Question # 22

Scrum Master is a management position because the Scrum Master is accountable for the following three management activities:

(choose the best three answers)

A.

Reporting on the performance of a team.

B.

Managing the Scrum process.

C.

Managing the project plan and the project deliverables.

D.

The way Scrum is understood and enacted within the organization.

E.

Removing organizational impediments that limit the team's progress and

productivity.

F.

Managing the capacity and utilization of the Developers.

Full Access